April 2014 till present TRANSNET Port Terminals, Iron ore Terminal – Saldanha, RSA
Mechanical Engineer, Engineering department (expansion project, etc). Relieve in Maintenance department as Technical manager Tipplers and Stacker Reclaimers due to staff shortages.
Projects include: replacement of 320 meters of schedule 160 hydraulic pipe; Tippler drum trunnion wheel and rail repair; Major structural repair of Tippler2 positioner; procure positioner and slew gearbox’es; Weld repair and line boring of slew gearbox mounting bores; Stacker Reclaimer luffing cylinder replacement; panfeeder overhaul; scope to build fluid cleanliness trolley; machine structural and performance audits; CAPEX...