Stevens Shuttle 2.0
Presenters
Chinonso Oham
Rohan Waghere
Akash Dhotre
Yash Raje
Devaun Armstrong
Agenda
 Stevens Shuttle 1.0
 Problems
 Solution (Stevens Shuttle 2.0)
 Logistics
Current commute to Stevens
Students
come to
the shuttle
stop
Check a
third-
party app
for
estimated
wait time
Shuttle
picks
students
and drives
them to
Stevens
Problems with the current system
 Inefficiency:
 Not enough seats during peak hours
 Unreliable tracking system
 Non-value rides
Solution
 Updated GPS Modules
 Handshake and Shuttle Capacity
 Generic Model
Operation & Limitation
Shuttle Routes
Solution Limitations
 Updates
 Beneficiary Satisfaction
Index
Estimated Fuel Savings
Efficiency
Summary
Parameters Red (6) Green (2) Gray (6) Blue (12)
Potential Save
Value
Total Cost for
NVR/Semester $216.36 $68.34 $227.52 $569.16 $1,081.38
Annual Costs on
NVR $649.08 $205.02 $682.56 $1,707.48 $3,244.14
% Costs for
NVR/Annually 15.00% 5.00% 15.00% 30.00% 17.38%
Stevens Shuttle 2.0
Total
Costs/Semester $1,442.40 $1,366.80 $1,516.80 $1,897.20 $6,223.20
Annual Costs $4,327.20 $4,100.40 $4,550.40 $5,691.60 $18,669.60
Current Fuel Costs
NVR  Non-Value Rides
Proposed Schedule
 Approx 123 days
 Latest Finish: 131 days
 Total slack time: 8 days
(131-123= 8 days)
Proposed Schedule
Launch first
survey
Survey results
Begin app
development
Register app on
Google Play/App
Store
Beta test
Advertise the app
Establish
maintenance
schedule for app
Calculate BSI
Proposed Schedule
 Each stage will be monitored to
ensure that the project is on track.
 Each team member is responsible for
certain activities
 Communication and changes will
be on to the project lead.
 The updates will be distributed in the
progress reports that will be sent out
on a bi-weekly basis.
Proposed Budget
 Activity costs: $17,805
 Material costs: $150
 Allowance for extra
costs: $1,800
 Total budget: $19,755
Risks facing Stevens Shuttle 2.0
Risk Impact
Not enough students respond to
the surveys
Smaller response sample,
responses not reflective of the
whole population
App development takes longer
than projected schedule
Milestones not delivered on time,
delayed project completion
Budget doesnt cover the entire
project
App quality may be compromised
Risks facing Stevens Shuttle 2.0
Risk Impact
Inaccuracy in shuttle arrival times
shown in the app
Passengers delayed
Hacks/cyber attacks App not working as intended,
accounts compromised
Unexpected shutdown in the app Students unable to notify drivers of
their locations / track locations of
shuttles
Assumptions
 Budget is estimated correctly
 Estimates for schedule and milestones are tangible
 Facilities/resources we need to work will be available when
required
 Risks, their severities, and mitigation plans have been properly
defined.
Assumptions
 We would have a sufficient sample in the surveys to calculate
the Beneficiary Satisfaction Index
 The solution proposed will save operational costs involved in
shuttle services
 The shuttles use an average of 17 miles per gallon
 Requirements are clearly understood by the software
development team
Stakeholders:
 Project Team
 Students
 Administration:
 President,
 Software developer,
 Shuttle riders
Thank you!

More Related Content

Final Presentation Stevens Shuttle 2.0

  • 1. Stevens Shuttle 2.0 Presenters Chinonso Oham Rohan Waghere Akash Dhotre Yash Raje Devaun Armstrong
  • 2. Agenda Stevens Shuttle 1.0 Problems Solution (Stevens Shuttle 2.0) Logistics
  • 3. Current commute to Stevens Students come to the shuttle stop Check a third- party app for estimated wait time Shuttle picks students and drives them to Stevens
  • 4. Problems with the current system Inefficiency: Not enough seats during peak hours Unreliable tracking system Non-value rides
  • 5. Solution Updated GPS Modules Handshake and Shuttle Capacity Generic Model
  • 6. Operation & Limitation Shuttle Routes Solution Limitations Updates Beneficiary Satisfaction Index
  • 7. Estimated Fuel Savings Efficiency Summary Parameters Red (6) Green (2) Gray (6) Blue (12) Potential Save Value Total Cost for NVR/Semester $216.36 $68.34 $227.52 $569.16 $1,081.38 Annual Costs on NVR $649.08 $205.02 $682.56 $1,707.48 $3,244.14 % Costs for NVR/Annually 15.00% 5.00% 15.00% 30.00% 17.38% Stevens Shuttle 2.0 Total Costs/Semester $1,442.40 $1,366.80 $1,516.80 $1,897.20 $6,223.20 Annual Costs $4,327.20 $4,100.40 $4,550.40 $5,691.60 $18,669.60 Current Fuel Costs NVR Non-Value Rides
  • 8. Proposed Schedule Approx 123 days Latest Finish: 131 days Total slack time: 8 days (131-123= 8 days)
  • 9. Proposed Schedule Launch first survey Survey results Begin app development Register app on Google Play/App Store Beta test Advertise the app Establish maintenance schedule for app Calculate BSI
  • 10. Proposed Schedule Each stage will be monitored to ensure that the project is on track. Each team member is responsible for certain activities Communication and changes will be on to the project lead. The updates will be distributed in the progress reports that will be sent out on a bi-weekly basis.
  • 11. Proposed Budget Activity costs: $17,805 Material costs: $150 Allowance for extra costs: $1,800 Total budget: $19,755
  • 12. Risks facing Stevens Shuttle 2.0 Risk Impact Not enough students respond to the surveys Smaller response sample, responses not reflective of the whole population App development takes longer than projected schedule Milestones not delivered on time, delayed project completion Budget doesnt cover the entire project App quality may be compromised
  • 13. Risks facing Stevens Shuttle 2.0 Risk Impact Inaccuracy in shuttle arrival times shown in the app Passengers delayed Hacks/cyber attacks App not working as intended, accounts compromised Unexpected shutdown in the app Students unable to notify drivers of their locations / track locations of shuttles
  • 14. Assumptions Budget is estimated correctly Estimates for schedule and milestones are tangible Facilities/resources we need to work will be available when required Risks, their severities, and mitigation plans have been properly defined.
  • 15. Assumptions We would have a sufficient sample in the surveys to calculate the Beneficiary Satisfaction Index The solution proposed will save operational costs involved in shuttle services The shuttles use an average of 17 miles per gallon Requirements are clearly understood by the software development team
  • 16. Stakeholders: Project Team Students Administration: President, Software developer, Shuttle riders