The document is a quotation from KITS TECHNOLOGIES LTD for the construction of a data center. It provides pricing for various components and work including wall cladding, doors, raised floors, suspended ceilings, lighting, power infrastructure, earthing systems, and lightning protection. The total cost quoted is over 158 million Naira. Payment terms specified are 80% in advance and 20% on delivery, and the price quoted excludes VAT. A 1-year warranty is provided against manufacturing defects.
1 of 3
Download to read offline
More Related Content
Rfq kit
1. March 22, 2013.
The Manager, Solution
KITS TECHNOLOGIES LTD,
Attention: Mr. Muideen .A Jokanola
Dear sir,
RE: QUOTATION FOR DATA CENTER CONSTRUCTION.
S/N DESCRIPTION QTY Unit Price
1WALL CLADDING AND GLASS PARTITIONING
Supply and installation of fire rated gypsum
board wall cladding sheet inclusive of other
i cladding materials 96 modules 15,500 1,488,000.00
Supply and Installation of 10mm thick Fire Rated
ii. Full Glass Partitions. 28 Modules 65,000 1,820,000.00
Supply and Installation of Half Glazed Board
iii Partitions 26 Modules 65,000 1,690,000.00
iv Installation Accessories 1 Lot 150,000 150,000.00
v Labour and professional Charges 250,000 250,000.00
Sub-
Total 5,398,000.00
2DOOR
i Supply of 2.4m Fire Rated Door 2 no 250,000 500,000.00
ii Supply of 3m Fire Rated Door 2 no 320,000 640,000.00
iii Supply of Double Leave Fire Rated Door 6 no 250,000 1,500,000.00
iv Installation Accessories 1 Lot 100,000 100,000.00
v Labour and professional Charges 300,000 300,000.00
Sub-
Total 3,040,000.00
3 RAISED FLOOR SYSTEM
Supply 600mm x 600mm PETRAL Srl Fire
i. retardant Cementitious Infill Raised Floor Panel 660 m2 25,000 16,500,000.00
Supply 600mm x 600mm Camino PEF 50 Air
ii Grate Perforated Raised Floor Panel 60 m2 19,500 1,170,000.00
iii. Supply of Aluminium skirting 720 m2 6,500 364,000.00
iv. Supply of Tile Lifter( Double cup) 4 nos 15,000 60,000.00
v Supply of Equipment Ramp (Steel, Removable) 2 no 120,000 240,000.00
vi Supply of 600mm x 600mm Perforated tiles 160 nos 19,500 3,120,000.00
vii Installation materials, glue,screws etc. 1 Lot 250,000
2. 250,000.00
viii Labour and professional Charges 1,800,000 1,800,000.00
Sub-
Total 23,504,000.00
4SUSPENDED CEILING & RECESSED LIGHTING
Supply and install fire rated 600mm x 600mm
i. gypsum or POP ceiling tiles. 720 m2 3500 2,527,200.00
Supply and install 4 x 20w recessed flourescent
ii. light 98 no 12000 1,176,000.00
Supply and install 2 x 36w Surface Flourescent
iii. light 10 no 10,000 100,000.00
iv. 1.5mm x 3 core flex 22 coil 3250 71,500.00
v. 20mmØ PVC conduit 10 bundle 4000 40,000.00
Installation accessories e.g Pegs,screws, boxes,
vi tangit gum etc 1 Lot 250,000 250,000.00
vii Labour and professional Charges 250,000 250,000.00
Sub-
Total 4,414,700.00
POWER
Supply and Installation of Liebert 1200A Static
1 Transfer Switch (STS2) 2 10,270,000 20,540,000.00
Labour and professional Charges 500,000 500,000.00
Sub-
Total 21,040,000.00
2POWER CABLES & ACCESSORIES (All cables
must be Nigerchin)
i 300mm x 1 Core armoured cable (Nigerchin) 120 14500 1,740,000.00
i 240mm x 1 Core armoured cable (Nigerchin) 240 12161 2,918,640.00
i 185mm x 1 Core Earth cable 60 8792.4 527,544.00
i 120mm x 1 Core armoured cable 480 6441 3,091,680.00
i 70mm x 1 Core Earth cable 120 1820 218,400.00
ii 35mm x 5 core flex cable 400 6110 2,444,000.00
ii 25mm x 5 core flex cable 520 4875 2,535,000.00
` 16mm x 5 core flex cable 480 2860 1,372,800.00
vii 4mm x 3 core flex cable 1600 7540 12,064,000.00
300 x 50 Cable Tray and other Cable
x management accessories (Foreign) 320 Pcs 18500 5,920,000.00
3. xii Supply of 25A SPN Industrial Sockets 80 1300 104,000.00
xiii Supply of 63A TPN Industrial Sockets 24 1950 46,800.00
xiii Supply of 32A SPN Industrial Sockets 120 1320 158,400.00
xiv Supply of 8-Way Metered PDU 200 22200 4,440,000.00
Other installation accessories (PVC Trunking and
xv pipes, pegs, screws, gums, etc) 1 300000 3,000,000.00
XVI Labour and professional Charges 2000000 2,000,000.00
Sub-
Total 42,581,264.00
3 Supply of 1200A STS Panel 2 1726400 3,452,800.00
Labour and professional Charges
Supply and Installation of 800A Phase Rotation
4 and Reversal Correction Panel 1 1221935 1,221,935.00
Labour and professional Charges 460,000.00
Supply and Installation of 1600kA (Per Phase)
5 Liebert S1 Series Interceptor II 2
14
Install Fresh Earthing System and Bond with
i Existing Earthing System 1 150000 150,000.00
Labour and professional Charges 50000 50,000.00
Sub-
Total COMPREHENSIVE EARTHING SYSTEM 200,000.00
15LIGHTNING ARRESTOR SYSTEM
Indelec Prevectron 2 standard Six S6.60 non-
radioactive lightning conductor of 79mtrs action
radius under level 1 condition Inclusive of all
i Installation Accessories. 1 405000 405,000.00
ii Labour and professional Charges 420000 420,000.00
SALES TERMS AND CONDITIONS.
Please note that the above price(s) is/are subject to change without notice.
Validity is two weeks
Payment terms: 80% in advance and 20% on delivery.
Price quoted are VAT Exclusive.
Warranty Period: 1 Year from the date of Installation against any manufacturing defects.
Sincerely,
Tunde Usman (Project Manager).