Active beams provide low maintenance cooling and heating through passive technology. They require low airflow which saves fan energy. During start-up, protective films must remain on beams until spaces are clean to prevent fouling. Commissioning involves carefully lowering secondary water temperatures, balancing primary airflow, and confirming water conditions to ensure proper operation. Active beams are a versatile solution that can be tailored for various space requirements with energy savings benefits.
1 of 49
Downloaded 45 times
More Related Content
Active Beam Commissioning Overview
1. OPERATION & COMMISSIONING OF
ACTIVE BEAMS
Twa Panel Systems Inc.
1201 4th Street
Nisku, AB
Canada, T9E 7L3
(780)-955-8757
www.twapanels.ca
6. Introduction to Active Beams
De-coupled ventilation systems
Energy Usage Noise Level Output Comments
Adaptable
Fan Coil Units Medium/High Medium 32-64 Btuh/ft2
solution
VAV Systems Very efficient
Low Low/Medium 32-64 Btuh/ft2
all-air system
VRV System
(Variable Possible high
Refrigerant High Medium 48-64 Btuh/ft2 maintenance
Volume) costs
Very low
Active Beams
Low Low 32-125 Btuh/ft
2
maintenance
costs
8. Introduction to Active Beams
Active beam benefits
1) Lower overall air volume processed by the primary air handling unit. (0.25-0.5 cfm/ft2)
2) Higher entering chilled water temperatures: (55属F-61属F).
3) Lower hot water temperatures: Select beams for cooling duty, then choose
appropriate hot water temperature for heating.
(i.e. usually less than 120属F. Beam discharge air
should be less than 15oF warmer than room design
temperature to limit the risk of stratification.
4) Suitable for use with water-to-water heat pumps, and has the potential to double the
COP of a dedicated chiller loop.
5) Self regulating secondary capacity: Approach = Room Temperature - Supply water
temperature
6) VAV control: Can be used to strictly limit room air velocity, provide linear
temperature control, and additional fan energy savings for areas with
highly variable latent loads.
(i.e. Labs, Boardrooms, coffee rooms, classrooms, etc)
10. Introduction to Active Beams
Psychrometrics
Option 1 Option 2
Primary air dew
48属F 51.5属F
point
Room air dew
55属F 57.8属F
point
Secondary CWT 55属F 58属F
Dehumidification 0.002 lbs/lbDA 0.002 lbs/lbDA
RESET FOR ENERGY
SAVINGS!
11. Introduction to Active Beams
Condensation risks
Areas of greatest condensation risk:
1) Near points of entry to the building
4)At the perimeter, with mixed-mode ventilation
5)Structures with poor building envelopes, including retrofit applications
6)In areas with highly variable latent loads:
Board rooms
Lunch / coffee rooms
Etc
Condensation prevention strategies may include:
10)De-activation of secondary chilled water supply, by zone, via loss of dew-point from
sensors mounted to CWS lines. ( or via combination: DB / RH zone stats, or
other)
2) Tempering secondary chilled water supply by zone via:
Three-way mixing valve
Injection pumps
3) Etc
12. Introduction to Active Beams
DOAS Information Resource
1) http://doas.psu.edu/
2) Not all primary air handling systems are DOAS!
13. Introduction to Active Beams
Placement within the ceiling
P2 drops rapidly
moving into the
room
P3 = 遜 at 3ft into
occupied zone
15. Introduction to Active Beams
Beam acoustics
Chart reports
acoustic values
without room
attenuation
effect
Active beams can
be very quiet!
16. Introduction to Active Beams
1/3rd Octave band analysis
Owens Corning Acoustic Testing
Acoustic test standards may include:
ISO3741
ASHRAE Std. 70
Reverberant chamber (No Attenuation)
Manufacturer A = Worst Case
2 x 8 D nozzle @ 1.20w.c.
Peak in the 2.5 KHz Band
Lw (dB) = 39.1
LwA (dBA) = 38.8
NC = 24 !
18. Installation and maintenance
Fastening beams to the structure
Upstream damper
at SMACNA
recommended
minimum distance
Drywall
N.B. - Include seismic restraint
where required by code
21. Installation and maintenance
Installation Tips
1. Rough-in: piping, ducting, concrete threaded inserts, and beams, prior
to T-bar installation. Lower beams into T-bar for final positioning.
3. Store beams on-site indoors whenever possible, in a low traffic area, and
otherwise covered for protection from the elements.
5. Leave plastic film on each unit to minimize site damage, and prevent coil
/ unit fouling.
7. Match beam label to schedule; - beams look alike! Confirm that the right
beam is in the right room. Contractor suggestion: - Confirm packing slip
matches shop drawing requirements upon receipt of material.
9. Limit flexible duct to no more than 10. Avoid sharp turns in ductwork.
22. Installation and maintenance
Installation Tips
1. Plan for access doors, and possibly welded-aluminum frames, with beams
mounted in dry-wall ceilings.
3. Manage glazing surface temperatures by planning discharge
configuration. With high quality glass, beams which discharge
perpendicular to the glazing, are typically preferred.
5. Stainless steel flexible hoses allow for some adjustment within the ceiling
grid.
23. Installation and maintenance
Sample active beam packaging
nits remain as-new
until final
commissioning
and turn-over.
ecyclable packaging
materials.
ace-to-face, and back-
to-back crating mini-
mizes shipping damage.
25. Installation and maintenance
IOM and precautions
ead the manufacturers Installation Operation and Maintenance Manual
ay particular note of any precautions which have been identified as high
risk conditions. (i.e. minimum two people to handle beams 6 and larger,
pulling on un-latched door may cause hardware failure, be cautious of
sharp edges, limit flex duct connections to 10 maximum, etc)
o NOT circulate water through the beam mounted coil until the mains
have been properly de-greased / flushed.
o NOT remove protective plastic film from beam body until the space has
been appropriately cleaned, to minimize fouling of the coil
O lower the secondary chilled water temperature slowly to limit the risk of
condensation damage during start-up.
26. Installation and maintenance
Coil maintenance
ctive beams require practically no maintenance. If the coil remains dry, as
expected, there is very little risk of fin bridging.
ecommended cleaning schedules typically involve lowering, or removing
the perforated doors / panels, in front of unit mounted coil, at 6-Months,
and 1-Yr., to establish a maintenance schedule. Areas with higher airborne
contamination require more frequent cleaning.
ften, cleaning schedules can extend to between 3-5 years in spaces subject
to weekly housekeeping.
igher housekeeping frequency, reduces the intervals between coil
28. Installation and maintenance
Unit cleanliness prior to start-up
eave active beams wrapped to prevent fouling unit or coil.
ipe unit with a damp rag to remove surface dirt, or vacuum with a horse-
hair bristle brush.
o NOT scrub the paint. Damage to the finish may occur.
soft bristle brush and mild detergent with water, can be used to remove
stubborn smudging, if required.
eams ship with repair kits for surface scratched units. Do NOT spray the
unit directly with spray-bomb type matched paint. Use artist paint
30. Air-side control and measurement
Ducting for equal static pressure
Pt = Ps + Pv
Pt = total pressure (w.c.)
Ps = static pressure (w.c.)
Pv = velocity pressure (w.c.)
If velocity pressure is kept negligibly low, then the same static pressure will
hold throughout the duct. ( i.e. Only if transport loss can be neglected).
Pv = 0,5 x r x v2
Pv = velocity pressure (w.c.)
r = air density (0.075 lbs/ft3)
v2 = air velocity (fpm)
At < (590 fpm) duct air velocity Pv < (0.02w.c.)
At < (590 fpm) transport
= (5) < (0.001w.c/ft.)
= (8) < (.0007w.c./ft.)
Low air volumes required for beams makes using round ducting practical
and low air velocity achievable.
31. Air-side control and measurement
Vary primary air pressure for capacity control ?
AV primary air flow is
typically simple with
arying the plenum pressure
orifice plate Iris type
yields a non-linear capacity
response. Tight control
with variable plenum
dampers.
pressure is typically
impractical.
32. Air-side control and measurement
Vary primary air pressure for capacity control ?
33. Air-side control and measurement
Recommended CAV damper types
Iris Dampers
(angled multi-leaf blades)
Pressure independent
butterfly type
Iris Dampers
34. Air-side control and measurement
Damper Tips
ize dampers for flow and pressure drop.
i.e. Do NOT oversize the damper by simply installing a nominal duct
diameter damper. Check range of flow control, step-down if required.
enturi style dampers are typically only used with labs, and narrow-band
pressurization control.
heck for flow generated noise with larger pressure drops.
Add duct silencers if necessary.
onsider VAV air valves for spaces with highly variable latent loads.
Be aware of additional control requirements
Consider occupancy type (i.e. 2-position) air valves for these spaces
in an effort to manage control costs.
35. Air-side control and measurement
Acoustics
atch for flow generated noise across Iris damper.
dd duct mounted silencers if required.
36. Air-side control and measurement
Balancing and confirmation
eams are considered a constant volume device. Apply a known plenum
static pressure, and the cross-sectional area of each nozzle sums to yield
the total primary air delivered by the beam. Adjust orifice P for beams
of common pressure; - their nozzle determines the primary air flow rate.
ince the induction ratio is exceedingly difficult to field measure, the most
accurate means of determining the primary air delivery, is to rely on the
manufacturers plenum pressure vs. volume relationship, which is typically
measured with a precision orifice. Confirmation of zone flow rates can be
accomplished via a duct traverse at a node of common intersection.
low hoods cannot be used to determine total air flow into the space due
to the recirculation component of the room air.
37. Air-side control and measurement
Challenges
ominal duct size vs. P across Iris dampers.
oning to minimize capital costs.
ight-time set-back.
imultaneous perimeter heating with core cooling.
ir-side free-cooling.
ew-point control.
39. Water-side control and measurement
Self-regulating thermal capacity
Example 1
(1365 Btuh) Room Temp = 75oF
Water temp = 61oF
Approach temp = 75oF-61oF
= 14oF
Capacity = X
(682 Btuh)
Room Temp = 68oF
Water Temp = 61oF
Approach temp = 68oF-61oF
= 7oF
Capacity = 1/2X
40. Water-side control and measurement
Modulating water flow
Turbulent
flow
Laminar
flow
Single circuit water flow Temperature controlled water
Non-linear Restricted to zone control
Expensive Expensive
Maintenance issues? Maintenance issues?
41. Water-side control and measurement
Challenges
ater-side free cooling
oning
hilled water reset by zone
alve authority
(Ensure that the control valves are sized based on Cv, NOT
line size)
42. Water-side control and measurement
Tips for easier commissioning
se pressure independent flow regulating valves
everse-return piping can sometimes make life easier in each zone
pply venting liberally
ressure independent
water control valve
(Constant Flow
Rate)
44. Start-up
Sample start-up sequence
onfirm start-up and operating sequence with the: plans, specifications, and
consulting engineer.
onfirm primary air ducting is free of dirt and debris to prevent beam nozzle
clogging.
eal all duct leaks, and ensure all duct access ports are affixed to the duct to
achieve specified duct leakage rates.
lit protective film at the active beam discharge to allow primary air to enter the
space. Do NOT remove the protective film, until the work space is in an as-
45. Start-up
Sample start-up sequence (contd)
o NOT operate the active beams for temporary heat without prior written
approval from the consulting engineer.
lose all operable windows, and ensure building exit doors are sealed to assist in
the envelope dehumidification.
ommission and operate the primary air handling unit for building envelope
dehumidification.
alance supply air ducting to each zone.
46. Start-up
Sample start-up sequence (contd)
nsure a clean environment within which the active beams will operate (i.e. no
gypsum dust or other construction contamination)
emove protective film from active beam units
nsure piping mains have been flushed and leak-tested, prior to being
connected to the beam coils
O NOT UNDER ANY CIRCUMSTANCES FLUSH THE PIPING SYSTEM
THROUGH THE BEAM MOUNTED COILS.
47. Start-up
Sample start-up sequence (contd)
onfirm that all air has been removed from the distribution piping. Deliver excess
water by increasing the pump flow, or by closing other zones to assist in the
removal of air from the system.
nce the building envelope dew point has been reached, slowly lower the
secondary chilled water temperature to the scheduled design value. Note that
dehumidifying the building envelope may require several days, or up to a week
initially, to completely dehumidify the space.
onfirm secondary water conditions regularly to ensure that it is properly filtered,
and appropriately inhibited.