Duties carried out for Buhasa pipeline project & OAG PKG.3 for GASCO, including but not limited:
Expediting of purchase orders including civil, piping, Mechanical, electrical, and instrumentation disciplines.
Material flow control, coordination with inspection & logistic teams.
Operational spare parts for 2-years, building database using clients MAXIMO system, to cover the required spare parts of main equipment and systems during the first couple of years of operation.
Preparing final handover to GASCO for the 2-years operational spare parts.
Preparing spare parts orders, expediting, and arranging for delivery.
Material preliminary checking and validation.
Interface with construction tea...