This document discusses five methods for measuring work progress on construction projects: 1) Units Completed, which measures work as a percentage of total units completed, 2) Cost or Time Ratio, which measures work as a percentage of total budget or time spent, 3) Start-Finish, which assigns percentages based on start and completion, 4) Supervisor's Opinion, which relies on a supervisor's subjective judgment, and 5) Incremental Milestones, which breaks work into weighted subtasks or milestones. Each method is best suited to certain types of activities based on their uniformity, duration, and ability to define progress objectively. Examples are provided to illustrate how to calculate progress for each method.
1 of 13
More Related Content
21.03.2018 ARDC session #3 measuring work Progress
3. Several methods for measuring work progress are suggested.
Five of these methods are as follows :
Calculating or Estimating the percent complete for .
Activity Project
1. Units Completed
2. Cost or Time Ratio
3. Start Finish
4. Supervisors Opinion
5. Incremental Milestones
4. This method works well for activities with Small, Identical, Repetitive components, of easily measured production of easily
measured ,when each piece requires approximately the same level of effort.
1- Units Completed
Work Progress =
Units completed
Total units
For example, in an activity involving installing 5000 concrete blocks, 2000 have
been installed.
Percent complete =
2000
5000
*100 = 40 %
40%
Laying bricks or CMUs (concrete masonry units),
Excavating,
Fishing electric wire, Installing tile or carpet, ..
5. For example, a project supervision activity scheduled for 10 months with a budget of SAR 200,000. After 2 months if SAR 38,000
is already spent, what is the percent complete ?
Cost Ratio =
Cost to Date
Total Budget Time Ratio =
Time Elapsed
Total Duration
Activities that Uniform throughout the project,
Long duration tasks or that are continuous during the life of a project,
which are estimated and budgeted on bulk allocations of money and workhours rather than on the basis of production.
Project Management,
Quality Assurance,
Contract Administration,
Project Controls ,
Safety Inspection
Percent complete =
2
10
*100 = 20 %
Percent complete =
38,000
220,000
*100 = 17 % 17COST RATIO
20TIME RATIO
2- COST OR TIME RATIO:
6. Examples : Planning activities, flushing ,cleaning, testing
3- Start Finish :
Have not started yet 0%
Started but not yet finished
(an arbitrary amount)
40% or 50%
Finished 100 %
Small activities or with no or a short
duration.
Where no intermediate milestones can
be defined
The effort/time required is very
difficult to estimate.
7. This method relies totally on the foreman or superintendents judgment.
Because it does not require actual measurements, it is considered the quickest
method.
Examples : Dewatering, Temporary construction, Landscaping
4- Supervisors opinion:
Used only for relatively minor tasks and where developing a more objective status
is not feasible.
used when no other method can be suitably
Be careful not to overuse this method.
8. The task is segmented into subtasks and each is assigned an increment of progress
weight for the entire task. Completing a subtask is the achievement task. of a
milestone.
Each subtasks assigned a weight that is approximately equal to its percentage share
of effort in the total task .
The milestone percentage is normally based. on the number of workhours required
5- Incremental Milestones:
Suitable for large and complex or multistage activities.
9. By J炭lio Reis - Own work, CC BY-SA 3.0,https://commons.wikimedia.org/w/index.php?curid=934562
Roman milestone XXIX on Via Romana XVIII the road linking the Iberian cities of Bracara Augusta and Asturica
Augusta
Milestones
The project manager or superintendent can assign a percent complete to a small, simple activity easier and more objectively than he or she can do so for a large, complex activity.
This subject is broad. In this chapter, it is covered only briefly.
There are no correct and incorrect methods; there are only more and less suitable methods for the specific type of activity under consideration.
In some cases, errors may arise despite the similarity in units because of the effect of learning curves or differing conditions. As an example of the second case is when a mason is installing block or brick to an 8-ft high wall. The blocks on the high courses take more time than those in
lower courses. When the error is small, it is ignored.
Another alternative is the man-hour ratio (actual man-hours consumed divided by total man-hours budgeted).
The time ratio method for individual activities is similar to the duration percent complete and baseline duration percent complete methods for calculating the project percent
complete. These methods are discussed in the next section
The contractor may use this method to exaggerate the percent complete for early payment.