際際滷

際際滷Share a Scribd company logo
7QS Consultant Sdn. Bhd.
Taylors University, Lakeside Campus.
No.1, Jalan Taylors,
47500 Subang Jaya,
Selangor Darul Ehsan
Loh Mun Tong 0323680
Loo Siah Mong 0321995
Muhammad Fareez 0322961
Michelle Tung 0324175
Ng Sheng Zhe 0323830
Nicole Thain Huey Wei 0325697
Pui Chun Shian 0323470
INTRODUCTION OF PROJECT
Project title: Construction and completion 1 unit semi-detached house 2
storey high Type B (Lot Lama 1774)
Address : Jalan kapar, Taman Sri Kapar (KU13), Mukim Kapar, Klang
Bandar Diraja, Selangor Darul Ehsan
Building Purposes: Residential
Type of Project: Private
SITE CONDITION
Generally flat. All earthwork, site clearance, external infrastructure works have
already completed by others.
KEY PLAN
CONSTRUCTION SITE
LOCATION PLAN
SITE PLAN
SEMI D TYPE B
SEMI D TYPE A
SEMI D TYPE B
FLOOR PLAN - GROUND FLOOR & FIRST FLOOR
FLOOR PLAN - ROOF PLAN
ELEVATION
FRONT ELEVATION BACK ELEVATION
ELEVATION
RIGHT ELEVATION
SECTIONS
SECTION B-B SECTION A-A
FORM OF CONTRACT
PAM Contract 2006 with Quantities
Under the terms and conditions of the PAM Standard Form contract 2006,
both the employer and contractor form the contractual parties to the
contract.
To ensure that the Contract is administered fairly between both
Contractual Parties, PAM Contract 2006 places the administration under
third party, namely the Architect.
Reasons of using PAM contract 2006 with Quantities
Quality and Quantity of works
Under clause 12, where PAM with quantities mentions that Contract Bills
form the basis for quantity of the works while PAM without quantities
mentions that the Contract Sum is derived from the contractor's own
estimate of the quantity based on Drawings and Specifications.
To ensure the performance on the quantities of works, BOQ is therefore
crucial to provide accurate and sufficient information of the project.
FORM OF CONTRACT (contd)
Completion of work on time
Under clause 22.1, liquidated damages and certificate of non-completion,
if the contractor fails to complete the works by the completion date and it
shall be ought to be completed in the opinion of the Architect, the architect
shall issue the certificate of non-completion.
The contractor will compensate the employer from the damages or
referred to as Liquidated Damages from the sum as a debt or from the
performance bond.
FORM OF CONTRACT (contd)
FORM OF TENDER
Form where the tenderer insert his
tender amount and agreement to
other specified tender conditions by
attesting its signature or company seal
and making this form to be his legal
offer to the Employer
INSTRUCTIONS TO TENDERER
Served to inform the tenderer on the
general rules & procedures that they need
to comply within the entire tendering
process
CONDITIONS OF TENDERING
Conditions of tendering is a rules and terms specific to a tender, submission,
evaluation and awarding of the contract.
 Basis of Tender
Firm price tender and no claim is allowed for variation
 Tender Deposit
Fee for the tender documents, RM500.00 shall pay in cash to
7QS CONSULTANT SDN BHD
CONDITIONS OF TENDERING (contd)
 Tender Bond
- Shall made in the form of Bankers Draft or unconditional Bankers Guarantee
- Shall be retained and remain valid until the expiration of 90 days after the
closing of tender
 Tender Validity Period
Remain valid open for consideration for a period of 90 days from the final
closing date for the submission of Tenders
FINAL SUMMARY OF TENDER
 Summary of total amount of
every bill in bills of quantity
 Total bill will be tender sum
PREAMBLE
Contain clauses that serve to introduce
and explain the provisions in the
Specification and Bills of Quantities
sections and the scope of coverage of
the rates in the BQ
SPECIFICATIONS
Contain extensive clauses on detail
procedures to be followed in executing
the works; requirements & description
of the works to be performed
Eg: Quality & performance of materials
Bill of Quantities
BILL NO. 1 - PRELIMINARIES
The purpose of Preliminaries is to
provide information, general
obligations and liabilities of the
project.
INSURANCE
Insurance of New Building/Works -
By The Employer
BILL NO. 1 - PRELIMINARIES
PROTECTION, PRECAUTION
& PREVENTION
Safety Precaution
Maintenance & protection of
Public Property
Mosquito Prevention
Watching and Security
Fencing and Hoarding
BILL NO 2 - MAIN BUILDING WORKS
PILLING
WORK BELOW LOWEST FLOOR FINISH
FRAME
UPPER FLOORS
ROOF
STAIR AND STAIRCASE FINISHES
EXTERNAL WALLS
BILL NO 2 - MAIN BUILDING WORKS
INTERNAL WALL AND PARTITIONS
WINDOWS & DOORS
INTERNAL WALL FINISHES
INTERNAL FLOOR FINISHES
INTERNAL CEILING FINISHES
EXTERNAL FINISHES
EXTERNAL WORK WITHIN BOUNDARY
BILL NO. 3 - PC AND PROVISIONAL SUMS
Prime Cost (PC) sums
Sums included in the contract to cover specialist works and the supply of
specific materials, which entail the employment of nominated
sub-contractor or nominated supplier.
Provisional sums
Sums included in the contract for works which the full extent and character
cannot be determined precisely at the time the BQ is prepared.
APPENDICES- LIST OF DRAWINGS
SCHEDULE OF FINISHES (1st Floor)
SCHEDULE OF FINISHES (Ground Floor)
SCHEDULE OF FINISHES CONTD (Ground Floor)
Timber Flooring
Terrazzo Tiles
Anti-Slip Ceramic
Tiles for bathrooms
Cement Render
Ceramic Tiles for Staircase
Cement Plaster
Emulsion Paint
Ceramic Wall Tiles in
Bathroom
Cement Plaster
Weathershield paint
Skim Coat Skim coat with plaster cornices
SCHEDULE OF DAYWORK RATES
SCHEDULE OF DAYWORK RATES
PRICES OF BASIC MATERIALS
FORM OF BANK GUARANTEE FOR EARNEST MONEY/ TENDER BOND
FORM OF BANK GUARANTEE FOR PERFORMANCE BOND
THANK YOU

More Related Content

Measurement 4 presentation slides

  • 1. 7QS Consultant Sdn. Bhd. Taylors University, Lakeside Campus. No.1, Jalan Taylors, 47500 Subang Jaya, Selangor Darul Ehsan Loh Mun Tong 0323680 Loo Siah Mong 0321995 Muhammad Fareez 0322961 Michelle Tung 0324175 Ng Sheng Zhe 0323830 Nicole Thain Huey Wei 0325697 Pui Chun Shian 0323470
  • 2. INTRODUCTION OF PROJECT Project title: Construction and completion 1 unit semi-detached house 2 storey high Type B (Lot Lama 1774) Address : Jalan kapar, Taman Sri Kapar (KU13), Mukim Kapar, Klang Bandar Diraja, Selangor Darul Ehsan Building Purposes: Residential Type of Project: Private
  • 3. SITE CONDITION Generally flat. All earthwork, site clearance, external infrastructure works have already completed by others.
  • 6. SITE PLAN SEMI D TYPE B SEMI D TYPE A
  • 8. FLOOR PLAN - GROUND FLOOR & FIRST FLOOR
  • 9. FLOOR PLAN - ROOF PLAN
  • 13. FORM OF CONTRACT PAM Contract 2006 with Quantities Under the terms and conditions of the PAM Standard Form contract 2006, both the employer and contractor form the contractual parties to the contract. To ensure that the Contract is administered fairly between both Contractual Parties, PAM Contract 2006 places the administration under third party, namely the Architect.
  • 14. Reasons of using PAM contract 2006 with Quantities Quality and Quantity of works Under clause 12, where PAM with quantities mentions that Contract Bills form the basis for quantity of the works while PAM without quantities mentions that the Contract Sum is derived from the contractor's own estimate of the quantity based on Drawings and Specifications. To ensure the performance on the quantities of works, BOQ is therefore crucial to provide accurate and sufficient information of the project. FORM OF CONTRACT (contd)
  • 15. Completion of work on time Under clause 22.1, liquidated damages and certificate of non-completion, if the contractor fails to complete the works by the completion date and it shall be ought to be completed in the opinion of the Architect, the architect shall issue the certificate of non-completion. The contractor will compensate the employer from the damages or referred to as Liquidated Damages from the sum as a debt or from the performance bond. FORM OF CONTRACT (contd)
  • 16. FORM OF TENDER Form where the tenderer insert his tender amount and agreement to other specified tender conditions by attesting its signature or company seal and making this form to be his legal offer to the Employer
  • 17. INSTRUCTIONS TO TENDERER Served to inform the tenderer on the general rules & procedures that they need to comply within the entire tendering process
  • 18. CONDITIONS OF TENDERING Conditions of tendering is a rules and terms specific to a tender, submission, evaluation and awarding of the contract. Basis of Tender Firm price tender and no claim is allowed for variation Tender Deposit Fee for the tender documents, RM500.00 shall pay in cash to 7QS CONSULTANT SDN BHD
  • 19. CONDITIONS OF TENDERING (contd) Tender Bond - Shall made in the form of Bankers Draft or unconditional Bankers Guarantee - Shall be retained and remain valid until the expiration of 90 days after the closing of tender Tender Validity Period Remain valid open for consideration for a period of 90 days from the final closing date for the submission of Tenders
  • 20. FINAL SUMMARY OF TENDER Summary of total amount of every bill in bills of quantity Total bill will be tender sum
  • 21. PREAMBLE Contain clauses that serve to introduce and explain the provisions in the Specification and Bills of Quantities sections and the scope of coverage of the rates in the BQ
  • 22. SPECIFICATIONS Contain extensive clauses on detail procedures to be followed in executing the works; requirements & description of the works to be performed Eg: Quality & performance of materials
  • 24. BILL NO. 1 - PRELIMINARIES The purpose of Preliminaries is to provide information, general obligations and liabilities of the project. INSURANCE Insurance of New Building/Works - By The Employer
  • 25. BILL NO. 1 - PRELIMINARIES PROTECTION, PRECAUTION & PREVENTION Safety Precaution Maintenance & protection of Public Property Mosquito Prevention Watching and Security Fencing and Hoarding
  • 26. BILL NO 2 - MAIN BUILDING WORKS PILLING WORK BELOW LOWEST FLOOR FINISH FRAME UPPER FLOORS ROOF STAIR AND STAIRCASE FINISHES EXTERNAL WALLS
  • 27. BILL NO 2 - MAIN BUILDING WORKS INTERNAL WALL AND PARTITIONS WINDOWS & DOORS INTERNAL WALL FINISHES INTERNAL FLOOR FINISHES INTERNAL CEILING FINISHES EXTERNAL FINISHES EXTERNAL WORK WITHIN BOUNDARY
  • 28. BILL NO. 3 - PC AND PROVISIONAL SUMS Prime Cost (PC) sums Sums included in the contract to cover specialist works and the supply of specific materials, which entail the employment of nominated sub-contractor or nominated supplier. Provisional sums Sums included in the contract for works which the full extent and character cannot be determined precisely at the time the BQ is prepared.
  • 30. SCHEDULE OF FINISHES (1st Floor)
  • 31. SCHEDULE OF FINISHES (Ground Floor)
  • 32. SCHEDULE OF FINISHES CONTD (Ground Floor)
  • 33. Timber Flooring Terrazzo Tiles Anti-Slip Ceramic Tiles for bathrooms Cement Render Ceramic Tiles for Staircase
  • 34. Cement Plaster Emulsion Paint Ceramic Wall Tiles in Bathroom Cement Plaster Weathershield paint
  • 35. Skim Coat Skim coat with plaster cornices
  • 38. PRICES OF BASIC MATERIALS
  • 39. FORM OF BANK GUARANTEE FOR EARNEST MONEY/ TENDER BOND
  • 40. FORM OF BANK GUARANTEE FOR PERFORMANCE BOND