Civil & Structural Inspector
• Earthwork base inspection: Sub Grade Acceptance and Release for Backfill
• Earthwork monitor: Review QC reports from 3rd party testing firm and preform field spot checks.
• Survey review: Review all survey as-built for accuracy and acceptability to job specs.
• Concrete Pre and Post Pour inspections.
• Hot/Cold Curing monitoring
• ACI Mass Concrete Pours
• Site inspections for bolting complete as per torque wrench and/or turn of the nut method CSA S16, CWB 178.2 CSA W59 and W47.1
• Weld Mapping