Since january 2011,I'm member of GCT team for the Lump Sum contract of building a process plant M'dhilla II which is aimed to produce Fertilizers (500 000 Tons of TSP/year).The estimated cost of this project is 400 Millions USD. Being on the side of the owner (GCT) and working with contractors like Hyundai Engineering , SOCOMENIN ,SBF,MERI and East China Science and technology Co gives me the opportunity to have an overview of the various stages of a project (Basic design, detailed design, procurement, construction ...) and be involved in them.
In project M'dhilla II, I’ve been assigned many tasks:
-Participating with GCT team members in the elaboration of the offers for tender
-Pa.