The document discusses efforts to reduce short terry defects in weaving from 1210 PPM to 968 PPM by August 8, 2014. It outlines the TPM project including forming a team, establishing a baseline and target, analyzing causes of defects, and developing an activity plan. Key activities included identifying abnormal conditions through a Fuguai register, analyzing tension variations and gripper issues, and implementing countermeasures like repairs, adjustments and part replacements. The goal was to standardize processes and equipment conditions to sustain the quality improvements.
1 of 49
Downloaded 94 times
More Related Content
ASHISH GUPTA CN3343 THT2(WEAVING)
1. TPM is our way of life
TPM
To Reduce Short Terry In Weaving
From 1210 PPM To 968 PPM in
THT-2, Till 08th August, 2014
Ashish Kumar Gupta
CN 3343
THT-2, Weaving/Production
5 April 2015 1
2. TPM is our way of life
TPM
5 April 2015 2
Crack
10%
Cheera
25%
Float
13%
Lining
3% Short Terry
17%
Selvage damage
9%
Others
13%
C-grade
10%
Average percentage contribution to total downgrade from FF-2 ,THT-2 for
BSC-1, BSC-2 & BSC-3
Grand Total downgrade = 3.46%
Total FF-2 downgrade = 0.68%
Short terry = 0.12%
3. TPM is our way of life
TPM
5 April 2015 3
Why this project is being undertaken?
Short terry is one of the major
problem of terry towel. It contribute
17% of total downgrade percentage
which is second highest downgrade in
FF-2, THT-2.
4. TPM is our way of life
TPM
STEP-0
5 April 2015 4
5. TPM is our way of life
TPM
TPM KK Project Registration
Unit THT - 2 Loss Loss 7: Quality loss
Project Name To reduce short terry in weaving from 1210 PPM to 968 PPM in FF-2, THT-2, till 08 August, 2014
Project Leader Ashish Kumar Gupta Project Guide Mr. Ajit Parandekar
Team Members
Member Name
Mr. Taj Afzal
(Weaving)
Mr. Prabhat
kumar
(Weaving)
Mr. A.P. Singh
(Maintenance)
Mr. Sunil
Arora
(R&D)
Mr. Narottam
kumar
(Weaving)
Mr. Iqbal
Singh
(Maintenance)
Sal. Code M30858 P04114 A37951 S49640 n43437 I43032
Baseline (Primary Metric) 1210 ppm Target (Primary Metric ) 968 ppm
Financial impact Calculation Method/Formula =(Baseline - Actual/Target)% * CSP Packed production * Downgrade Cost 150
Project Start Date 09/06/2014 Target Completion Date 08/08/2014
Remarks & Sign.
Unit Head
Remarks & Sign.
Project Leader
Remarks & Sign.
KK Pillar Head
Remarks & Sign.
MIS & Costing Representative
Mr. Lalit Kaushal Ashish Kumar Gupta Amit Mandal Deepak Garg
L06158
CN3343 A52202 D06799
Step 0.1
5 April 2015 5
6. TPM is our way of life
TPM
KK Project Team Details
Project Name :To reduce short terry in weaving from 1210 PPM to 968 PPM in,THT-2, till 08, August 2014
Team Leader : Ashish Kumar Gupta
Team Members :-
S No. Member Name Responsibility Description
1 Mr. A.P. Singh
To give an incite into the
details of the looms, to
impart thorough knowledge
about the machines
1) To understand and reach to the minute details and
settings of the air jet looms
2) To understand the machine related causes of the defects
and to achieve standardized settings
2 Mr. Taj Afzal
To understand the whole
process from production
point of view
1)To understand the production process as a whole
2) To understand hurdles and bottlenecks in the process
3) To conduct trials to eliminate abnormalities
3 Mr. Prabhat Kumar
To provide all weaving
related data
To give the data and day to day downgrade detail and other
weaving related information.
4 Mr. Sunil Arora
To give an incite into the
quality of the raw materials,
to get predictions and to
help understand quality
matrix
To help study, analyze and understand the data to identify
quality related issues causing defects
5 Mr. Narottam Kumar
To understand the weaving
process
To understand the weaving mechanism and defect related to
terry towel.
6 Mr. Iqbal Singh
To understand the maintenance
related aspects of the
machinery
1) To conduct maintenance and machine related trials
2) To identify the flaws in maintenance process causing defects
Step 0.2
5 April 2015 6
7. TPM is our way of life
TPM
TPM KK Activity Plan
Project Name : To reduce short terry in weaving from 1210ppm to 968ppm
Owner Name :Ashish Kumar Gupta
Week (BSC) -->
S No. Activity Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19
Step
0 1) Select and register topic
P
A
2) Form project team
P
A
3) Plan activities
P
A
Step
1
1) Identify bottleneck
processes
P
A
2) Measure failure/defects
and other losses
P
A
3) Use baseline (bench
mark) to set targets
P
A
Step
2
1) Thoroughly study
,expose and eliminate
abnormalities
P
A
2) Establish basic
conditions equipment
P
A
Step 0.3
5 April 2015 7
8. TPM is our way of life
TPM
TPM KK Activity Plan
Project Name : : To reduce short terry in weaving from 1210ppm to 968ppm
Owner Name :Ashish Kumar Gupta
Week (BSC) -->
S No. Activity Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19
Step
3
1) Stratify and analyze the
causes
P
A
2) Apply analytical methods
P
A
3) Conduct experiments see if
root causes are applicable or not
P
A
Step
4 1) Implement improvements
P
A
2) Perform tests and trial runs
P
A
3) Provide instructions to work
on improved equipments,
operating conditions
P
A
Step
5
1) Evaluate results with time as
improvement project goes on
P
A
2)Check whether target has
been achieved or not/if not start
from step 3 again
P
A
Step 0.3
5 April 2015 8
9. TPM is our way of life
TPM
TPM KK Activity Plan
Project Name : : To reduce short terry in weaving from 1210ppm to 968ppm
Owner Name :Ashish Kumar Gupta
Week (BSC) -->
S No. Activity Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 17 Week 18 Week 19
Step
6
1) Evaluate Results against
target
P
A
2) Check whether target
has been achieved or not
P
A
Step
7
1) Prepare inspection and
work standards
P
A
2) Make drawings and feed
into DM Pillar
P
A
3) Train members to
sustain results
P
A
Step 0.3
5 April 2015 9
10. TPM is our way of life
TPM
STEP-1
5 April 2015 10
11. TPM is our way of life
TPM
Flow Chart
Process Name : Weaving Date : 18/06/2014
Conclusion/ Way Forward : Weaving is the bottleneck for formation of Short terry. And further study based on mainly
weaving.
Prepared By : Ashish kumar gupta Approved By :Mr. Ajit Parandekar
Step 1.1
5 April 2015 11
Winding Warping
Creeling of
warper beam
If, stripe
pattern/dyed
yarn
Weaver beam
prepared
Sow box
Sectional
Warping
Direct
Warping
No
Yes
Cloth
doffing
Weaving Knotting
Grey
folding
12. TPM is our way of life
TPM Step 1.2
Check-Sheet
Process Name : Weaving Name of the investigator : Ashish Kumar Gupta
Location of Data Collection : R&D Date & time: From 1st
week to 13th
week
Why this data is collected : To know about all the weaving defect
Defect Type/
Event Occurance
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Average
# 1 Cheera 1403 1000 1128 1179 1158 2029 1797 1568 1285 2419 2032 2292 1590 1606
# 2 Short terry 790 957 591 534 304 1377 1299 1181 1544 1990 1551 1844 1772 1210
# 3 Crack 544 659 394 374 314 826 847 881 1240 1204 823 1717 841 820
# 4 Float 439 701 139 239 280 515 672 306 234 535 443 394 639 425
# 5 Lining 44 100 43 306 265 940 141 188 758 336 144 1158 627 388
# 6 Others 904 922 1006 605 1340 1683 1412 793 1215 1390 1539 1303 1133 1172
FF-1 GRAND
TOTAL
4124 4339 3300 3238 3661 7369 6169 4916 6277 7874 6532 8709 6603 5623
*All the data taken in PPM
Conclusion/ Way Forward : : Short terry is one of the major defect generated in the weaving. Further study will be based on this
defect.
Prepared By : Ashish Kumar Gupta Approved By : Mr. Ajit Parandekar
5 April 2015 12
13. TPM is our way of life
TPM
KK Project Target Setting
S No. Failure/Defect/Cause Description UOM Baseline Target
1. Short terry ppm 1210 968
Step 1.3
5 April 2015 13
14. TPM is our way of life
TPM
STEP-2
5 April 2015 14
15. TPM is our way of life
TPM Step 2.1爐爛. 爐爛. 爐踱. 爐爛 爐爐 爐萎爐逗じ爛爐爐 (TPM Fuguai Register)
1. 爐爐鉦ぎ爛爐迦 爐爐萎ぞ爐爛 2. 爐爐о爐萎 爐爛爐爐逗く爐鉦う爛 爐項ぞ爐迦い 3. 爐爛爐萎爐爐 爐伍爐ムぞ爐 4. 爐伍爐爛爐劇ぃ 爐伍爐萎爐 5. 爐萎爛爐爐朽い爛爐むぞ 爐爛爐 爐伍爐萎爐 6. 爐爐逗ぞ爐朽ざ爛爐爐 爐爐 爐萎爛爐 爐爐萎爐萎 爐朽じ爛爐む 7. 爐爐伍爐萎爛爐劇た爐 爐爐萎爐
1. Minor Flaws 2. Unfulfilled Basic Conditions 3. Inaccessible Places 4. Contamination Source 5. Quality Defect Sources 6. Unnecessary & Non Urgent Item 7. Unsafe Places
爐爛爐萎ぎ爐鉦
爐
爐∇爛爐爐∇た爛 爐爛
爐むぞ爐萎爐
爐∇爛爐爐∇た爛 爐朽ぞ爐迦ぞ
爐爐伍ぞ爐爐鉦え爛爐爐むぞ (Fuguai)
爐朽さ爐朽ぐ爐
爐爐伍ぞ爐爐鉦え爛爐
爐むぞ 爐爛
爐爛爐萎爐鉦ぐ
爐爐伍ぞ爐爐鉦え爛爐爐むぞ
爐爛爐萎
(爐迦ぞ爐/爐伍か爛 爐)
爐朽さ爐爐鉦ぐ爛 爐伍す爛 爐爐萎た爛 爐朽ぞ爐迦ぞ 爐爐朽ぞ爐爛 爐爐爐鉦く / 爐爐鉦ぐ爐爐朽ぞ爐
爐伍爐оぞ爐 爐爛
爐むぞ爐萎爐
(爐迦爛爐劇爐)
爐伍爐оぞ爐 爐爛
爐むぞ爐萎爐
(爐朽ぞ爐伍爐むさ爐朽)
爐迦爐÷ぐ 爐爛爐朽ぞ爐萎ぞ
爐爐爐爛爐爐爛
Sl.
No
Date of
Detectio
n
Name of
Detector
Abnormality (Fuguai)
description
Abnormal
ity Type
(1/2/3/4/5
/6/7)
Abnormality
tag
(Red /
White)
Department (Mech./ Elec./
Instr./ Tool/ Process)
Executor
Name
Counter Measure / Action
Taken
Target
Date of
Rectifica
tion
Actual Date
of
Rectification
Remarks
1. 23/06/14 Ashish
Short terry at left side of
fabric loom no.96
5 Red Mechanical Rakesh Gripper changed 23/06/14 23/06/14 Ok
2. 23/06/14 Balaram
Short terry occurs at left side
on loom no. 146
5 White Weaving Balaram Clean the gripper and tighten it 23/06/14 23/06/14 Ok
3. 24/06/14 Tribhuvan
Formation of Sort terry due
to tension variation in pile
beam at loom no. 133
5 Red Weaving Dhiran
Replaced the load cell and zero
setting done
24/06/14 24/06/14 Ok
4. 24/06/14 Virendra
Short terry occurs on right
side of the fabric at loom no.
16
5 Red Mechanical jagvir
Change the jammed relay nozzle
valve by new one
24/06/14 24/06/14 Ok
5. 25/06/14 Ashish
Negative pile beam length
(-825m) on loom no. 36
5 Red Weaving Surendra
Enter the correct beam length in
ICS setting (1850m)
25/06/14 25/06/14 Ok
6. 25/06/14
Tribhuvan Short terry occurs at right
side temple
5 Red Maintenance Dayal
Loose the temple and reduced the
temple angle below 90 degree
25/06/14 25/06/14 Ok
7. 25/06/14 Dhiran
Short terry formed full width
of cloth
5 White Weaving Dhiran Tension of pile warp beam reduces 25/06/14 25/06/14 Ok
8. 26/06/14 Dinesh
Tension variation in pile warp
beam due to faulty load cell
at loom no.18
5 Red Mechanical Prafful patil Change the load cell 26/06/014 26/06/14 Ok
9. 26/06/14 Bambam
Short terry occurs at left side
of loom
5 White Weaving Bambam
Clean the accumulated fluff and
tighten the gripper
26/06/14 26/06/14 Ok
10. 27/06/14 Sonu
Fluctuation in tension of pile
beam on loom no. 123
5 Red Electrical Khushpreet
Change the electrical pile let-off
card
27/06/14 27/06/14 Ok
11. 27/06/14 Basant
Gripper side short terry
formed on loom no.113
5 White Maintenance Basant
Open the gripper remove the
broken weft & fluff and reset
27/06/14 27/06/14 Ok
12. 28/06/14 Dayal
Short terry formed full width
of fabric
5 White Maintenance Dayal
Reduced the pile warp beam
tension
28/06/14 28/06/14 Ok
13. 28/06/14 Ashish
Wrong feed diameter of pile
warp beam at loom no. 103
5 White Weaving Ashish
Enter the correct diameter of pile
warp beam
28/06/14 28/06/14 Ok
5 April 2015 15
16. TPM is our way of life
TPM Step 2.2
S No. Activity
Identification
date
Target Date
Completion
Date
Responsibility
(Member
Name)
Review
Date
Review by Remarks
1.
Formation of Sort terry due to tension variation
in pile beam at loom no. 133
24/06/14 24/06/14 24/06/14 Dhiran
25/06/14 A. P. singh
Replaced the load cell
and zero setting done
2.
Short terry occurs at right side temple 25/06/14 25/06/14 25/06/14 Dayal
25/06/14 A. P. singh
Loose the temple and
reduced the temple
pulling below 90
degree
3.
Tension variation in pile warp beam due to
faulty load cell at loom no.18
26/06/14 26/06/014 26/06/14 Prafful patil 27/06/14
A. P. singh
Change the load cell
4.
Fluctuation in tension of pile beam on loom no.
123 27/06/14 27/06/14 27/06/14 Khushpreet 27/06/14
Gurpreet
singh
Change the electrical
pile let-off card
5 April 2015 16
17. TPM is our way of life
TPM
STEP-3
5 April 2015 17
18. TPM is our way of life
TPM Step 3.1
Stratification & Analysis of Causes
S No. Failure/Defect/Cause Description Stratification Tool Analysis Tool
1. Short terry
Flow chart,
Fish-bone
Check list,
Pareto analysis
5 April 2015 18
19. TPM is our way of life
TPM
5 April 2015 19
Weaving
start
Loom
start
Loom
continuously
run
Short terry
formation
Loom
running
Attend the
loom
Loom stopped due
to any reason
Attend the
short terry
Stop the loom
NO
NO
YES
YES
* Tension variation
* Gripper problem
* Relay nozzle direct
* Negative beam length
* Temple setting
* Wrong dia. fed
Step 3.1
Short terry generation in weaving
PROCESS FLOW CHART
20. TPM is our way of life
TPM Step 3.1
5 April 2015 20
Problem Phenomena : Short terry Date : 27/06/14
Fish-bone diagram
Short terry
ManMachineMaterial
Environment
Method
Measurement
Temple setting
Sticky ends
Tension variation
in pile beam
Relay nozzle direct
Faulty terry motion
Prepared By : Ashish Kumar Gupta Approved By : Mr. Ajit Parandekar
Improper sub valve
timing
Fitter negligence
Software problem
Wrong beam diameter
Wrong pick finding
Wrong beam length
Variation in beam hardness
Wrong method of
load cell connecting
Weft quality
Wrong method of
knotting pass
21. TPM is our way of life
TPM Step 3.1
5 April 2015 21
Process Name : Short terry Name of the investigator : Ashish Kumar Gupta
Location of Data Collection : Loom shed Date & time: 27/06/14 to 08/07/14 & 9:00AM to 6:00PM
Why this data is collected : To find out the causes for the short terry
Defect Type/
Event Occurance
27/06/14 28/06/14 30/06/14 01/07/14 02/07/14 03/07/14 04/07/14 05/07/14 07/07/14 08/07/14 TOTAL
Pile beam tension
variation
III II II III II III III II III III 26
Gripper setting
II III II II I II I III II II 20
Relay nozzle direct I II II I III I II I II I 16
Negative beam
length
II I I I II I I I 10
Temple setting I I I I I I I 7
Wrong diameter
fed
I I I I 4
Weft yarn rupture I I I I 4
Variation in beam
hardness
I I 2
TOTAL 10 9 9 8 7 9 10 9 9 9 89
Conclusion/ Way Forward : Pile beam tension variation, gripper setting, relay nozzle directed & negative beam length are
major problem for generation of short terry defect.
Prepared By : Ashish Kumar Gupta Approved By : Mr. Ajit Parandekar
22. TPM is our way of life
TPM Step 3.1
5 April 2015 22
Problem Phenomena :Short terry Date : 09/07/14
PARETO-ANALYSIS
Prepared By: Ashish Kumar Gupta Approved By: Mr. Ajit Parandekar
Conclusion/ Way Forward : 80%age cause responsible for generation of short terry are pile beam tension variation, gripper
setting, relay nozzle directed & negative beam length.
26
20
16
10
7
4 4 2
29%
52%
70%
81%
89%
93%
98% 100% 100% 100% 100%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
10
20
30
40
50
60
70
80
90
100
Pile beam
tension
variation
Gripper setting Relay nozzle
directed
Negative beam
length
Temple setting Wrong
diameter fed
Weft yarn
rupture
Variation in
beam hardness
%CumulativeContribution
Frequency/ContributionofCause
Causes -->
Frequency/ Qty. Frequency/ Qty.
23. TPM is our way of life
TPM Step 3.2
5 April 2015 23
TPM WHY-WHY ANALYSIS Report
Date:
09/07/14
Area : Weaving Equipment : Toyota Air jet loom
Subsystem/
Component:
Gripper
Breakdown/ Physical Phenomenon Short terry formation.
What is your final action? sufficient torque applied to gripper bolt & checking of it once in a week.
After final action, is it okay? YES
Why do you take above action Action
Why 1 Short terry observed on loom stop the loom
Why 2 Gripper standard position not ok Gripper position check
Why 3 Gripper found loose Tighten the gripper
Why 4 Due to vibration in loom
Why 5 Design of loom
Root cause is one of the following 5 items Action Planned AM/ JH PM Design E&T
1 Poor basic condition CLRI
2 Poor operating condition OPL, SOP
3 Deterioration PM Schedule
4 Weak Design Redesign, MP sheet
5 Poor Skill Training, OPL
C
C
Kaizen idea : Upper portion of gripper is tightly cover to reduce vibration effect.
24. TPM is our way of life
TPM Step 3.2
5 April 2015 24
TPM WHY-WHY ANALYSIS Report
Date:
12/07/14
Area : Weaving Equipment : Toyota Air jet loom
Subsystem/
Component:
Relay nozzle, sub-valve
Breakdown/ Physical Phenomenon Short terry formation.
What is your final action? Solenoid valve change.
After final action, is it okay? YES
Why do you take above action Action
Why 1 Short terry observed at four sub-nozzles Sub-nozzles checking
Why 2 Relay nozzle direct(continuous air supply) Valve open & checking
Why 3 Solenoid valve piston jam Changed the valve.
Why 4 Rust with air supply
Why 5 Due to mild steel pipe line
Root cause is one of the following 5 items Action Planned AM/ JH PM Design E&T
1 Poor basic condition CLRI
2 Poor operating condition OPL, SOP
3 Deterioration PM Schedule
4 Weak Design Redesign, MP sheet
5 Poor Skill Training, OPL
C
C
Kaizen idea : To change the mild steel pipe line by galvanised irons pipe line to avoid corrosion.
25. TPM is our way of life
TPM Step 3.2
Application of Analytical Techniques
S No.
Applicable Root Causes/
Vital Few Causes
Kaizen Idea
Countermeasure/ Action Plan
1. Pile beam tension variation Standardize the tension of pile beam as per quality.
2. Gripper setting
Gripper should be covered with a support to reduce
vibration effect & misalignment.
(Before: DSC01195.JPG, After: DSC011944.jpg)
Once in a week checking of gripper setting(Gripper
position & deterioration) .
3. Relay nozzle direct
Sub-valve piston cylinder of relay nozzle should be
changed.
4.
Negative beam length &
diameter(Software problem)
Checking of negative beam length & diameter per day
and where ever found negative again length & diameter
to be entered.
5 April 2015 25
26. TPM is our way of life
TPM Step 3.3
Conduct Experiments/ Develop Prototypes
S No.
Kaizen Idea
Countermeasure/ Action Plan
Experiment Done/ Prototype
Developed
1. Standardize the tension of pile beam as per quality.
Standard tension chart prepared according to the
quality & distributed to the fitter. Tension reading.xlsx
Run the trial on loom no.123(TG4949) according to
standard tension & no full width short terry found
when doff checked.
2.
Gripper should be covered with a support to reduce
vibration effect & misalignment.
A covered gripper use on loom no. 54(TG 4949) &
55(TG 5691).
Gripper position does not disturbed when it is
covered and hence chances of loosening is reduced.
3.
Checking of negative beam length & diameter per day
and where ever found negative again length & diameter
to be entered.
Checking of negative beam length & diameter started
per day and it is corrected whenever it go to
negative.
5 April 2015 26
27. TPM is our way of life
TPM
STEP-4
5 April 2015 27
28. TPM is our way of life
TPM Step 4.1
Make Improvement Proposals
S No.
Kaizen Idea
Countermeasure/ Action Plan Improvement Proposal
Approved by
HOD?
1.
Standardize the tension of pile beam as per
quality. Std tension.xlsx
When the new quality run their standard
tension should be add in the standard tension
list. YES
2.
Gripper should be covered with a support to
reduce vibration effect.
Once in two week checking of gripper
setting(Gripper position, deterioration).
Gripper covered with a tight support to reduce
vibration effect of loom & misalignment of
gripper. YES
3.
Sub-valve piston cylinder of relay nozzle
should be changed.
Sub-valve piston of relay nozzle should be
changed. YES
4.
Checking of negative beam length & diameter
per day and where ever found negative again
length & diameter to be entered.
Checking of negative beam length & diameter
per shift and where ever found negative again
length & diameter to be entered. YES
5 April 2015 28
29. TPM is our way of life
TPM Step 4.2
Compare Cost Effectiveness & Make Budget
S No.
Kaizen Idea
Countermeasure/ Action Plan Approved by HOD? Budget Required
1.
Standardize the tension of pile beam
as per quality. YES NIL
2.
Gripper should be covered with a
support to reduce vibration effect &
misalignment of gripper. YES NIL
3.
Sub-valve piston cylinder of relay
nozzle should be changed. YES 1100/piston cylinder
4.
Checking of negative beam length &
diameter per shift and where ever
found negative again length & diameter
to be entered. YES NIL
5 April 2015 29
30. TPM is our way of life
TPM Step 4.3
Check for Possible adverse Effects
S No.
Kaizen Idea
Countermeasure/
Action Plan
Approved by
HOD? Budget Required
Any adverse
Effect?
1.
Standardize the tension of
pile beam as per quality. YES NIL NO
2.
Gripper should be covered
with a support to reduce
vibration effect &
misalignment of gripper. YES NIL NO
3.
Sub-valve piston cylinder of
relay nozzle should be
changed. YES
1100/piston
cylinder NO
4.
Checking of negative beam
length & diameter per shift
and where ever found negative
again length & diameter to be
entered. YES NIL NO
5 April 2015 30
31. TPM is our way of life
TPM
STEP-5
5 April 2015 31
32. TPM is our way of life
TPM
Countermeasures implementation plan
Project Name : : To reduce short terry in weaving from 1210ppm to 968ppm
Owner Name : Ashish Kumar Gupta
Week (BSC)-->
S No. Countermeasure Week 16 Week 17 Week 18 Week 19
1.
Standardize the tension of pile beam as per
quality.
P
A
2.
Gripper covered with a support to reduce
vibration effect.
P
A
3.
Sub-valve piston cylinder of relay nozzle
should be changed.
P
A
4.
Checking of negative beam length &
diameter per shift and where ever found
negative again length & diameter to be
entered.
P
A
P
A
Step 5.1
5 April 2015 32
33. TPM is our way of life
TPM
KK Project Results Review
S No.
Failure/Defect/Cause
Description
UOM Baseline Target
Actual
(From 1st
to
6th
Aug)
Status
(Ok/ Not OK)
1. Short terry ppm 1210 968 1117 OK
Step 5.2 Perform tests & trial runs
5 April 2015 33
34. TPM is our way of life
TPM Step 5.3
TENTATIVE STANDARD OPERATING PROCEDUE (SOP)
Business : Towel Location/ Unit : FF-2/THT-2
Machine Name/
Process Name :
Weaving loom
Process : Beam knotting SOP during beam change
SOP for knotter during beam change
1. Take charge of knotting machine and frame from previous shift worker.
2. Check the availability of beam as per requirement and preparatory section officer in case of non-
availability of beams.
3. Unload the previous beam from the loom and do proper cleaning of the machine.
4. Load the new beam as per detail written on the slip.
5. Check the beam ends and do proper dressing of the yarn sheet.
6. Use correct needles as per count of yarn in the beam.
7. Start knotting as per required pattern and ensure for no yarn end breakage during knotting process.
8. Also, ensure for no crossing ends during knotting.
9. Finish the knotting and unmounts the knotting machine from the frame.
10. Keep the knotting waste in its proper place during knotting process.
11. Measure the accurate diameter of beam by using scale and feed it into loom system(computer).
12. Temple cover should be open to prevent temple ring jam during passing the knotting.
13. Handover the loom to weaver after passing knotting from reed area.
(Prepared By)
Ashish Kumar Gupta
(Approved By)
Mr. Ajit Parandekar
Format No.:/ Issue Date: Page
__ of __Revision No. & Rev. Date:
5 April 2015 34
35. TPM is our way of life
TPM Step 5.3
TENTATIVE STANDARD OPERATING PROCEDUE (SOP)
Business : Towel Location/ Unit : FF-2/THT-2
Machine Name/
Process Name :
Weaving loom
Process : Fitter working SOP during quality change
SOP for fitter during quality change
1. Take the round of loom in starting 15 minutes of shift and check quality change looms for incomplete
work.
2. Ensure that there should no jammed temple ring or ring with blunt spikes.
3. Check temple pulling.
4. Check gripper condition.
5. Check all relay nozzle work properly and no one will be directed.
6. Feed the pile and ground warp tension according to the standard tension.
7. Check other settings like air pressure, detect angle, weft arrival timing etc.
8. Before starting the loom ensure all setting are correct and work properly.
9. Start quality change looms by feeding parameters given on quality card.
10. Check performance of loom breakage and attend any major deviation on loom.
11. To attend the looms with low efficiency allotted by shift officer.
12. Check the high weft breakage looms and attend the loom.
13. In case of major problem on quality, attend the loom with the help of maintenance team.
(Prepared By)
Ashish Kumar Gupta
(Approved By)
Mr. Ajit Parandekar
Format No.:/ Issue Date: Page
__ of __Revision No. & Rev. Date:
5 April 2015 35
36. TPM is our way of life
TPM
STEP-6
5 April 2015 36
37. TPM is our way of life
TPM
5 April 2015 37
Evaluation of Result of Project (Primary Metric)
Target Vs Actual
686
1350
1789
2749
1117
0
500
1000
1500
2000
2500
3000
BSC 1 BSC 2 BSC 3 BSC 4 1st Aug to 6th Aug
Actual Base line Target
1210
968
Booking of jail
material in
between 15th
to 31st july
38. TPM is our way of life
TPM Step 6.2
KK Project Results Review
S No. Primary Metric UOM Baseline Target
Actual
(From 1st
to 6th
Aug)
Status
(Ok/ Not OK)
1. Short terry ppm 1210 968 1117 OK
5 April 2015 38
*In BSC 4, from 15th July to 31st July ,short terry defect has been
rapidly increased due to regular booking of Jail material and now
actual downgrade from 1st August to 6th August is under control i.e.
in between given baseline and target.
39. TPM is our way of life
TPM
STEP-7
5 April 2015 39
40. TPM is our way of life
TPM Step 7.1
STANDARD OPERATING PROCEDUE (SOP)
Business : Towel Location/ Unit : FF-2/THT-2
Machine Name/
Process Name :
Weaving loom
Process : Beam knotting SOP during beam change
SOP for knotting during beam change
1. Take charge of knotting machine and frame from previous shift worker.
2. Check the availability of beam as per requirement and preparatory section officer in case of non-
availability of beams.
3. Unload the previous beam from the loom and do proper cleaning of the machine.
4. Load the new beam as per detail written on the slip.
5. Check the beam ends and do proper dressing of the yarn sheet.
6. Use correct needles as per count of yarn in the beam.
7. Start knotting as per required pattern and ensure for no yarn end breakage during knotting process.
8. Also, ensure for no crossing ends during knotting.
9. Finish the knotting and unmounts the knotting machine from the frame.
10. Keep the knotting waste in its proper place during knotting process.
11. Measure the accurate diameter of beam by using scale and feed it into loom system(computer).
12. Temple cover should be open to prevent temple ring jam during passing the knotting.
13. Handover the loom to weaver after passing knotting from reed area.
(Prepared By)
Ashish Kumar Gupta
(Approved By)
Mr. Ajit Parandekar
Format No.:/ Issue Date: Page
__ of __Revision No. & Rev. Date:
5 April 2015 40
41. TPM is our way of life
TPM Step 7.1
TENTATIVE STANDARD OPERATING PROCEDUE (SOP)
Business : Towel Location/ Unit : FF-2/THT-2
Machine Name/
Process Name :
Weaving loom
Process : Fitter working SOP during quality change
SOP for fitter during quality change
1. Take the round of loom in starting 15 minutes of shift and check quality change looms for incomplete
work.
2. Ensure that there should no jammed temple ring or ring with blunt spikes.
3. Check temple pulling.
4. Check gripper condition.
5. Check all relay nozzle work properly and no one will be directed.
6. Feed the pile and ground warp tension according to the standard tension. Std tension.xlsx
7. Check other settings like air pressure, detect angle, weft arrival timing etc.
8. Before starting the loom ensure all setting are correct and work properly.
9. Start quality change looms by feeding parameters given on quality card.
10. Check performance of loom breakage and attend any major deviation on loom.
11. To attend the looms with low efficiency allotted by shift officer.
12. Check the high weft breakage looms and attend the loom.
13. In case of major problem on quality, attend the loom with the help of maintenance team.
(Prepared By)
Ashish Kumar Gupta
(Approved By)
Mr. Ajit Parandekar
Format No.:/ Issue Date: Page
__ of __Revision No. & Rev. Date:
5 April 2015 41
42. TPM is our way of life
TPM Step 7.2
5 April 2015 42
Daily tracing of worst operator
1. Collect the data of damages produce per loom from damage report of grey
folding.
2. Select those looms on which more than 9 damages are produced.
3. Trace the operator name of those looms.
4. Record those worst operator name in Damage observation register.
5. Council those worst operator that they do not produce as much damage
and also worn them if their name repeated more than three times in that
list, they will be punished.
43. TPM is our way of life
TPM Step 7.3
5 April 2015 43
Negative beam length cause let-off
synchronization error.
Beam length should be correct for let-
off synchronization.
Ashish Kumar Gupta
Beam length should be correct.
10/7/14
Surendra rawat
11/7/14
Mr. Ajit parandekar
Loom shed, THT-2
Subedar Sanjay
44. TPM is our way of life
TPM Step 7.3
5 April 2015 44
Here temple cover is closed while
knotting pass which cause chances
of jamming of temple rings.
Here temple cover is open while
knotting pass so no chances of temple
rings jamming.
Ashish Kumar Gupta
During knotting pass temple cover should be open.
4/7/14
Ashish Kumar Gupta
5/7/14
Mr. Ajit parandekar
Sushil Arun
Loom shed, THT-2
Sarwan singh Sunil
45. TPM is our way of life
TPM Step 7.3
5 April 2015 45
Here temple rings are jammed with
fluff which creates short terry in
towels
Here temple ring is clean so no chance
of short terry due to temple.
Ashish Kumar Gupta
Temple ring should be always clean
27/6/14
Ashish Kumar Gupta
28/6/14
Mr. Ajit parandekar
Rakesh Arun
Loom shed, THT-2
Jagat negi Ananjay
46. TPM is our way of life
TPM Step 7.3
5 April 2015 46
Fluff accumulated in between
gripper and its platform which
cause loose gripping of picks.
Gripper should be always clean &
free from Fluff accumulation for
proper gripping of picks.
Ashish Kumar Gupta
Gripper should be clean.
21/6/14
Ashish Kumar Gupta
23/6/14
Mr. Ajit parandekar
Amandeep Soni kaur
Loom shed, THT-2
Ratandeep Rani
47. TPM is our way of life
TPM Step 7.3
KAIZEN IDEA - SHEET
Activity KK JH QM PM SHE OTPM DM ET
Loss
No./
Step
5
Result Area P Q C D S M
Plant/ Function : THT-2 Machine/ Area : Toyota Air jet/Loom shed Muskaan/ Kaizen No :
Kaizen theme : To reduce short terry
generation due to gripper.
Idea : Give additional support to gripper to reduce loom vibration effect. KPI UOM Data
Benchmark/ Baseline NA NA NA
Countermeasure : The upper portion of gripper is tightly covered which reduce
the vibration effect also nullify the chance of damage of reed & main cutter due
to misalignment of gripper.
Target NA NA NA
Problem/present status :
short terry formation due to gripper.
Due to vibration in running loom
gripper loose frequently & hence
resulting short terry formed.
Kaizen start 14 07 2014
Before condition
(Photograph/Sketch) :
After condition (Photograph/Sketch) : Kaizen Finish Ongoing
Team
members
Name
Salary
Code
Dept/
Functi
on
Ashish kumar
gupta
CN3343 Weaving
Taj afzal
M30858 Weaving
Iqbal singh I43032 Maintenance
Benefits:
P
Description (Before) :Less contact
portion of gripper hence effect of
loom vibration is more & it loose
easily.
Description (After) :Upper portion of
gripper tightly covered hence loosening of
gripper reduces by loom vibration.
Q
C
Analysis why - why analysis : Results (Bar Chart of before & after of the problem metric) : S
Problem Phenomena :
Short terry formation
M
Tangibl
e
In-
tangible
Approved
Savings in Rs.
Why 1 : short terry formation due to
gripper
Approved by:
Department Champion/
Muskaan Co-ordinator:
Taj afzal
Why 2 : Gripper become loose.
Unit Champion:
Unit Costing Team:
Why 3 : Vibration in running loom Scope & plan for Horizontal Deployment Yes/ No
S no M/c No.
Target
date
Responsibility StatusWhy 4 :Weak design
1. 55 24/7/2014
Iqbal singh
ok
Root Cause : Weak design of gripper
0
1
2
3
4
5
Befor After
Shortterryindoff
48. TPM is our way of life
TPM
5 April 2015 48
Consolidating gains
Date CSP Prod in
MT
Actual Short
terry in PPM
Base line
(Week 1 to 13)
Target in
PPM
1-Aug 40.2 1309
1210 968
2-Aug 38.28 605
3-Aug 50.26 792
4-Aug 38.24 1306
5-Aug 37.22 1133
6-Aug 37.61 1560
Average 40.30 1118 1210 968
(Base line-Actual)%*CSP packed production*150
Reduction(Base line-Actual) =0.1%
Average production from 1th Aug to 6Th Aug = 40.30MT
Saving(1st Aug to 6th Aug) = 3355