際際滷

際際滷Share a Scribd company logo
Welcome
A Seminar on the Basis of the
Construction of Bored Cast-in-Situ Piles
 Subham Kundu (CE - 33)
 Subhankar Karmakar (CE - 34)
 Supriya Chowdhury (CE - 35)
IMPS College of Engineering and Technology, Malda.
 Content:
 INTRODUCTION
 TERMINOLOGY
 PILE CLASSIFICATION
 GENERAL DESCRIPTION OF WORK
 WORKMANSHIP
 PILE COMPRESSION LOAD TEST BY KENTLEDGE SYSTEM
 EXECUTION OF CONSTRUCTION WORKS AT SITE
 PICTURES
 PILE CUT OFF, EXCAVATION AND CLEAN-UP
 THE EQUIPMENTS OF PILING
 VERTICAL PILE LOAD TEST (INITAIL AND ROUTINE)
 (COMPRESSION TEST OF CONCRETE) CUBE TEST
 THE SLUMP TEST OF CONCRETE
 FINENESS MODULUS TEST FOR COARSE AGGREGATE
 REQUIREMENTS OF DRILLING MUD (BENTONITE)
 CONCLUTION
 REFERENCES
 Content:
Introduction:
Classification based on the function
Classification based on material and composition
Terminology:
 Bored Cast In-situ Pile
 Cut-off Level
 Diameter of Piles
 Factor of Safety
 Initial Load Test
 Initial Test Pile
 Load Bearing Pile
 Pile Spacing
 Routine Test Pile
 Safe Load
 Ultimate Load Capacity
 Working Load
 Working Pile
 Negative Skin Friction or Drag down Force
Pile Classification:
 Main Functions of Piles  End Bearing (left) and Friction (right)
General Description Of Work:
 Location
 Piling Work
 Materials
 Dewatering
 Back Filling
 Power and Water
 Period of Completion
Workmanship:
 Control of Piling Installation
 Use of Drilling Mud
 Cleaning of Borehole
 Tremie Concreting
 Defective Pile
 Recording of Data
 Pile Compression Load Test by
Kentledge System :
 General
 Frequency
 Prerequisite
 Method
KENTLEDGE
 Section view of Tension Test Setup using reaction pile
and a Hydraulic jack
 View of Tension Test Setup system
DIAL GUAGE
HYDROLIC PUMP TESTING PILE
Execution of construction
works at site :
 Preliminary Works
 Piling Work
 Steps of Piling
RIG(TRIPOD WITH WINCH)
BAILERCASING
DMC PIPES CHISEL
TREMIE PIPE REINFORCEMENTS
HYDROMETER
HOPPER
COVER BLOCK
CONCRETE MIXING MECHINETOTAL STATION
 Pile Cut Off, Excavation And
Clean-up:
 Pile Cut off Level
 Excavation
 Cleaning of Work Site
PILE CUT OFF
 The Equipments Of Piling :
 Reinforcements (Stirrups & Stiffeners)
 DMC Pipes
 Development Length & Lap Length
 Tremie Pipes
 Chisel
 Bailer
 Casing
 Hopper
 Cement & Admixture
REINFORCEMENTS
Stirrups & Stiffeners
DMC PIPES
TREMIE PIPES
HOPPER
CHISEL
BAILER CASING
 Vertical Pile Load Test
(Initial & Routine) :
 Definition
 Process
TEST PILE
PILE LOAD TEST
LOAD vs SETTLEMENT GRAPH
 Compression Test Of Concrete
(Cube Test) :
 Aim
 Equipments
 Procedure
 Precaution
 Information
 Results
 Judgments
UNIVERSAL TESTING MACHINE
CONCRETE CUBES CUBE MOULDS
 The Slump Test Of Concrete :
 Aim
 Equipments
 Procedure
 Precaution
 Information
 True Slump
 Shear Slump
 Collapse
 Results
 Judgments
SLUMP CONE
MEASUREMENT OF SLUMP SLUMP CLASSIFICATION
 Fineness Modulus of Coarse
Aggregate :
 Aim
 Equipments
 Procedure
 Precaution
 Information
 Results
 Judgments
Sieve
 Requirements Of Drilling Mud
(Bentonite):
 Properties
 Functions
 Requirements
BENTONITE
 Conclusion:
 Bored Cast in situ piling is favourable than other piling processes.
Because there is no waste of time and materials so it is economical and
can be cast into exact length. It can bear heavier load and transfer it to
the ground soil. Also the transportation cost is not high.
 It is not necessary to reinforce the pile in normal cases or in places where
the pile is completely submerged in the soil. But for more stability and
durability of structure we use reinforcement. Over all, Bored cast in situ is
preferable for bearing huge amount of load as it can be cast deep inside
the ground.
References :
 MURTHY V.N.S  SOIL MECHANICS AND FOUNDATION
ENGINEERING
 SHETTY M.S  CONCRETE TECHNOLOGY
 IS 2911 (Part 1/Sec 2) : 2010
Thank You

More Related Content

A Presentation on Bored Cast-in-Situ Piles

  • 2. A Seminar on the Basis of the Construction of Bored Cast-in-Situ Piles Subham Kundu (CE - 33) Subhankar Karmakar (CE - 34) Supriya Chowdhury (CE - 35) IMPS College of Engineering and Technology, Malda.
  • 3. Content: INTRODUCTION TERMINOLOGY PILE CLASSIFICATION GENERAL DESCRIPTION OF WORK WORKMANSHIP PILE COMPRESSION LOAD TEST BY KENTLEDGE SYSTEM EXECUTION OF CONSTRUCTION WORKS AT SITE PICTURES PILE CUT OFF, EXCAVATION AND CLEAN-UP
  • 4. THE EQUIPMENTS OF PILING VERTICAL PILE LOAD TEST (INITAIL AND ROUTINE) (COMPRESSION TEST OF CONCRETE) CUBE TEST THE SLUMP TEST OF CONCRETE FINENESS MODULUS TEST FOR COARSE AGGREGATE REQUIREMENTS OF DRILLING MUD (BENTONITE) CONCLUTION REFERENCES Content:
  • 5. Introduction: Classification based on the function Classification based on material and composition
  • 6. Terminology: Bored Cast In-situ Pile Cut-off Level Diameter of Piles Factor of Safety Initial Load Test Initial Test Pile Load Bearing Pile Pile Spacing Routine Test Pile Safe Load Ultimate Load Capacity Working Load Working Pile Negative Skin Friction or Drag down Force
  • 7. Pile Classification: Main Functions of Piles End Bearing (left) and Friction (right)
  • 8. General Description Of Work: Location Piling Work Materials Dewatering Back Filling Power and Water Period of Completion
  • 9. Workmanship: Control of Piling Installation Use of Drilling Mud Cleaning of Borehole Tremie Concreting Defective Pile Recording of Data
  • 10. Pile Compression Load Test by Kentledge System : General Frequency Prerequisite Method KENTLEDGE
  • 11. Section view of Tension Test Setup using reaction pile and a Hydraulic jack View of Tension Test Setup system
  • 12. DIAL GUAGE HYDROLIC PUMP TESTING PILE
  • 13. Execution of construction works at site : Preliminary Works Piling Work Steps of Piling
  • 19. COVER BLOCK CONCRETE MIXING MECHINETOTAL STATION
  • 20. Pile Cut Off, Excavation And Clean-up: Pile Cut off Level Excavation Cleaning of Work Site PILE CUT OFF
  • 21. The Equipments Of Piling : Reinforcements (Stirrups & Stiffeners) DMC Pipes Development Length & Lap Length Tremie Pipes Chisel Bailer Casing Hopper Cement & Admixture
  • 24. Vertical Pile Load Test (Initial & Routine) : Definition Process
  • 25. TEST PILE PILE LOAD TEST LOAD vs SETTLEMENT GRAPH
  • 26. Compression Test Of Concrete (Cube Test) : Aim Equipments Procedure Precaution Information Results Judgments UNIVERSAL TESTING MACHINE
  • 28. The Slump Test Of Concrete : Aim Equipments Procedure Precaution Information True Slump Shear Slump Collapse Results Judgments SLUMP CONE
  • 29. MEASUREMENT OF SLUMP SLUMP CLASSIFICATION
  • 30. Fineness Modulus of Coarse Aggregate : Aim Equipments Procedure Precaution Information Results Judgments Sieve
  • 31. Requirements Of Drilling Mud (Bentonite): Properties Functions Requirements BENTONITE
  • 32. Conclusion: Bored Cast in situ piling is favourable than other piling processes. Because there is no waste of time and materials so it is economical and can be cast into exact length. It can bear heavier load and transfer it to the ground soil. Also the transportation cost is not high. It is not necessary to reinforce the pile in normal cases or in places where the pile is completely submerged in the soil. But for more stability and durability of structure we use reinforcement. Over all, Bored cast in situ is preferable for bearing huge amount of load as it can be cast deep inside the ground.
  • 33. References : MURTHY V.N.S SOIL MECHANICS AND FOUNDATION ENGINEERING SHETTY M.S CONCRETE TECHNOLOGY IS 2911 (Part 1/Sec 2) : 2010