The Max Bogl company constructed phases 4, 5 and 6 of the Mushrif Water Reservoir in Dubai, creating the world's largest drinking water reservoir. The $600 million AED project involved building three new water storage tanks with a combined capacity of 820 million liters. Over 26 months, the construction consumed large amounts of materials and utilized up to 2,000 laborers working around the clock. Safety protocols ensured no accidents occurred during the 5 million hours of work to complete the reservoir on schedule and provide crucial water supply to nearby districts of Dubai.
1 of 8
Download to read offline
More Related Content
Mushrif_Water reservoir_Phase_4_5_and_6
1. Progress is built on ideas.
Mushrif Water Reservoir
Phases 4, 5 and 6
3. 3
On the outskirts of Dubai the
world’s largest drinking water
reservoir has been built by
Max Bogl. Dubai Electricity and
Water Authority (DEWA) have
invested approxÂimately 600 mil-
lion AED in the construction
of three new tanks with a
capacity of 820 million litres of
drinking water. The Reservoir
is supplied with water from
the desalination plant located
in the Jebel Ali district 35 km
away. The new Reservoir is
crucial for the water supply to
the close-by districts of Dubai.
During a construction period
of approximately 26Â months
the project has consumed
300,000 m³ of concrete and
30,000 to of reinforced steel.
5,000 m of pipes with diam-
eters of DNÂ 900 up to DNÂ 1,200
have been installed.
Mushrif Water Reservoir
Phases 4, 5 and 6 (180 Million Gallon)
4. 4
The reinforced concrete Reser-
voir is built on a 33 km drain-
age system. The purpose of it
is to observe leak tightness and
to drain potentially accumu-
lated water in order to prevent
structural damages.
Each of the three storage tanks
measures 375 m x 175 m with
a depth of 5,5 m. The Tanks
are partitioned into 4 compartÂ
ments, which are further divid-
ed into 8 smaller sections by
9,500 running metres of run-
ning walls.
Construction Concept
9,500 m running walls
30,000 to of reinforced steel was installed.
5. 5
New pipes and chambers were connected with the existing network.
20,000 pieces
filigran elements
4,500 pieces of precast beams and 6,000 columns were erected.
One million cubic metres of
desert sand was excavated.
6. 6
In order to ensure leak tight-
ness 40 km of waterstop and
300,000 m² PVC membranes
were installed. After com-
pletion of the shell and core
works all tanks underwent a
series of leak tightness tests,
with 65 million litres of water.
A network of approximately
100 fully automated valves
enabled the supervision of the
supply and drain of drinking
water from a centralised con-
trol centre.
Up-to-date measuring instru-
ments allow a fully automated
control of water quality, water
pressure and water levels in
the tanks as well as a CCTV sys-
tem covering the entire site.
7. 7
Tight Program
To achieve the Program
2,000 labourers were work-
ing 24Â hours per day, 7 days
a week. At the peak of
the construction 13 Tower
cranes were operating with
outside temperatures of up
to 50°C. In order to provide
the construction site with
the necessary daily quan-
tity of 1,000 m³ concrete, a
batching plant was erected
directly on site.
Safety
To assure safety for the entire
work force throughout all
construction phases was in-
deed a highly challenging task.
Due to regular site inspec-
tions carried out by safety and
health protection experts and
safety training provided for
all labourers and employees,
5 million working hours were
performed without any inter-
ruptions caused by security-
related accidents.
8. Technical Data
Plant gross area: 1,932,126 m2
Number of Storage Tanks: 3
Measure of each tank: 375 m x 175 m x 5,5 m
Capacity of Storage water: 820 million L
Construction period: 01/2008–02/2010
Client:
Dubai Electricity & Water Authority
Client Consultant Manager PCM:
Nippon Jogesuido Sekkai Consultants NJS
General Contractor:
Max Bogl Emirates Building Contracting LLC
dessign.deblueböne11225703/11
Max Bogl Emirates
Building Contracting LLC
Al Ghaith Holding Tower
11th
Floor, Office – 1114
P. O. Box 62570
Abu Dhabi, UAE
Phone +971 2404-7144
Fax +971 2404-7145
info@max-boegl.com
www.max-boegl.com
Max Bogl Emirates
Building Contracting LLC
Iridium Building
1st
Floor, Office – 127
P. O. Box 125696
Dubai, UAE
Phone +971 4381-4400
Fax +971 4381-4401
info@max-boegl.com
www.max-boegl.com