This document outlines the timeline for completion of the Orange Line Metro Train project in Lahore, Pakistan. Key details include a total length of 27.1 km, with 25.4 km as elevated viaduct and 1.71 km as cut-and-cover section. The timeline lists 39 activities from commencement of the project to testing and commissioning, assigning responsibility and planned/expedited/highly accelerated dates. Critical activities that could advance the project if expedited include construction of stations and girders, track laying, and installation of power, signaling and other systems. The planned timeline is 27 months, while expedited is 24 months and highly accelerated is 20.75 months for completion.
1 of 7
Downloaded 15 times
More Related Content
Activities - Presentation (NESPAK) v1.6
1. GOVERNMENT OF THE PUNJAB
ORANGE LINE METRO TRAIN TIMELINES
NATIONAL ENGINEERING SERVICES
PAKISTAN (PVT) LIMITED
THE PUNJAB METRO BUS AUTHORITY
June 2015
1
2. Introduction
• Total Length = 27.1 km
• Elevated Viaduct = 25.4 km
• Cut & Cover Section = 1.71 km
• Elevated Stations = 24
• Underground Stations = 2
• Date of Commencement of Project = Date of Advance Payment to CR-NORINCO = 1-8-2015
2
3. Timelines for Orange Line …. Contd.
3
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
1
Info about Survey + Geotech Requirements from CR-
NORINCO
CR-NORINCO 0.5 months
from contract signing date
(21.4.15)
7-5-2015
(received)
---- ----
2 Preparation of EIA Report NESPAK 0.5 months
from contract signing date
(21.4.15)
7-5-2015
(already submitted)
---- ----
3
Preparation and Approval of main PC-1 (Based on preliminary
design)
NESPAK / PMA 0.75 months
from contract signing date
(21.4.15)
15-5-2015
(already approved)
---- ----
4
Preparation of second PC-1 for Misc. Items (Based on
estimated costs)
NESPAK 1.25 months
from contract signing date
(21.4.15)
30-5-2015
(submitted to PMA)
---- ----
5 Prequalification of Civil Contractors LDA 1 month after approval of PC-1 15-6-2015 ---- ----
6 Topographic Survey NESPAK 1 month
from info received from CR-
NORINCO
7-6-2015
(already submitted)
---- ----
7 Information about Underground Utilities LDA 15-6-2015
8 Preparation of Utility Relocation Plans
LDA/WASA/
SNGPL/LESCO
30-6-2015
9 Geotech Investigation NESPAK 1.5 months
from info received from CR-
NORINCO
21-6-2015
(already submitted)
---- ----
4. Timelines for Orange Line …. Contd.
4
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
10
Info about Land Acquisition and Relocation of Facilities
from CR-NORINCO
CR-NORINCO 0.5 months
from topographic survey
and utility plan submission
7-7-2015 ---- ----
11 Time for Public Hearing after EIA Report submission EPA 2.0 months
from EIA Report
Submission
7-7-2015 ---- ----
12
Concept Design of Civil and E&M works by CR-
NORINCO
CR-NORINCO 0.5 months from commencement date 15-8-2015 ---- 30-6-2015
13 Review and Approval of Civil and E&M Concept Design NESPAK 1.5 months from commencement date 15-9-2015 ---- 7-7-2015
14 Preliminary Design of Viaduct NESPAK
0.5 - 2.0
months
from commencement date 30-9-2015 ---- 10-7-2015
15 Preliminary Design of Cut & Cover Section NESPAK
0.5 - 2.0
months
from commencement date 30-9-2015 ---- 10-7-2015
16 Preliminary Design of Elevated Stations NESPAK
0.5 - 2.0
months
from commencement date 30-9-2015 ---- 10-7-2015
17 Preliminary Design of Underground Stations NESPAK
0.5 - 2.0
months
from commencement date 30-9-2015 ---- 10-7-2015
5. Timelines for Orange Line …. Contd.
5
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
18 Preliminary Design of Depots / Stabling Yards NESPAK
0.5 - 2.0
months
from commencement
date
30-9-2015 ---- 10-7-2015
19 Preliminary Design of Substation NESPAK
0.5 - 2.0
months
from commencement
date
30-9-2015 ---- 10-7-2015
20
Preliminary Civil Design and layout drawings
submission to CR-NORINCO
NESPAK 2 months
from commencement
date
30-9-2015 ---- 10-7-2015
21
Requirements of E&M from Contractor for Detailed Civil
Design
CR-NORINCO 3 months
from commencement
date
30-10-2015 ---- 13-7-2015
22 Preparation of Tender Design for Civil-works and Tender NESPAK / LDA 0.5 months
after E&M info from CR-
NORINCO
15-11-2015 ---- 15-7-2015
23 Evaluation and Award of Civil Contract LDA / NESPAK 0.5 months after Tender 30-11-2015 ---- 7-8-2015
24
Final Civil Design and provision of drawings to CR-
NORINCO
NESPAK 5 months
from commencement
date
30-12-2015 ---- 30-10-2015
25
Detailed design of E&M system furnished by CR-
NORINCO
CR-NORINCO 10 months
from commencement
date
30-5-2016 ---- 30-12-2015
6. Timelines for Orange Line …. Contd.
6
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
26
Construction of the sections from the throat area to
building at Depot and Stabling Yard
LDA / NESPAK 10 months from commencement date 30-5-2016 ---- 15-3-2016
27 Review and approval of detailed design of E&M system NESPAK 11 months from commencement date 30-6-2016 ---- 30-1-2016
28
Provision of Civil-works in sections for Track Laying
Base
LDA / NESPAK 8.5 months after award of civil contract 15-8-2016 ---- 21-5-2016
29
Start of Construction of the track laying base by CR-
NORINCO
CR-NORINCO
12.5
months
from commencement date 15-8-2016 ---- 21-5-2016
30
Completion of Construction of buildings and other
sections at Depot and Stabling Yard
LDA / NESPAK
13 months
9 months
from commencement date
after award of civil contract
30-8-2016 ---- 30-5-2016
31 Completion of Cut and Cover with subgrade works LDA / NESPAK
14.5
months
10.5
months
from commencement date
after award of civil contract
15-10-2016 ---- 30-6-2016
32 Provision of External 132KV Power Supply by Employer PMA / LDA 15 months from commencement date 30-10-2016 ---- 30-6-2016
33
Completion of Construction of Cast-in-situ U-type girder
and continuous girder **
LDA / NESPAK
16.5
months
12.5
months
from commencement date
after award of civil contract
15-12-2016 15-10-2016 15-7-2016
7. Timelines for Orange Line …. Contd.
7
Sr. # ACTIVITY RESPONSIBILITY TIME FOR ACTIVITY (Months)
PLANNED /
AGREED DATES
EXPEDITED
DATES
HIGH ACCELERATION
DATES
34 Completion of Construction of Stations ** LDA / NESPAK
18.5
months
14.5
months
from commencement date
after award of civil contract
15-2-2017 15-10-2016 15-7-2016
35 Completion of Erection of U-type Girders ** LDA / NESPAK
19 months
15 months
from commencement date
after award of civil contract
28-2-2017 30-10-2016 30-7-2016
36
Provision of working conditions for other E&M system according to
interface table requirement (Power Supply Signaling Telecom AFC
PSD & APG HVAC Escalator & Elevator Fire Fighting Water Supply
& Drainage Illumination BAS FAS FES Depot & Stabling Yard
equipment)
LDA / NESPAK
12TH
- 19TH
months
from commencement date
1-8-2016 to
30-3-2017
----
15-5-2016 to
30-11-2016
37 Track Laying ** CR-NORINCO 23 months from commencement date 30-6-2017 30-3-2017 30-12-2016
38
Installation of Power Supply System, Communication,
Signaling, and other E&M Systems **
CR-NORINCO 24 months from commencement date 30-7-2017 30-4-2017 30-1-2017
39 Testing and Commissioning CR-NORINCO 27 months from commencement date 30-10-2017 30-7-2017 23-3-2017
** Critical Activities : Time saved here, if possible will advance the project completion date.
Time for
Completion
27 months
Time for
Completion
24 months
Planned / Agreed time for Civil-Works = 6 months to 15 months
Expedited time for Civil-Works = 6 months to 11 months
High Accelerated for Civil-Works = 6 months to 10.5 months
Time for
Completion
20.75 months
Inauguration
March 23, 2017