The document discusses several risks and open issues for a construction project. Key risks include the terrain possibly retaining water which needs study, ensuring a main contractor signs supply contracts, and potential price fluctuations in cement that require stockpiling. Open issues involve specifications not being met for taps, paint color, window frames and tiles, with solutions such as returning non-compliant items to suppliers. A risk also exists around land acquisition facing local refusal unless additional compensation is provided.
1 of 8
Download to read offline
More Related Content
Group 3 risk & issue (question 7)
1. Unmitigated risks
Terrain suspected to retain a lot of water
To study and report terrain condition
Main Contractor Allegiance
Develop and sign supplier contract
Price fluctuations on cement
Stock-up cement
Open Issues
Taps in the spa area not according to specifications sent to the
supplied last week
The shade of Beige paint is not according to specs and will clash with
the overall design
The windows frames delivered is 1m by 1.5m instead on 1m by 1m
Some window frames are not fitting properly return back to
supplier
The tiles in the sample unit are cracking. Please replace them with
better grade tiles.
Proposed solution : return back to supplier and supplier to deliver
the right specification
Issue with land acquisition. Local refuse to give up
Pay additional compensation
Land acquisition act 1960