March 22, 2013.
The Manager, Solution
KITS TECHNOLOGIES LTD,
Attention: Mr. Muideen .A Jokanola
Dear sir,

RE: QUOTATION FOR DATA CENTER CONSTRUCTION.

 S/N     DESCRIPTION                                        QTY                Unit       Price
         1WALL CLADDING AND GLASS PARTITIONING
         Supply and installation of fire rated gypsum
         board wall cladding sheet inclusive of other
   i     cladding materials                                 96    modules   15,500    1,488,000.00
         Supply and Installation of 10mm thick Fire Rated
  ii.    Full Glass Partitions.                             28    Modules   65,000    1,820,000.00
         Supply and Installation of Half Glazed Board
  iii    Partitions                                         26    Modules   65,000    1,690,000.00

  iv     Installation Accessories                            1      Lot     150,000   150,000.00

   v     Labour and professional Charges                                    250,000   250,000.00
Sub-
Total                                                                                 5,398,000.00
2DOOR

   i     Supply of 2.4m Fire Rated Door                      2      no      250,000   500,000.00

   ii    Supply of 3m Fire Rated Door                        2      no      320,000   640,000.00

  iii    Supply of Double Leave Fire Rated Door              6      no      250,000   1,500,000.00

  iv     Installation Accessories                            1      Lot     100,000   100,000.00

   v     Labour and professional Charges                                    300,000   300,000.00
 Sub-
 Total                                                                                3,040,000.00
         3 RAISED FLOOR SYSTEM
         Supply 600mm x 600mm PETRAL Srl Fire
  i.     retardant Cementitious Infill Raised Floor Panel   660     m2      25,000    16,500,000.00
         Supply 600mm x 600mm Camino PEF 50 Air
   ii    Grate Perforated Raised Floor Panel                60      m2      19,500    1,170,000.00

  iii.   Supply of Aluminium skirting                       720     m2      6,500     364,000.00

  iv.    Supply of Tile Lifter( Double cup)                  4      nos     15,000    60,000.00

   v     Supply of Equipment Ramp (Steel, Removable)         2      no      120,000   240,000.00

  vi     Supply of 600mm x 600mm Perforated tiles           160     nos     19,500    3,120,000.00
  vii    Installation materials, glue,screws etc.            1      Lot     250,000
250,000.00

 viii   Labour and professional Charges                                    1,800,000    1,800,000.00
Sub-
Total                                                                                   23,504,000.00

        4SUSPENDED CEILING & RECESSED LIGHTING
        Supply and install fire rated 600mm x 600mm
  i.    gypsum or POP ceiling tiles.                       720     m2      3500         2,527,200.00
        Supply and install 4 x 20w recessed flourescent
 ii.    light                                              98      no      12000        1,176,000.00
        Supply and install 2 x 36w Surface Flourescent
 iii.   light                                              10      no      10,000       100,000.00

 iv.    1.5mm x 3 core flex                                22     coil     3250         71,500.00

 v.     20mmØ PVC conduit                                  10    bundle    4000         40,000.00
        Installation accessories e.g Pegs,screws, boxes,
 vi     tangit gum etc                                     1       Lot     250,000      250,000.00

 vii    Labour and professional Charges                                    250,000      250,000.00
Sub-
Total                                                                                   4,414,700.00

POWER
        Supply and Installation of Liebert 1200A Static
  1     Transfer Switch (STS2)                                     2       10,270,000   20,540,000.00

        Labour and professional Charges                                    500,000      500,000.00
Sub-
Total                                                                                   21,040,000.00

        2POWER CABLES & ACCESSORIES (All cables
        must be Nigerchin)

  i     300mm x 1 Core armoured cable (Nigerchin)                 120      14500        1,740,000.00

  i     240mm x 1 Core armoured cable (Nigerchin)                 240      12161        2,918,640.00

  i     185mm x 1 Core Earth cable                                 60      8792.4       527,544.00

  i     120mm x 1 Core armoured cable                             480      6441         3,091,680.00

  i     70mm x 1 Core Earth cable                                 120      1820         218,400.00

  ii    35mm x 5 core flex cable                                  400      6110         2,444,000.00

  ii    25mm x 5 core flex cable                                  520      4875         2,535,000.00

  `     16mm x 5 core flex cable                                  480      2860         1,372,800.00

 vii    4mm x 3 core flex cable                                   1600     7540         12,064,000.00
        300 x 50 Cable Tray and other Cable
  x     management accessories (Foreign)                         320 Pcs   18500        5,920,000.00
xii     Supply of 25A SPN Industrial Sockets                         80    1300      104,000.00

          xiii    Supply of 63A TPN Industrial Sockets                         24    1950      46,800.00

          xiii    Supply of 32A SPN Industrial Sockets                         120   1320      158,400.00

          xiv     Supply of 8-Way Metered PDU                                  200   22200     4,440,000.00
                  Other installation accessories (PVC Trunking and
          xv      pipes, pegs, screws, gums, etc)                              1     300000    3,000,000.00

          XVI     Labour and professional Charges                                    2000000   2,000,000.00
         Sub-
         Total                                                                                 42,581,264.00

           3      Supply of 1200A STS Panel                                    2     1726400   3,452,800.00
                  Labour and professional Charges
                  Supply and Installation of 800A Phase Rotation
           4      and Reversal Correction Panel                                1     1221935   1,221,935.00

                  Labour and professional Charges                                              460,000.00
                  Supply and Installation of 1600kA (Per Phase)
          5       Liebert S1 Series Interceptor II                             2
          14
                  Install Fresh Earthing System and Bond with
           i      Existing Earthing System                                     1     150000    150,000.00

                  Labour and professional Charges                                    50000     50,000.00
         Sub-
         Total    COMPREHENSIVE EARTHING SYSTEM                                                200,000.00
                  15LIGHTNING ARRESTOR SYSTEM
                  Indelec Prevectron 2 standard Six S6.60 non-
                  radioactive lightning conductor of 79mtrs action
                  radius under level 1 condition Inclusive of all
           i      Installation Accessories.                                    1     405000    405,000.00

           ii     Labour and professional Charges                                    420000    420,000.00

SALES TERMS AND CONDITIONS.

Please note that the above price(s) is/are subject to change without notice.

Validity is two weeks

Payment terms: 80% in advance and 20% on delivery.

Price quoted are VAT Exclusive.

Warranty Period: 1 Year from the date of Installation against any manufacturing defects.

Sincerely,

Tunde Usman (Project Manager).

More Related Content

Rfq kit

  • 1. March 22, 2013. The Manager, Solution KITS TECHNOLOGIES LTD, Attention: Mr. Muideen .A Jokanola Dear sir, RE: QUOTATION FOR DATA CENTER CONSTRUCTION. S/N DESCRIPTION QTY Unit Price 1WALL CLADDING AND GLASS PARTITIONING Supply and installation of fire rated gypsum board wall cladding sheet inclusive of other i cladding materials 96 modules 15,500 1,488,000.00 Supply and Installation of 10mm thick Fire Rated ii. Full Glass Partitions. 28 Modules 65,000 1,820,000.00 Supply and Installation of Half Glazed Board iii Partitions 26 Modules 65,000 1,690,000.00 iv Installation Accessories 1 Lot 150,000 150,000.00 v Labour and professional Charges 250,000 250,000.00 Sub- Total 5,398,000.00 2DOOR i Supply of 2.4m Fire Rated Door 2 no 250,000 500,000.00 ii Supply of 3m Fire Rated Door 2 no 320,000 640,000.00 iii Supply of Double Leave Fire Rated Door 6 no 250,000 1,500,000.00 iv Installation Accessories 1 Lot 100,000 100,000.00 v Labour and professional Charges 300,000 300,000.00 Sub- Total 3,040,000.00 3 RAISED FLOOR SYSTEM Supply 600mm x 600mm PETRAL Srl Fire i. retardant Cementitious Infill Raised Floor Panel 660 m2 25,000 16,500,000.00 Supply 600mm x 600mm Camino PEF 50 Air ii Grate Perforated Raised Floor Panel 60 m2 19,500 1,170,000.00 iii. Supply of Aluminium skirting 720 m2 6,500 364,000.00 iv. Supply of Tile Lifter( Double cup) 4 nos 15,000 60,000.00 v Supply of Equipment Ramp (Steel, Removable) 2 no 120,000 240,000.00 vi Supply of 600mm x 600mm Perforated tiles 160 nos 19,500 3,120,000.00 vii Installation materials, glue,screws etc. 1 Lot 250,000
  • 2. 250,000.00 viii Labour and professional Charges 1,800,000 1,800,000.00 Sub- Total 23,504,000.00 4SUSPENDED CEILING & RECESSED LIGHTING Supply and install fire rated 600mm x 600mm i. gypsum or POP ceiling tiles. 720 m2 3500 2,527,200.00 Supply and install 4 x 20w recessed flourescent ii. light 98 no 12000 1,176,000.00 Supply and install 2 x 36w Surface Flourescent iii. light 10 no 10,000 100,000.00 iv. 1.5mm x 3 core flex 22 coil 3250 71,500.00 v. 20mmØ PVC conduit 10 bundle 4000 40,000.00 Installation accessories e.g Pegs,screws, boxes, vi tangit gum etc 1 Lot 250,000 250,000.00 vii Labour and professional Charges 250,000 250,000.00 Sub- Total 4,414,700.00 POWER Supply and Installation of Liebert 1200A Static 1 Transfer Switch (STS2) 2 10,270,000 20,540,000.00 Labour and professional Charges 500,000 500,000.00 Sub- Total 21,040,000.00 2POWER CABLES & ACCESSORIES (All cables must be Nigerchin) i 300mm x 1 Core armoured cable (Nigerchin) 120 14500 1,740,000.00 i 240mm x 1 Core armoured cable (Nigerchin) 240 12161 2,918,640.00 i 185mm x 1 Core Earth cable 60 8792.4 527,544.00 i 120mm x 1 Core armoured cable 480 6441 3,091,680.00 i 70mm x 1 Core Earth cable 120 1820 218,400.00 ii 35mm x 5 core flex cable 400 6110 2,444,000.00 ii 25mm x 5 core flex cable 520 4875 2,535,000.00 ` 16mm x 5 core flex cable 480 2860 1,372,800.00 vii 4mm x 3 core flex cable 1600 7540 12,064,000.00 300 x 50 Cable Tray and other Cable x management accessories (Foreign) 320 Pcs 18500 5,920,000.00
  • 3. xii Supply of 25A SPN Industrial Sockets 80 1300 104,000.00 xiii Supply of 63A TPN Industrial Sockets 24 1950 46,800.00 xiii Supply of 32A SPN Industrial Sockets 120 1320 158,400.00 xiv Supply of 8-Way Metered PDU 200 22200 4,440,000.00 Other installation accessories (PVC Trunking and xv pipes, pegs, screws, gums, etc) 1 300000 3,000,000.00 XVI Labour and professional Charges 2000000 2,000,000.00 Sub- Total 42,581,264.00 3 Supply of 1200A STS Panel 2 1726400 3,452,800.00 Labour and professional Charges Supply and Installation of 800A Phase Rotation 4 and Reversal Correction Panel 1 1221935 1,221,935.00 Labour and professional Charges 460,000.00 Supply and Installation of 1600kA (Per Phase) 5 Liebert S1 Series Interceptor II 2 14 Install Fresh Earthing System and Bond with i Existing Earthing System 1 150000 150,000.00 Labour and professional Charges 50000 50,000.00 Sub- Total COMPREHENSIVE EARTHING SYSTEM 200,000.00 15LIGHTNING ARRESTOR SYSTEM Indelec Prevectron 2 standard Six S6.60 non- radioactive lightning conductor of 79mtrs action radius under level 1 condition Inclusive of all i Installation Accessories. 1 405000 405,000.00 ii Labour and professional Charges 420000 420,000.00 SALES TERMS AND CONDITIONS. Please note that the above price(s) is/are subject to change without notice. Validity is two weeks Payment terms: 80% in advance and 20% on delivery. Price quoted are VAT Exclusive. Warranty Period: 1 Year from the date of Installation against any manufacturing defects. Sincerely, Tunde Usman (Project Manager).