High Performance
Computing
The Challenge
3 months on site to deliver a highly
efficient Tier 3 data centre



                                   .. in partnership with ARM
The Challenge
Only eight weeks to obtain planning permission




                                 .. in partnership with ARM
The Challenge
Guaranteed annual PUE of below 1.20




                                .. in partnership with ARM
The Challenge
Significant onsite space constraints




                                  .. in partnership with ARM
DAY 1
                              Work begins on site
                              The clock is ticking!




.. in partnership with ARM                           2bm.co.uk
Early progress
                              Data Centre floor prepared




.. in partnership with ARM                           2bm.co.uk
Concrete slab poured
                              and ready




.. in partnership with ARM                          2bm.co.uk
Meanwhile preparatory
                              work continues apace for
                              the cooling plant




.. in partnership with ARM                           2bm.co.uk
New cable runs required
                              for new generators and
                              & UPS




.. in partnership with ARM                             2bm.co.uk
start of new diverse
                              power cable installation




.. in partnership with ARM                              2bm.co.uk
Week 2
                              Ground works for
                              containerised generator
                              and UPS




.. in partnership with ARM                             2bm.co.uk
New home for super low
                              transformer




.. in partnership with ARM                            2bm.co.uk
Support structure goes
                              in for generators and
                              UPS containers




.. in partnership with ARM                            2bm.co.uk
Meanwhile off-site
                              fabrication work carries on


                              UPS container in production




.. in partnership with ARM                            2bm.co.uk
Off-site fitting out of UPS
                              container to ensure
                              timescales are met




.. in partnership with ARM                                 2bm.co.uk
Ready to be delivered
                              to site




.. in partnership with ARM                           2bm.co.uk
Cooling towers are not far
                              behind




.. in partnership with ARM                            2bm.co.uk
Modular pre-assembled
                              design




.. in partnership with ARM                           2bm.co.uk
Data centre structure
                              taking shape.




.. in partnership with ARM                           2bm.co.uk
Work progressing well
                              despite the best efforts of
                              the winter weather




.. in partnership with ARM                             2bm.co.uk
Structure in place.
                              work begins on interior
                              room cladding




.. in partnership with ARM                          2bm.co.uk
.and the cooling system




.. in partnership with ARM                          2bm.co.uk
Individual tap-offs to serve
                              each cabinet door




.. in partnership with ARM                             2bm.co.uk
Co-ordinated programme
                              300 tonne crane arrives to
                              lift in generators, UPS, cooling
                              towers and transformers




.. in partnership with ARM                               2bm.co.uk
UPS container is first to be
                              craned in




.. in partnership with ARM                             2bm.co.uk
Generators in place




.. in partnership with ARM                         2bm.co.uk
Cooling towers in position




.. in partnership with ARM                           2bm.co.uk
New temporary road also
                              required for access and
                              egress




.. in partnership with ARM                             2bm.co.uk
Pipework for cooling
                              towers and LPS system




.. in partnership with ARM                           2bm.co.uk
Main flow and return
                              Pipework with redundant
                              circuits




.. in partnership with ARM                             2bm.co.uk
Main pipework installation
                              nearing completion




.. in partnership with ARM                           2bm.co.uk
Generators and UPS fully
                              possitioned




.. in partnership with ARM                          2bm.co.uk
Internal fit out ongoing.
                              raised floor starts




.. in partnership with ARM                            2bm.co.uk
.and is quickly in place




.. in partnership with ARM                               2bm.co.uk
Installation of the first
                              of 60 cabinets is started




.. in partnership with ARM                               2bm.co.uk
Innovative real door cooling
                              in place




.. in partnership with ARM                            2bm.co.uk
12 weeks in
                              job complete




.. in partnership with ARM                   2bm.co.uk
Fully integrated solution




.. in partnership with ARM                               2bm.co.uk
with new roads for access




.. in partnership with ARM                          2bm.co.uk
Exceeding Expectations
Not only did we construct a Tier3 HPC data centre
in phenomenal time, we still pushed the boundaries of
innovation and efficiencies, ensuring 2bm provided
one of the most energy efficient data centres possible
                                  .. in partnership with ARM
Award Winning Solution
UK IT Industry Awards 2012  Data Centre Project of the Year
European Award for New Data Centre Facility 2012
First ever CEEDA gold accreditation




                                  .. in partnership with ARM