202nnnn40829_Update Phhjrogres Cabot.pptx
- 3. Engineering
No Area Volume (ton) Start Finish GA Shop Drawing
1 325 67 22-Jul 31-Jul 100% 100%
2 916 27 01-Aug 14-Aug 100% 100%
3 315 - Segmen 1 65 08-Aug 03-Sep 100% 30%
4 315 - Segmen 2 50 08-Aug 03-Sep 45% 0%
5 315 - Segmen 3 40 08-Aug 09-Sep 45% 0%
6 915 12 08-Aug 03-Sep 100% 0%
7 345/450 42 22-Aug 04-Sep 30% 0%
8 335 83 22-Aug 07-Sep 45% 0%
- 4. Fabrikasi & Delivery
No Area Volume (ton) Start Finish Progress Fabrikasi Lokasi Fabrikasi
1 325 67 08-Aug 29-Aug 95% Hanggar 1
2 916 27 21-Aug 04-Sep 15% Hanggar 1
3 315 - Segmen 1 65 26-Aug 22-Sep 3% CFD
4 315 - Segmen 2 50 01-Sep 26-Sep - CFD
5 315 - Segmen 3 40 03-Sep 25-Sep - CFD
6 915 12 30-Aug 10-Sep - Finishing BM
7 345/450 42 06-Sep 30-Sep - Finishing BM
8 335 83 06-Sep 27-Sep - SMS - Cikande
325
Welder : 4 Prsn
Fitter : 6 Prsn
Helper : 8 Prsn
Blaster : 2 Prsn
Painter : 2 Prsn
916
Welder : 2 Prsn
Fitter : 4 Prsn
Helper : 4 Prsn
Blaster : 1 Prsn
Painter : 1 Prsn
315 (1-3)
Welder : 12 Prsn
Fitter : 18 Prsn
Helper : 20 Prsn
Blaster : 6 Prsn
Painter : 6 Prsn
915
Welder : 2 Prsn
Fitter : 4 Prsn
Helper : 4 Prsn
Blaster : 1 Prsn
Painter : 1 Prsn
345/450
Welder : 4 Prsn
Fitter : 6 Prsn
Helper : 8 Prsn
Blaster : 2 Prsn
Painter : 2 Prsn
335
Welder : 6 Prsn
Fitter : 8 Prsn
Helper : 10 Prsn
Blaster : 2 Prsn
Painter : 2 Prsn
Manpower
Delivery (ton)
48
-
-
-
-
-
-
-