The document summarizes the recovery and repair of aircraft VH-OJH after it crashed at Bangkok International Airport on September 23, 1999. It describes stabilizing the aircraft, removing damaged sections, replacing parts, documenting work, and certifying repairs over a 6 month period. The aircraft was then repainted and returned to service on April 8, 2000.
1 of 63
Downloaded 59 times
More Related Content
Qantas repair
1. VH-OJH INCIDENT 23 SEPTEMBER 1999 PETER THOMAS OJH PROJECT COORDINATOR
2. THE FIRST DAY VH-OJH left the end of RWY 21L at BKK INTERNATIONAL AIRPORT on the night of 23 SEPTEMBER 1999. The A/C travelled a further 200 metres across the RWY run-off area. On its way the A/C collided with the RWY 03R Localiser Antenna before coming to rest in a RWL position.
9. THE RECOVERY The importance of keeping the Station Aircraft Recovery List updated, including checking Emergency Contacts and Equipment Suppliers phone numbers. An assistant is required to keep notes during the initial Recovery planning period.
16. ARRIVAL OF PARTS To ensure swift delivery of Parts, Materials and Tooling a Customs Agent must be engaged who has contacts at the HIGHEST LEVELS. Arranging a Customs Carnet is of utmost importance to overcome heavy Customs Duties. To ensure these deliveries are completed with the utmost promptness, cooperation with all levels of the Airport Authority is required.
19. INCIDENT SITE SCRAP All scrap had to be collected for documentation. To conform to Customs regulations all parts and raw materials movements had to be thoroughly documented and presented to the Authorities for approval so as not to incur large Customs duties. This procedure was also required for all scrap material.
21. JANUARY 23 2000 REPAIR BEGINS The Boeing Team begins the repair by first stabilising and jigging the Aircraft to prevent fuselage movement during the removal of the lower sections of Sections41 and 42.
22. pth13: A/C was tied to the tail jack and the jack was cabled to the ground. Jack point was drilled to allow fitment of a rod between the jack adaptor and the jack point.
25. AIRCRAFT REPAIR BEGINS Removal of Section 41 and 42 begins. Replacement of the damaged window-belt has to be done before removal of the lower Section 41. This is to ensure the alignment of the Aircraft is maintained.
36. STORES PERSONNEL A team of Stores Personnel was required to acquit all the Parts demands and to administer a Parts store to ensure a smooth production flow is maintained. Boeing were ordering hundreds of parts daily from Seattle and expecting 2 days delivery at the site.
38. DOCUMENTING AND CERTIFICATION To lessen the impact of the cost of the repair to QANTAS a lot of rotable parts were supplied by QANTAS. The Insurance Company will only pay Market Price for these parts. A Team of LAMEs were needed to document and certify these parts as a lot of the Parts were delivered straight from the Vendor. This included all the Landing Gear assemblys.
47. ROLL-OUT AFTER REPAIR Rollout from Hangar after approx. 6 months. Due to publicity sensitivity the A/C had to be similar in appearance to other B744s prior to rollout. The repaint of the repaired areas was achieved by paint rollers.