We enjoyed meeting Saturday with the Ward 5 Brookland Middle School community. If you happened to have missed the meeting or simply wish to share the update and new proposed work hours with your neighbors, friends and family feel free to share! Thanks.
1 of 13
Download to read offline
More Related Content
Brookland Middle School Community Meeting (November 16, 2013)
6. SCHEDULE & WORK HOURS
UPDATE
SCHEDULE
Students and staff to occupy building 2015-16 school year
Construction to complete in January 2015
WORK HOURS
Work to take place during standard DCRA work hours
7AM-7PM Monday through Saturday
No applications for extended work hours
BROOKLAND COMMUNITY MEETING MARCH 23, 2013
7. CONSTRUCTION UPDATE
ACTIVITY SCHEDULE
COMPLETE
Building demolition
Ground improvements
ONGOING & UPCOMING
Concrete foundations and
waterproofing
Steel structure
Geothermal Well Drilling (Requires closure of baseball
field and track from December 1, 2013 April 15, 2014)
BROOKLAND COMMUNITY MEETING MARCH 23, 2013
8. CONSTRUCTION UPDATE
PARK USAGE
WORK ACTIVITY
Ongoing DPR modernization of Turkey Thicket park
Baseball field and track closed during geothermal well drilling and
field restoration
Basketball courts closed during expansion of Turkey Thicket
parking lot and basketball court relocation
Two (2) Tennis courts closest to school not in use during school
structure and fa巽ade work
All eight (8) tennis courts closed during court re-surfacing
BROOKLAND COMMUNITY MEETING MARCH 23, 2013
TIMEFRAME
Present
December 2013
December 2013
April 2014
April 2014
May 2014
Present
October 2014
October 2014
9. CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
STRUCTURE / SKIN
Present December 2013
Two (2) Tennis courts closest to
school not in use during school
structure and fa巽ade work
(Present October 2014)
BROOKLAND COMMUNITY MEETING MARCH 23, 2013
10. CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
GEOTHERMAL & FACADE
December 2013 April 2014
Baseball field and track closed during
geothermal well drilling and field
restoration (Present October 2014)
Two (2) Tennis courts closest to
school not in use during school
structure and fa巽ade work
(Present October 2014)
BROOKLAND COMMUNITY MEETING MARCH 23, 2013
11. CONSTRUCTION UPDATE
CONSTRUCTION ACTIVITY
INTERIORS
May 2013 January 2015
Parking lot expanded and basketball
courts relocated during April & May 2014
BROOKLAND COMMUNITY MEETING MARCH 23, 2013
Tennis courts get resurfaced
in October 2014
12. NEXT STEPS
Next SIT Meeting in December 2013
Focus on interior finishes and design
Resume envelope meetings
Monthly updates to be e-mailed at end of each
month
Community Meeting in February 2014