ºÝºÝߣ

ºÝºÝߣShare a Scribd company logo
Progress is built on ideas.
Mushrif Water Reservoir
Phases 4, 5 and 6
2
3
On the outskirts of Dubai the
world’s largest drinking water
reservoir has been built by
Max Bogl. Dubai Electricity and
Water Authority (DEWA) have
invested approx­imately 600 mil-
lion AED in the construction
of three new tanks with a
capacity of 820 million litres of
drinking water. The Reservoir
is supplied with water from
the desalination plant located
in the Jebel Ali district 35 km
away. The new Reservoir is
crucial for the water supply to
the close-by districts of Dubai.
During a construction period
of approximately 26 months
the project has consumed
300,000 m³ of concrete and
30,000 to of reinforced steel.
5,000 m of pipes with diam-
eters of DN 900 up to DN 1,200
have been installed.
Mushrif Water Reservoir
Phases 4, 5 and 6 (180 Million Gallon)
4
The reinforced concrete Reser-
voir is built on a 33 km drain-
age system. The purpose of it
is to observe leak tightness and
to drain potentially accumu-
lated water in order to prevent
structural damages.
Each of the three storage tanks
measures 375 m x 175 m with
a depth of 5,5 m. The Tanks
are partitioned into 4 compart­
ments, which are further divid-
ed into 8 smaller sections by
9,500 running metres of run-
ning walls.
Construction Concept
9,500 m running walls
30,000 to of reinforced steel was installed.
5
New pipes and chambers were connected with the existing network.
20,000 pieces
filigran elements
4,500 pieces of precast beams and 6,000 columns were erected.
One million cubic metres of
desert sand was excavated.
6
In order to ensure leak tight-
ness 40 km of waterstop and
300,000 m² PVC membranes
were installed. After com-
pletion of the shell and core
works all tanks underwent a
series of leak tightness tests,
with 65 million litres of water.
A network of approximately
100 fully automated valves
enabled the supervision of the
supply and drain of drinking
water from a centralised con-
trol centre.
Up-to-date measuring instru-
ments allow a fully automated
control of water quality, water
pressure and water levels in
the tanks as well as a CCTV sys-
tem covering the entire site.
7
Tight Program
To achieve the Program
2,000 labourers were work-
ing 24 hours per day, 7 days
a week. At the peak of
the construction 13 Tower
cranes were operating with
outside temperatures of up
to 50°C. In order to provide
the construction site with
the necessary daily quan-
tity of 1,000 m³ concrete, a
batching plant was erected
directly on site.
Safety
To assure safety for the entire
work force throughout all
construction phases was in-
deed a highly challenging task.
Due to regular site inspec-
tions carried out by safety and
health protection experts and
safety training provided for
all labourers and employees,
5 million working hours were
performed without any inter-
ruptions caused by security-
related accidents.
Technical Data
Plant gross area:			 1,932,126 m2
Number of Storage Tanks:	 3
Measure of each tank:		 375 m x 175 m x 5,5 m
Capacity of Storage water:	 820 million L
Construction period: 	 01/2008–02/2010
Client:
Dubai Electricity & Water Authority
Client Consultant Manager PCM:
Nippon Jogesuido Sekkai Consultants NJS
General Contractor:
Max Bogl Emirates Building Contracting LLC
dessign.deblueböne11225703/11
Max Bogl Emirates
Building Contracting LLC
Al Ghaith Holding Tower
11th
Floor, Office – 1114
P. O. Box 62570
Abu Dhabi, UAE
Phone 	 +971 2404-7144
Fax 	 +971 2404-7145
info@max-boegl.com
www.max-boegl.com
Max Bogl Emirates
Building Contracting LLC
Iridium Building
1st
Floor, Office – 127
P. O. Box 125696
Dubai, UAE
Phone 	 +971 4381-4400
Fax 	 +971 4381-4401
info@max-boegl.com
www.max-boegl.com

More Related Content

Mushrif_Water reservoir_Phase_4_5_and_6

  • 1. Progress is built on ideas. Mushrif Water Reservoir Phases 4, 5 and 6
  • 2. 2
  • 3. 3 On the outskirts of Dubai the world’s largest drinking water reservoir has been built by Max Bogl. Dubai Electricity and Water Authority (DEWA) have invested approx­imately 600 mil- lion AED in the construction of three new tanks with a capacity of 820 million litres of drinking water. The Reservoir is supplied with water from the desalination plant located in the Jebel Ali district 35 km away. The new Reservoir is crucial for the water supply to the close-by districts of Dubai. During a construction period of approximately 26 months the project has consumed 300,000 m³ of concrete and 30,000 to of reinforced steel. 5,000 m of pipes with diam- eters of DN 900 up to DN 1,200 have been installed. Mushrif Water Reservoir Phases 4, 5 and 6 (180 Million Gallon)
  • 4. 4 The reinforced concrete Reser- voir is built on a 33 km drain- age system. The purpose of it is to observe leak tightness and to drain potentially accumu- lated water in order to prevent structural damages. Each of the three storage tanks measures 375 m x 175 m with a depth of 5,5 m. The Tanks are partitioned into 4 compart­ ments, which are further divid- ed into 8 smaller sections by 9,500 running metres of run- ning walls. Construction Concept 9,500 m running walls 30,000 to of reinforced steel was installed.
  • 5. 5 New pipes and chambers were connected with the existing network. 20,000 pieces filigran elements 4,500 pieces of precast beams and 6,000 columns were erected. One million cubic metres of desert sand was excavated.
  • 6. 6 In order to ensure leak tight- ness 40 km of waterstop and 300,000 m² PVC membranes were installed. After com- pletion of the shell and core works all tanks underwent a series of leak tightness tests, with 65 million litres of water. A network of approximately 100 fully automated valves enabled the supervision of the supply and drain of drinking water from a centralised con- trol centre. Up-to-date measuring instru- ments allow a fully automated control of water quality, water pressure and water levels in the tanks as well as a CCTV sys- tem covering the entire site.
  • 7. 7 Tight Program To achieve the Program 2,000 labourers were work- ing 24 hours per day, 7 days a week. At the peak of the construction 13 Tower cranes were operating with outside temperatures of up to 50°C. In order to provide the construction site with the necessary daily quan- tity of 1,000 m³ concrete, a batching plant was erected directly on site. Safety To assure safety for the entire work force throughout all construction phases was in- deed a highly challenging task. Due to regular site inspec- tions carried out by safety and health protection experts and safety training provided for all labourers and employees, 5 million working hours were performed without any inter- ruptions caused by security- related accidents.
  • 8. Technical Data Plant gross area: 1,932,126 m2 Number of Storage Tanks: 3 Measure of each tank: 375 m x 175 m x 5,5 m Capacity of Storage water: 820 million L Construction period: 01/2008–02/2010 Client: Dubai Electricity & Water Authority Client Consultant Manager PCM: Nippon Jogesuido Sekkai Consultants NJS General Contractor: Max Bogl Emirates Building Contracting LLC dessign.deblueböne11225703/11 Max Bogl Emirates Building Contracting LLC Al Ghaith Holding Tower 11th Floor, Office – 1114 P. O. Box 62570 Abu Dhabi, UAE Phone +971 2404-7144 Fax +971 2404-7145 info@max-boegl.com www.max-boegl.com Max Bogl Emirates Building Contracting LLC Iridium Building 1st Floor, Office – 127 P. O. Box 125696 Dubai, UAE Phone +971 4381-4400 Fax +971 4381-4401 info@max-boegl.com www.max-boegl.com