This document introduces a simple approach to earned value management for product-based planners. It discusses measuring work completed, time taken, and costs incurred to determine if a project is on track. The document outlines steps to modify an existing product-based plan to include a weighted planned value and earned value calculation for each product. This provides a percentage completion measure over time for reporting progress to stakeholders.
1 of 9
More Related Content
Product Based Earned Value
1. Earned Value
A simple approach for
Product Based Planners
David Willcox
Senior Consultant
IT Project Manager
息 PlanIT 2TCQ Ltd 1 http://www.planit2tcq.co.uk/
2. Are you a fan or a sceptic?
Earned Value is an advanced Project progress monitoring
approach where you measure the work complete, the time
taken and the costs incurred to see if a project is on track
In terms of usefulness it has divided option, some believe it
should always be used because it is the only true way of
measuring overall progress; some believe that the effort
necessary to measure properly outweighs the benefits gained
I have never used it fully myself or seen it fully implemented
despite being involved in some major programmes over the last
20 years
However, I suggest that good product based planners can gain
some of the key benefits for little extra work
I have been testing the concept on a recent project and it
seems to offer benefits including Project Board communication
as people prefer a graph to a dry set of milestones (although I
have used both in progress packs)
息 PlanIT 2TCQ Ltd 2 http://www.planit2tcq.co.uk/
3. Are you a Product Based Planner?
Identifying the Products to be delivered is a cornerstone of
methods such as PRINCE2
It is an excellent planning approach which I always use
Even on its own, it is a way of measuring project progress
However, for a little extra effort, it can be used to measure a
simplified Earned Value representation and give an even
better view of progress
I will take you through step by step on a sample project and
you can see the benefits
息 PlanIT 2TCQ Ltd 3 http://www.planit2tcq.co.uk/
4. Step 1
Normal Product Based Planning
Identify the products, their flow etc.
Estimate the effort to produce and quality assure
Build your plan
Produce a Product Inventory in Excel
Do not forget to include nondocumentproducts
For documents, you record your baseline dates for production of
a draft and for the document to be baselined following full
quality review / signoff
For non documents I have still included a draft date
approximately around 50% through the production cycle
息 PlanIT 2TCQ Ltd 4 http://www.planit2tcq.co.uk/
5. Step 2
Add weighted Planned Value
Add 3 columns to your spreadsheet (you will an example in
a moment)
PV = Valuation of each product (relative factor)
EV% = % of the value of the product earned
EV = PV * EV%
PV needs a bit of thought, for simplicity I use a relative
value of each product. It is a judgement call but I have used
1 when in doubt
Reduced for some management products (but increased for PID
as this is important)
Bigger values for important design docs, software to be used etc
息 PlanIT 2TCQ Ltd 5 http://www.planit2tcq.co.uk/
6. Step 3
How much value by Product Status?
My Product Inventory tracks the following statuses and my
suggested relative value
Not Started = 0%
Being Drafted = 20%
Draft Issued = 50%
Partially Approved = 70%
Approved = 100%
Some simple VLOOKUPS & you have an Earned Value for
each product to be produced
100% of ALL products approved is the total value of the
project
息 PlanIT 2TCQ Ltd 6 http://www.planit2tcq.co.uk/
7. The Project Products Inventory
Project xxxxxx - Key Product Status as at 29/06/2012 33.9 11.4
Draft Draft Draft Fully Fully Fully
Issued Issued Issued Approve Approve Approve
# Gate Name Status Base Fore Actual Base Fore Actual PV EV% EV
1 1Q A-B Feasibility Delivery Approach Approved 15/05/12 15/05/12 16/05/12 16/05/12 1.0 100% 1.0
2 1Q A-B Gate B Investment Case Approved 25/05/12 25/05/12 31/05/12 08/06/12 0.5 100% 0.5
3 1Q A-B High Level Architecture Partially Approved 18/05/12 18/05/12 01/06/12 02/07/12 0.5 70% 0.4
Aligne Book / Trade
4 3D B-C Descriptions Design Approved 01/06/12 01/06/12 15/06/12 22/06/12 3.0 100% 3.0
5 3D B-C Detailed Requirements Draft Issued 12/06/12 21/06/12 22/06/12 05/07/12 1.5 50% 0.8
6 3D B-C Process Map Partially Approved 12/06/12 15/06/12 22/06/12 03/07/12 1.5 70% 1.1
7 3D B-C Inventory of Build Items Partially Approved 15/06/12 22/06/12totals at top02/07/12
See 22/06/12 1.5 70% 1.1
Inventory of Process /
8 3D B-C Procedures to amend Partially Approved 15/06/12 Product relative value of
22/06/12 22/06/12 02/07/12 1.0 70% 0.7
9 3D B-C Business Readiness Plan Partially Approved 15/06/12 3, it is fully approved so
15/06/12 22/06/12 29/06/12 0.5 70% 0.4
10 3D B-C Gate C Investment Case Partially Approved 21/06/12 21/06/12 100% of 3 = 3
EV is 26/06/12 06/07/12 0.5 70% 0.4
11 3D B-C Technical Architecture Design Draft Issued 15/06/12 27/06/12 27/06/12 09/07/12 0.5 50% 0.3
12 3D B-C Project Initiation Document Draft Issued 21/06/12 21/06/12 29/06/12 09/07/12 2.0 50% 1.0
13 4B C-D Test Plan Not Started 06/07/12 20/07/12 1.5 0% 0.0
Reports, Models all built & unit
14 3D B-C tested Being Drafted 20/07/12 27/07/12 5.0 20% 1.0
Processes / Procedures all
15 3D B-C updated & reviewed Not Started 27/07/12 03/08/12 2.0 0% 0.0
16 4B C-D Test Scripts Not Started 20/07/12 03/08/12 2.0 0% 0.0
17 5T C-D Go/No Go Checklist Not Started 20/08/12 28/08/12 1.0 0% 0.0
18 5T C-D Storm Plan Not Started 28/08/12 11/09/12 1.0 0% 0.0
19 5T C-D End of Test Report Not Started 11/09/12 14/09/12 3.0 0% 0.0
Implemented Reports, Models
20 6I C-D etc Not Started 14/09/12 14/09/12 4.0 0% 0.0
21 7H C-D End of Project Report Not Started 05/11/12 12/11/12 0.2 0% 0.0
22 7H C-D Lessons Learnt Report Not Started 05/11/12 12/11/12 0.2 0% 0.0
息 PlanIT 2TCQ Ltd 7 http://www.planit2tcq.co.uk/
8. Step 4
Add Sheet with some running totals
Sort the Inventory by baseline FA Bas Date Tot PV% Tot EV%
16/05/12 2.9% 2.9%
product approved date 31/05/12 4.4%
01/06/12
Use the relative factors to show in 15/06/12
5.9%
14.7%
a table % of PV over time leading 22/06/12 19.2%
22/06/12
to 100% 22/06/12
23.6%
28.0%
Spreadsheet calculates the 22/06/12 31.0%
22/06/12 32.4% 29.5%
totalto date EVas a by-product 26/06/12 33.9%
of updating milestones for 27/06/12 35.4%
29/06/12 41.3% 33.5%
tracking purposes as below and 20/07/12 45.7%
while you are updating product 27/07/12 60.5%
03/08/12 66.4%
status & forecasts, you enter the 03/08/12 72.3%
EV% in the table for the date 28/08/12 75.2%
11/09/12 78.2%
14/09/12 87.0%
Total EV showing at the moment is 11.35 for date 29/06/2012 14/09/12 98.8%
which represents a percentage of 33.5% 12/11/12 99.4%
12/11/12 100.0%
息 PlanIT 2TCQ Ltd 8 http://www.planit2tcq.co.uk/
9. The EV chart for use in reporting
Project xxxx - Earned Value via Products
120.0% As at 29/6 EV% for project is 33%.
Planned to be 41%. Reason -
struggling to get full approval of
100.0% some products produced as large
number of approvers
80.0%
% of Value
Tot PV%
60.0% A lot of planned value when have
implemented - only a little added Tot EV%
during post implementation to
40.0% project closedown
33.5%
29.5%
20.0%
2.9%
0.0%
12
12
12
12
12
12
12
12
12
12
12
12
12
20
20
20
20
20
20
20
20
20
20
20
20
20
5/
6/
7/
8/
8/
0/
0/
6/
7/
9/
9/
0/
5/
/0
/0
/1
/0
/0
/0
/0
/1
/0
/0
/0
/0
/1
16
11
25
05
19
03
31
30
13
27
08
22
17
息 PlanIT 2TCQ Ltd 9 http://www.planit2tcq.co.uk/