際際滷

際際滷Share a Scribd company logo
Earned Value
      A simple approach for
     Product Based Planners


                       David Willcox
                    Senior Consultant
                    IT Project Manager

息 PlanIT 2TCQ Ltd           1      http://www.planit2tcq.co.uk/
Are you a fan or a sceptic?
 Earned Value is an advanced Project progress monitoring
  approach where you measure the work complete, the time
  taken and the costs incurred to see if a project is on track
 In terms of usefulness it has divided option, some believe it
  should always be used because it is the only true way of
  measuring overall progress; some believe that the effort
  necessary to measure properly outweighs the benefits gained
 I have never used it fully myself or seen it fully implemented
  despite being involved in some major programmes over the last
  20 years
 However, I suggest that good product based planners can gain
  some of the key benefits for little extra work
 I have been testing the concept on a recent project and it
  seems to offer benefits including Project Board communication
  as people prefer a graph to a dry set of milestones (although I
  have used both in progress packs)
   息 PlanIT 2TCQ Ltd            2           http://www.planit2tcq.co.uk/
Are you a Product Based Planner?
 Identifying the Products to be delivered is a cornerstone of
  methods such as PRINCE2
 It is an excellent planning approach which I always use
 Even on its own, it is a way of measuring project progress
 However, for a little extra effort, it can be used to measure a
  simplified Earned Value representation and give an even
  better view of progress
 I will take you through step by step on a sample project and
  you can see the benefits




  息 PlanIT 2TCQ Ltd             3            http://www.planit2tcq.co.uk/
Step 1
    Normal Product Based Planning
   Identify the products, their flow etc.
   Estimate the effort to produce and quality assure
   Build your plan
   Produce a Product Inventory in Excel
     Do not forget to include nondocumentproducts
     For documents, you record your baseline dates for production of
      a draft and for the document to be baselined following full
      quality review / signoff
     For non documents I have still included a draft date
      approximately around 50% through the production cycle




    息 PlanIT 2TCQ Ltd              4            http://www.planit2tcq.co.uk/
Step 2
      Add weighted Planned Value
 Add 3 columns to your spreadsheet (you will an example in
  a moment)
    PV = Valuation of each product (relative factor)
    EV% = % of the value of the product earned
    EV = PV * EV%
 PV needs a bit of thought, for simplicity I use a relative
  value of each product. It is a judgement call but I have used
    1 when in doubt
    Reduced for some management products (but increased for PID
     as this is important)
    Bigger values for important design docs, software to be used etc




  息 PlanIT 2TCQ Ltd                5            http://www.planit2tcq.co.uk/
Step 3
How much value by Product Status?
 My Product Inventory tracks the following statuses and my
  suggested relative value
      Not Started = 0%
      Being Drafted = 20%
      Draft Issued = 50%
      Partially Approved = 70%
      Approved = 100%
 Some simple VLOOKUPS & you have an Earned Value for
  each product to be produced
 100% of ALL products approved is the total value of the
  project




  息 PlanIT 2TCQ Ltd               6       http://www.planit2tcq.co.uk/
The Project Products Inventory
Project xxxxxx - Key Product Status as at              29/06/2012                                                              33.9         11.4
                                                                   Draft     Draft   Draft       Fully       Fully     Fully
                                                                   Issued Issued     Issued      Approve     Approve Approve
#       Gate Name                               Status             Base      Fore    Actual      Base        Fore      Actual    PV EV% EV
1 1Q    A-B Feasibility Delivery Approach       Approved            15/05/12          15/05/12    16/05/12              16/05/12 1.0 100% 1.0
2    1Q A-B Gate B Investment Case              Approved            25/05/12          25/05/12    31/05/12              08/06/12 0.5 100% 0.5
3    1Q A-B High Level Architecture             Partially Approved 18/05/12           18/05/12    01/06/12    02/07/12            0.5 70% 0.4
             Aligne Book / Trade
4    3D B-C Descriptions Design                 Approved             01/06/12         01/06/12 15/06/12             22/06/12    3.0 100%     3.0
5    3D B-C Detailed Requirements               Draft Issued         12/06/12         21/06/12 22/06/12 05/07/12                1.5   50%    0.8
6    3D B-C Process Map                         Partially Approved   12/06/12         15/06/12 22/06/12 03/07/12                1.5   70%    1.1
7    3D B-C Inventory of Build Items            Partially Approved   15/06/12         22/06/12totals at top02/07/12
                                                                                         See 22/06/12                           1.5   70%    1.1
             Inventory of Process /
8    3D B-C Procedures to amend                 Partially Approved   15/06/12            Product relative value of
                                                                                      22/06/12 22/06/12 02/07/12                1.0   70%    0.7
9    3D B-C Business Readiness Plan             Partially Approved   15/06/12            3, it is fully approved so
                                                                                      15/06/12 22/06/12 29/06/12                0.5   70%    0.4
10   3D B-C Gate C Investment Case              Partially Approved   21/06/12         21/06/12 100% of 3 = 3
                                                                                         EV is 26/06/12 06/07/12                0.5   70%    0.4
11   3D B-C Technical Architecture Design       Draft Issued         15/06/12         27/06/12 27/06/12 09/07/12                0.5   50%    0.3
12   3D B-C Project Initiation Document         Draft Issued         21/06/12         21/06/12 29/06/12 09/07/12                2.0   50%    1.0
13   4B C-D Test Plan                           Not Started          06/07/12                     20/07/12                      1.5   0%     0.0
             Reports, Models all built & unit
14   3D B-C tested                              Being Drafted        20/07/12                    27/07/12                       5.0   20%    1.0
             Processes / Procedures all
15   3D B-C updated & reviewed                  Not Started          27/07/12                    03/08/12                       2.0   0%     0.0
16   4B C-D Test Scripts                        Not Started          20/07/12                    03/08/12                       2.0   0%     0.0
17   5T C-D Go/No Go Checklist                  Not Started          20/08/12                    28/08/12                       1.0   0%     0.0
18   5T C-D Storm Plan                          Not Started          28/08/12                    11/09/12                       1.0   0%     0.0
19   5T C-D End of Test Report                  Not Started          11/09/12                    14/09/12                       3.0   0%     0.0
             Implemented Reports, Models
20   6I C-D etc                                 Not Started          14/09/12                    14/09/12                       4.0   0%     0.0
21   7H C-D End of Project Report               Not Started          05/11/12                    12/11/12                       0.2   0%     0.0
22   7H C-D Lessons Learnt Report               Not Started          05/11/12                    12/11/12                       0.2   0%     0.0


             息 PlanIT 2TCQ Ltd                                                  7                   http://www.planit2tcq.co.uk/
Step 4
   Add Sheet with some running totals
 Sort the Inventory by baseline                                 FA Bas Date Tot PV% Tot EV%
                                                                     16/05/12      2.9%    2.9%
  product approved date                                              31/05/12      4.4%
                                                                     01/06/12
 Use the relative factors to show in                                15/06/12
                                                                                   5.9%
                                                                                  14.7%
  a table % of PV over time leading                                  22/06/12     19.2%
                                                                     22/06/12
  to 100%                                                            22/06/12
                                                                                  23.6%
                                                                                  28.0%

 Spreadsheet calculates the                                         22/06/12     31.0%
                                                                     22/06/12     32.4%   29.5%
  totalto date EVas a by-product                                   26/06/12     33.9%

  of updating milestones for                                         27/06/12     35.4%
                                                                     29/06/12     41.3%   33.5%
  tracking purposes as below and                                     20/07/12     45.7%

  while you are updating product                                     27/07/12     60.5%
                                                                     03/08/12     66.4%
  status & forecasts, you enter the                                  03/08/12     72.3%

  EV% in the table for the date                                      28/08/12     75.2%
                                                                     11/09/12     78.2%
                                                                     14/09/12     87.0%
Total EV showing at the moment is    11.35 for date   29/06/2012     14/09/12     98.8%
which represents a percentage of    33.5%                            12/11/12     99.4%
                                                                     12/11/12    100.0%


       息 PlanIT 2TCQ Ltd                      8                 http://www.planit2tcq.co.uk/
The EV chart for use in reporting
                                 Project xxxx - Earned Value via Products
             120.0%      As at 29/6 EV% for project is 33%.
                         Planned to be 41%. Reason -
                         struggling to get full approval of
             100.0%      some products produced as large
                         number of approvers

              80.0%
% of Value




                                                                                                        Tot PV%
              60.0%                                               A lot of planned value when have
                                                                  implemented - only a little added     Tot EV%
                                                                  during post implementation to
              40.0%                                               project closedown
                                                   33.5%
                                               29.5%

              20.0%

                          2.9%
                  0.0%
                          12




                          12
                          12
                          12



                          12




                          12

                          12




                          12
                          12

                          12




                          12

                          12




                          12
                       20




                       20
                       20



                       20




                       20

                       20




                       20
                       20

                       20




                       20

                       20




                       20
                       20
                    5/



                    6/




                    7/

                    8/

                    8/




                    0/

                    0/
                    6/

                    7/




                    9/

                    9/




                    0/
                    5/
                 /0




                 /0




                 /1
                 /0

                 /0




                 /0

                 /0




                 /1
                 /0

                 /0




                 /0

                 /0




                 /1
             16




              11

              25




              05

              19

              03



              31
              30

              13

              27




              08

              22




              17

                  息 PlanIT 2TCQ Ltd                           9                    http://www.planit2tcq.co.uk/

More Related Content

Product Based Earned Value

  • 1. Earned Value A simple approach for Product Based Planners David Willcox Senior Consultant IT Project Manager 息 PlanIT 2TCQ Ltd 1 http://www.planit2tcq.co.uk/
  • 2. Are you a fan or a sceptic? Earned Value is an advanced Project progress monitoring approach where you measure the work complete, the time taken and the costs incurred to see if a project is on track In terms of usefulness it has divided option, some believe it should always be used because it is the only true way of measuring overall progress; some believe that the effort necessary to measure properly outweighs the benefits gained I have never used it fully myself or seen it fully implemented despite being involved in some major programmes over the last 20 years However, I suggest that good product based planners can gain some of the key benefits for little extra work I have been testing the concept on a recent project and it seems to offer benefits including Project Board communication as people prefer a graph to a dry set of milestones (although I have used both in progress packs) 息 PlanIT 2TCQ Ltd 2 http://www.planit2tcq.co.uk/
  • 3. Are you a Product Based Planner? Identifying the Products to be delivered is a cornerstone of methods such as PRINCE2 It is an excellent planning approach which I always use Even on its own, it is a way of measuring project progress However, for a little extra effort, it can be used to measure a simplified Earned Value representation and give an even better view of progress I will take you through step by step on a sample project and you can see the benefits 息 PlanIT 2TCQ Ltd 3 http://www.planit2tcq.co.uk/
  • 4. Step 1 Normal Product Based Planning Identify the products, their flow etc. Estimate the effort to produce and quality assure Build your plan Produce a Product Inventory in Excel Do not forget to include nondocumentproducts For documents, you record your baseline dates for production of a draft and for the document to be baselined following full quality review / signoff For non documents I have still included a draft date approximately around 50% through the production cycle 息 PlanIT 2TCQ Ltd 4 http://www.planit2tcq.co.uk/
  • 5. Step 2 Add weighted Planned Value Add 3 columns to your spreadsheet (you will an example in a moment) PV = Valuation of each product (relative factor) EV% = % of the value of the product earned EV = PV * EV% PV needs a bit of thought, for simplicity I use a relative value of each product. It is a judgement call but I have used 1 when in doubt Reduced for some management products (but increased for PID as this is important) Bigger values for important design docs, software to be used etc 息 PlanIT 2TCQ Ltd 5 http://www.planit2tcq.co.uk/
  • 6. Step 3 How much value by Product Status? My Product Inventory tracks the following statuses and my suggested relative value Not Started = 0% Being Drafted = 20% Draft Issued = 50% Partially Approved = 70% Approved = 100% Some simple VLOOKUPS & you have an Earned Value for each product to be produced 100% of ALL products approved is the total value of the project 息 PlanIT 2TCQ Ltd 6 http://www.planit2tcq.co.uk/
  • 7. The Project Products Inventory Project xxxxxx - Key Product Status as at 29/06/2012 33.9 11.4 Draft Draft Draft Fully Fully Fully Issued Issued Issued Approve Approve Approve # Gate Name Status Base Fore Actual Base Fore Actual PV EV% EV 1 1Q A-B Feasibility Delivery Approach Approved 15/05/12 15/05/12 16/05/12 16/05/12 1.0 100% 1.0 2 1Q A-B Gate B Investment Case Approved 25/05/12 25/05/12 31/05/12 08/06/12 0.5 100% 0.5 3 1Q A-B High Level Architecture Partially Approved 18/05/12 18/05/12 01/06/12 02/07/12 0.5 70% 0.4 Aligne Book / Trade 4 3D B-C Descriptions Design Approved 01/06/12 01/06/12 15/06/12 22/06/12 3.0 100% 3.0 5 3D B-C Detailed Requirements Draft Issued 12/06/12 21/06/12 22/06/12 05/07/12 1.5 50% 0.8 6 3D B-C Process Map Partially Approved 12/06/12 15/06/12 22/06/12 03/07/12 1.5 70% 1.1 7 3D B-C Inventory of Build Items Partially Approved 15/06/12 22/06/12totals at top02/07/12 See 22/06/12 1.5 70% 1.1 Inventory of Process / 8 3D B-C Procedures to amend Partially Approved 15/06/12 Product relative value of 22/06/12 22/06/12 02/07/12 1.0 70% 0.7 9 3D B-C Business Readiness Plan Partially Approved 15/06/12 3, it is fully approved so 15/06/12 22/06/12 29/06/12 0.5 70% 0.4 10 3D B-C Gate C Investment Case Partially Approved 21/06/12 21/06/12 100% of 3 = 3 EV is 26/06/12 06/07/12 0.5 70% 0.4 11 3D B-C Technical Architecture Design Draft Issued 15/06/12 27/06/12 27/06/12 09/07/12 0.5 50% 0.3 12 3D B-C Project Initiation Document Draft Issued 21/06/12 21/06/12 29/06/12 09/07/12 2.0 50% 1.0 13 4B C-D Test Plan Not Started 06/07/12 20/07/12 1.5 0% 0.0 Reports, Models all built & unit 14 3D B-C tested Being Drafted 20/07/12 27/07/12 5.0 20% 1.0 Processes / Procedures all 15 3D B-C updated & reviewed Not Started 27/07/12 03/08/12 2.0 0% 0.0 16 4B C-D Test Scripts Not Started 20/07/12 03/08/12 2.0 0% 0.0 17 5T C-D Go/No Go Checklist Not Started 20/08/12 28/08/12 1.0 0% 0.0 18 5T C-D Storm Plan Not Started 28/08/12 11/09/12 1.0 0% 0.0 19 5T C-D End of Test Report Not Started 11/09/12 14/09/12 3.0 0% 0.0 Implemented Reports, Models 20 6I C-D etc Not Started 14/09/12 14/09/12 4.0 0% 0.0 21 7H C-D End of Project Report Not Started 05/11/12 12/11/12 0.2 0% 0.0 22 7H C-D Lessons Learnt Report Not Started 05/11/12 12/11/12 0.2 0% 0.0 息 PlanIT 2TCQ Ltd 7 http://www.planit2tcq.co.uk/
  • 8. Step 4 Add Sheet with some running totals Sort the Inventory by baseline FA Bas Date Tot PV% Tot EV% 16/05/12 2.9% 2.9% product approved date 31/05/12 4.4% 01/06/12 Use the relative factors to show in 15/06/12 5.9% 14.7% a table % of PV over time leading 22/06/12 19.2% 22/06/12 to 100% 22/06/12 23.6% 28.0% Spreadsheet calculates the 22/06/12 31.0% 22/06/12 32.4% 29.5% totalto date EVas a by-product 26/06/12 33.9% of updating milestones for 27/06/12 35.4% 29/06/12 41.3% 33.5% tracking purposes as below and 20/07/12 45.7% while you are updating product 27/07/12 60.5% 03/08/12 66.4% status & forecasts, you enter the 03/08/12 72.3% EV% in the table for the date 28/08/12 75.2% 11/09/12 78.2% 14/09/12 87.0% Total EV showing at the moment is 11.35 for date 29/06/2012 14/09/12 98.8% which represents a percentage of 33.5% 12/11/12 99.4% 12/11/12 100.0% 息 PlanIT 2TCQ Ltd 8 http://www.planit2tcq.co.uk/
  • 9. The EV chart for use in reporting Project xxxx - Earned Value via Products 120.0% As at 29/6 EV% for project is 33%. Planned to be 41%. Reason - struggling to get full approval of 100.0% some products produced as large number of approvers 80.0% % of Value Tot PV% 60.0% A lot of planned value when have implemented - only a little added Tot EV% during post implementation to 40.0% project closedown 33.5% 29.5% 20.0% 2.9% 0.0% 12 12 12 12 12 12 12 12 12 12 12 12 12 20 20 20 20 20 20 20 20 20 20 20 20 20 5/ 6/ 7/ 8/ 8/ 0/ 0/ 6/ 7/ 9/ 9/ 0/ 5/ /0 /0 /1 /0 /0 /0 /0 /1 /0 /0 /0 /0 /1 16 11 25 05 19 03 31 30 13 27 08 22 17 息 PlanIT 2TCQ Ltd 9 http://www.planit2tcq.co.uk/