North Boone Athletic
Stadium Information
The Stadium Project Timeline
 2004 -2006 - Originally brought up by the Facilities Task Force
 2006-2007 - Identified as the #1 issue for NBHS
 2011 - Project was re-estimated by Wold Architects in January at a
cost of $1,374,660 to rebuild existing field on site with grass
 2012 July - Stadium discussed at the Facilities Committee
 2012 Sept - New stadium committee was named
 2012 Nov  Community surveyed regarding stadium options
 2013 Oct - Final presentation to Board
 Boosters paid half the design fees
 Lack of funding sources delayed moving the project forward
 2014 Board wished to reconsider using sales tax funding for the
project after being notified of CDB Grant
2004/5 Facilities Task Force
Final Report April 18, 2006
 Seven community members
 Two district staff
 Four board members
 Superintendent Houselog
 Included in its final 2006 Report a
recommended Central Campus Site Plan
including a new athletic facility
Map from
4/18/2006
Facilities
Report
showing
placement of
new stadium
2006-2007 Facilities Needs
Facilities Memo from Mrs. Troller to Board
 The hard sell, but the right sell is a new
football/soccer/track facility. We should have
an 8 lane track with all of the field events
available for competition.
In 2010/11 Facilities Plan Update
 Wold Architects, the districts architect
provided a updated fiscal summary of the
project in January 2011
 The project seems to have been originally
projected for 2008-2009 as a part of a new
high school building
2012 Committee Information
 The new stadium committee met on September 12,
2012 and presented their findings to the Board in the
fall of 2013
 Members included: Laura Zwart  BOE member; Amy
Morris  Football parent, Aaron Sullivan-FB, Paul
Hathcock-Soccer parent, Sandy Kleckler & Lynn Brody-
Track, Brenda Kamholz & Dr. Belcastro-MS, Allan
Johnson & Butch Peters-Community, Jim Novak-
Facilities Manager, Mrs. Troller & DalePurvis-
AD/Admin. & Stephen Cashman.
Stadium Committee Met with Board
Facilities Committee on Oct. 29, 2013
Stephen Cashman and Dale Purvis, along with
several other members attended the meeting
and answered questions about the proposal
for the committee. Stephen Cashman took
suggestions from the stadium committee and
with modifications to the February 6th
estimate, the price was now $4,395,111.
Community Input via Survey
 The committee decided to seek input from the
community about priorities if we were to build
a stadium
 A 14 question online survey was offered
seeking community feedback
 Ninety-six Individuals completed the survey
Survey Results
 Respondents
 Wanted a multi-use field (80%)
 Wanted a new track (93%)
 Allow PE to utilize (72%)
 Wanted restrooms included (85%)
 A majority didnt want to continue to use NBMS
restrooms (63%)
Comparisons to Other Big Northern
Facilities
 All other schools can host track meets
 X of X have a soccer field
 X of X have turf fields
 The range of seating is from X to X
 X of X schools with turf fields have reported a
reduction in maintenance costs
Concerns Raised with Current Facility
 Seating is inadequate and beyond the end of its life
 Smallest and oldest stadium in the Big Northern Conference
 The viablity of current bleachers is a concern
 Lighting is inadequate according to IHSA standards
 Current stadium only serves football; field is not wide enough for soccer;
track cannot hold home meets; has no track to practice on
 Band isnt allowed to regularly practice on field
 North Boone Youth Sports cannot use the current field; they dont feel
they have an adequate location in the community for their games
 No restrooms in current facility
 Press box isnt adequate for current needs
 Crowd control is inadequate
 No staff assigned to maintain the current fields; Current maintenance is
performed by a volunteer
Benefits of New Stadium
 Increased use of facility by band, PE, football,
soccer & track, as well as baseball and softball
 A turf field allows for more use without damage
 Seating increase to 1500 from 430
 Better control and security during events
 Meeting lighting standards for events
 Ability to host home track meets
 Accessible restrooms for fans
Current Placement Recommendation
Grass v. Turf
Grass
 Costs less initially
 More expensive to
maintain
 Cant be used for
multiple contests
 Need to use
pesticides and
fertilizers
Turf
 More expensive to
install
 Less expensive to
maintain
 Allows for multiple
events
 Potential to reduce
injuries
 No need to use
pesticides or fertilizers
Cost
 Current projections for the complete project
are between $4.5 and $5.5 million including
restrooms and a concession stand
 The Boosters have committed to actively
looking to reduce the total cost through
donations where possible
Cost Summary from 2/2013
Upgrading the current stadium to current safety standards would cost approximately
$1,500,000 to $2,000,0000 according to architectural estimates
This would still not accommodate band, soccer, track, PE or baseball and softball
Capital Development Funds
 The Board could have paid for the project out of
Capital Development Board funding, however
 The Board has committed ALL of the Capital
Development funds and interest on those funds to
abate property taxes.
 That is projected to reduce property tax collections by
more than $16 million over the next seven years; or
approximately $4100 for the owner of a $100K home
 NB Press Release 11/25/2014
Paying for the Project
 The Boards current concept would use approximately
$316,000 of Sales Tax Dollars annually to pay for the
project
 That would leave about $140,000 annually for other
facilities projects; along with approximately $700,000
that would accumulate prior to the first bond
payments being due
 To date, all sales tax dollars have been used for
facilities projects. None of the money has been used to
abate property taxes
Cost to Taxpayer
 Since this project is projected to be paid out of
sales tax dollars, there is no direct impact on the
property tax payer.
 If one assumed that all of the sales tax dollars
used for the stadium project would otherwise be
used for the abatement of property taxes (not
necessarily a good assumption), the owner of a
$100K home would save approximately $80 per
year.
Turf vs. Grass
 Indicate choice of playing surface:
 Natural grass 53% (44)
 Turf 47% (39)
 Benefits of Turf over grass:
 1. Safety HS Football survey-44% Fewer Concussions,
33% Fewer ACL Injuries, 34% Fewer Ligament Tears.
 Meyers, M.C. (2010). Incidence, Mechanisms, and
Severity of Game-Related College Football Injuries on
FieldTurf Versus Natural Grass American Journal Of
Sports Medicine, Vol. 38 (4).
Turf vs. Grass
 2. Increased play-ability. Stadium can be a
multi-purpose facility, not a football field. Now
we can allow PE classes and other programs to
use the field area.
 3. Reduced Maintenance. No need to mow,
stripe or water turf. Also no need for
pesticides, weed killers or fertilizers.
Location
Four locations for the stadium were offered on the
survey.
Results:
 1. Southeast of NBHS 31%
 2. Current location 28%
 3. Near current field, reoriented North to South,
23%
 4. Northwest of NBHS 16%
 The committee decided on the southeast
location.
Stadium Uses
 The survey asked, what should the stadium be
designed for? Results:
 1.Football 98%
 2.Track & Field 93%
 3. Soccer 80%
 4. Band Practice 75%
 5. PE Classes 72%
Restrooms
Several questions were asked regarding
restrooms. Results:
1. Acceptable to use MS restrooms? 63% No
2. Exterior restrooms provided? 85% yes
3. Portable toilets for spectators? 57% yes
Issues With Current Stadium
 Not Multi-use- Unable to host anything with the
exception of football. Track cannot host home
meets. Field is not wide enough for soccer field.
 Seating- Current seats available-250 home side,
and 150 on visitor side. BNC average seats range
from 1200-2800. Safety issue with bleachers.
 Lighting- Recommended lighting calls for 30
footcandles on a high school field. We are below
15.
Ad

Recommended

PPT
Online Credit Recovery
Steven Baule
PPTX
Rubric Development
Steven Baule
PPT
LAN Fundamentals
Steven Baule
PPTX
201209collegereadinessupdate
Steven Baule
PPTX
Unofficial T&L School CIO notes
Steven Baule
PPTX
IASA social media presentation 2012
Steven Baule
PPTX
Purdue Ross-Ade Stadium
Purdue University
PPTX
Jasper School Board presentation for a new football field and stadium
Matthew Crane
PPS
Stadiums In The World-football
Diramar Costa
ODP
Angles powerpoint
dolorscastro
PPTX
Prairie View A&M Sports Complex/Football Stadium Presentation
pv
PDF
Deloitte Football Money League 2014
Deloitte UK
PDF
Shyam Thesis Report
Shyam Singh
PDF
Civil structural engineering - Flat slab design
Satish Narayan
PDF
May 2014 ascension parish recreation presentation a r
cmccall9
PDF
190429 hardy rec center community meeting
RamaChilamkurthy
PPT
Club Seminar November 2010
Yorkshire Cricket Board
PDF
Arboretum community meeting 01.22.19 final
RamaChilamkurthy
PPT
LA SCORP promo
suzette simms
PPT
Draft space plan_del_wg
northvanrec
PPT
Saltex 2016, Fields in Trust: Guidance for Outdoor Sport and Play
Fields in Trust
PPT
HRCA Backcountry Wilderness Area Bench
HRCA
PPT
Recreation advisory committee plan 04 16-13rev.07-15-13
Mollie Hillburn
PPTX
UNF facility proposal
Hassan Smith
PDF
Creative Ways to Find Money for the Facilities That You Desperately Need
Tom O'Rourke
PDF
Hearst Park & Pool Project Community Meeting (February 15, 2017)
DC Department of General Services
PPTX
Community Advisory Group meeting 5
publicinvolvement
PDF
Benning park community meeting march 2020
RamaChilamkurthy
PPTX
Discussion of 2015 Bond Citizen Committee's Facility Recommendations
City of College Station

More Related Content

Viewers also liked (7)

PPS
Stadiums In The World-football
Diramar Costa
ODP
Angles powerpoint
dolorscastro
PPTX
Prairie View A&M Sports Complex/Football Stadium Presentation
pv
PDF
Deloitte Football Money League 2014
Deloitte UK
PDF
Shyam Thesis Report
Shyam Singh
PDF
Civil structural engineering - Flat slab design
Satish Narayan
Stadiums In The World-football
Diramar Costa
Angles powerpoint
dolorscastro
Prairie View A&M Sports Complex/Football Stadium Presentation
pv
Deloitte Football Money League 2014
Deloitte UK
Shyam Thesis Report
Shyam Singh
Civil structural engineering - Flat slab design
Satish Narayan

Similar to Athletic Facilities Presentation from Feb 2015 (20)

PDF
May 2014 ascension parish recreation presentation a r
cmccall9
PDF
190429 hardy rec center community meeting
RamaChilamkurthy
PPT
Club Seminar November 2010
Yorkshire Cricket Board
PDF
Arboretum community meeting 01.22.19 final
RamaChilamkurthy
PPT
LA SCORP promo
suzette simms
PPT
Draft space plan_del_wg
northvanrec
PPT
Saltex 2016, Fields in Trust: Guidance for Outdoor Sport and Play
Fields in Trust
PPT
HRCA Backcountry Wilderness Area Bench
HRCA
PPT
Recreation advisory committee plan 04 16-13rev.07-15-13
Mollie Hillburn
PPTX
UNF facility proposal
Hassan Smith
PDF
Creative Ways to Find Money for the Facilities That You Desperately Need
Tom O'Rourke
PDF
Hearst Park & Pool Project Community Meeting (February 15, 2017)
DC Department of General Services
PPTX
Community Advisory Group meeting 5
publicinvolvement
PDF
Benning park community meeting march 2020
RamaChilamkurthy
PPTX
Discussion of 2015 Bond Citizen Committee's Facility Recommendations
City of College Station
PPT
City Council May 1, 2012 Recreation Netting at Sports Complex
City of San Angelo Texas
PDF
Comox Valley Community Meeting October 23, 2013
Island Health
PDF
Community presentation-comox-valley-oct232013
Island Health
PPTX
Athletic Plan Update
Jaime Festa-Daigle
PPTX
Presentation.pptx
PawanNegi35
May 2014 ascension parish recreation presentation a r
cmccall9
190429 hardy rec center community meeting
RamaChilamkurthy
Club Seminar November 2010
Yorkshire Cricket Board
Arboretum community meeting 01.22.19 final
RamaChilamkurthy
LA SCORP promo
suzette simms
Draft space plan_del_wg
northvanrec
Saltex 2016, Fields in Trust: Guidance for Outdoor Sport and Play
Fields in Trust
HRCA Backcountry Wilderness Area Bench
HRCA
Recreation advisory committee plan 04 16-13rev.07-15-13
Mollie Hillburn
UNF facility proposal
Hassan Smith
Creative Ways to Find Money for the Facilities That You Desperately Need
Tom O'Rourke
Hearst Park & Pool Project Community Meeting (February 15, 2017)
DC Department of General Services
Community Advisory Group meeting 5
publicinvolvement
Benning park community meeting march 2020
RamaChilamkurthy
Discussion of 2015 Bond Citizen Committee's Facility Recommendations
City of College Station
City Council May 1, 2012 Recreation Netting at Sports Complex
City of San Angelo Texas
Comox Valley Community Meeting October 23, 2013
Island Health
Community presentation-comox-valley-oct232013
Island Health
Athletic Plan Update
Jaime Festa-Daigle
Presentation.pptx
PawanNegi35
Ad

Recently uploaded (20)

PPT
M&A5 Q1 1 differentiate evolving early Philippine conventional and contempora...
ErlizaRosete
PPTX
Great Governors' Send-Off Quiz 2025 Prelims IIT KGP
IIT Kharagpur Quiz Club
PPTX
GREAT QUIZ EXCHANGE 2025 - GENERAL QUIZ.pptx
Ronisha Das
PPTX
How to Manage Different Customer Addresses in Odoo 18 Accounting
Celine George
PDF
Public Health For The 21st Century 1st Edition Judy Orme Jane Powell
trjnesjnqg7801
PPTX
CRYPTO TRADING COURSE BY FINANCEWORLD.IO
AndrewBorisenko3
PPTX
June 2025 Progress Update With Board Call_In process.pptx
International Society of Service Innovation Professionals
PDF
Hurricane Helene Application Documents Checklists
Mebane Rash
PDF
English 3 Quarter 1_LEwithLAS_Week 1.pdf
DeAsisAlyanajaneH
PPTX
LAZY SUNDAY QUIZ "A GENERAL QUIZ" JUNE 2025 SMC QUIZ CLUB, SILCHAR MEDICAL CO...
Ultimatewinner0342
PPTX
Code Profiling in Odoo 18 - Odoo 18 際際滷s
Celine George
PDF
ECONOMICS, DISASTER MANAGEMENT, ROAD SAFETY - STUDY MATERIAL [10TH]
SHERAZ AHMAD LONE
PDF
HistoPathology Ppt. Arshita Gupta for Diploma
arshitagupta674
PDF
Learning Styles Inventory for Senior High School Students
Thelma Villaflores
PPTX
Peer Teaching Observations During School Internship
AjayaMohanty7
PPTX
2025 Completing the Pre-SET Plan Form.pptx
mansk2
PPTX
YSPH VMOC Special Report - Measles Outbreak Southwest US 6-14-2025.pptx
Yale School of Public Health - The Virtual Medical Operations Center (VMOC)
PPTX
Birnagar High School Platinum Jubilee Quiz.pptx
Sourav Kr Podder
PDF
Romanticism in Love and Sacrifice An Analysis of Oscar Wildes The Nightingal...
KaryanaTantri21
PPTX
Filipino 9 Maikling Kwento Ang Ama Panitikang Asiyano
sumadsadjelly121997
M&A5 Q1 1 differentiate evolving early Philippine conventional and contempora...
ErlizaRosete
Great Governors' Send-Off Quiz 2025 Prelims IIT KGP
IIT Kharagpur Quiz Club
GREAT QUIZ EXCHANGE 2025 - GENERAL QUIZ.pptx
Ronisha Das
How to Manage Different Customer Addresses in Odoo 18 Accounting
Celine George
Public Health For The 21st Century 1st Edition Judy Orme Jane Powell
trjnesjnqg7801
CRYPTO TRADING COURSE BY FINANCEWORLD.IO
AndrewBorisenko3
June 2025 Progress Update With Board Call_In process.pptx
International Society of Service Innovation Professionals
Hurricane Helene Application Documents Checklists
Mebane Rash
English 3 Quarter 1_LEwithLAS_Week 1.pdf
DeAsisAlyanajaneH
LAZY SUNDAY QUIZ "A GENERAL QUIZ" JUNE 2025 SMC QUIZ CLUB, SILCHAR MEDICAL CO...
Ultimatewinner0342
Code Profiling in Odoo 18 - Odoo 18 際際滷s
Celine George
ECONOMICS, DISASTER MANAGEMENT, ROAD SAFETY - STUDY MATERIAL [10TH]
SHERAZ AHMAD LONE
HistoPathology Ppt. Arshita Gupta for Diploma
arshitagupta674
Learning Styles Inventory for Senior High School Students
Thelma Villaflores
Peer Teaching Observations During School Internship
AjayaMohanty7
2025 Completing the Pre-SET Plan Form.pptx
mansk2
YSPH VMOC Special Report - Measles Outbreak Southwest US 6-14-2025.pptx
Yale School of Public Health - The Virtual Medical Operations Center (VMOC)
Birnagar High School Platinum Jubilee Quiz.pptx
Sourav Kr Podder
Romanticism in Love and Sacrifice An Analysis of Oscar Wildes The Nightingal...
KaryanaTantri21
Filipino 9 Maikling Kwento Ang Ama Panitikang Asiyano
sumadsadjelly121997
Ad

Athletic Facilities Presentation from Feb 2015

  • 2. The Stadium Project Timeline 2004 -2006 - Originally brought up by the Facilities Task Force 2006-2007 - Identified as the #1 issue for NBHS 2011 - Project was re-estimated by Wold Architects in January at a cost of $1,374,660 to rebuild existing field on site with grass 2012 July - Stadium discussed at the Facilities Committee 2012 Sept - New stadium committee was named 2012 Nov Community surveyed regarding stadium options 2013 Oct - Final presentation to Board Boosters paid half the design fees Lack of funding sources delayed moving the project forward 2014 Board wished to reconsider using sales tax funding for the project after being notified of CDB Grant
  • 3. 2004/5 Facilities Task Force Final Report April 18, 2006 Seven community members Two district staff Four board members Superintendent Houselog Included in its final 2006 Report a recommended Central Campus Site Plan including a new athletic facility
  • 5. 2006-2007 Facilities Needs Facilities Memo from Mrs. Troller to Board The hard sell, but the right sell is a new football/soccer/track facility. We should have an 8 lane track with all of the field events available for competition.
  • 6. In 2010/11 Facilities Plan Update Wold Architects, the districts architect provided a updated fiscal summary of the project in January 2011 The project seems to have been originally projected for 2008-2009 as a part of a new high school building
  • 7. 2012 Committee Information The new stadium committee met on September 12, 2012 and presented their findings to the Board in the fall of 2013 Members included: Laura Zwart BOE member; Amy Morris Football parent, Aaron Sullivan-FB, Paul Hathcock-Soccer parent, Sandy Kleckler & Lynn Brody- Track, Brenda Kamholz & Dr. Belcastro-MS, Allan Johnson & Butch Peters-Community, Jim Novak- Facilities Manager, Mrs. Troller & DalePurvis- AD/Admin. & Stephen Cashman.
  • 8. Stadium Committee Met with Board Facilities Committee on Oct. 29, 2013 Stephen Cashman and Dale Purvis, along with several other members attended the meeting and answered questions about the proposal for the committee. Stephen Cashman took suggestions from the stadium committee and with modifications to the February 6th estimate, the price was now $4,395,111.
  • 9. Community Input via Survey The committee decided to seek input from the community about priorities if we were to build a stadium A 14 question online survey was offered seeking community feedback Ninety-six Individuals completed the survey
  • 10. Survey Results Respondents Wanted a multi-use field (80%) Wanted a new track (93%) Allow PE to utilize (72%) Wanted restrooms included (85%) A majority didnt want to continue to use NBMS restrooms (63%)
  • 11. Comparisons to Other Big Northern Facilities All other schools can host track meets X of X have a soccer field X of X have turf fields The range of seating is from X to X X of X schools with turf fields have reported a reduction in maintenance costs
  • 12. Concerns Raised with Current Facility Seating is inadequate and beyond the end of its life Smallest and oldest stadium in the Big Northern Conference The viablity of current bleachers is a concern Lighting is inadequate according to IHSA standards Current stadium only serves football; field is not wide enough for soccer; track cannot hold home meets; has no track to practice on Band isnt allowed to regularly practice on field North Boone Youth Sports cannot use the current field; they dont feel they have an adequate location in the community for their games No restrooms in current facility Press box isnt adequate for current needs Crowd control is inadequate No staff assigned to maintain the current fields; Current maintenance is performed by a volunteer
  • 13. Benefits of New Stadium Increased use of facility by band, PE, football, soccer & track, as well as baseball and softball A turf field allows for more use without damage Seating increase to 1500 from 430 Better control and security during events Meeting lighting standards for events Ability to host home track meets Accessible restrooms for fans
  • 15. Grass v. Turf Grass Costs less initially More expensive to maintain Cant be used for multiple contests Need to use pesticides and fertilizers Turf More expensive to install Less expensive to maintain Allows for multiple events Potential to reduce injuries No need to use pesticides or fertilizers
  • 16. Cost Current projections for the complete project are between $4.5 and $5.5 million including restrooms and a concession stand The Boosters have committed to actively looking to reduce the total cost through donations where possible
  • 17. Cost Summary from 2/2013 Upgrading the current stadium to current safety standards would cost approximately $1,500,000 to $2,000,0000 according to architectural estimates This would still not accommodate band, soccer, track, PE or baseball and softball
  • 18. Capital Development Funds The Board could have paid for the project out of Capital Development Board funding, however The Board has committed ALL of the Capital Development funds and interest on those funds to abate property taxes. That is projected to reduce property tax collections by more than $16 million over the next seven years; or approximately $4100 for the owner of a $100K home NB Press Release 11/25/2014
  • 19. Paying for the Project The Boards current concept would use approximately $316,000 of Sales Tax Dollars annually to pay for the project That would leave about $140,000 annually for other facilities projects; along with approximately $700,000 that would accumulate prior to the first bond payments being due To date, all sales tax dollars have been used for facilities projects. None of the money has been used to abate property taxes
  • 20. Cost to Taxpayer Since this project is projected to be paid out of sales tax dollars, there is no direct impact on the property tax payer. If one assumed that all of the sales tax dollars used for the stadium project would otherwise be used for the abatement of property taxes (not necessarily a good assumption), the owner of a $100K home would save approximately $80 per year.
  • 21. Turf vs. Grass Indicate choice of playing surface: Natural grass 53% (44) Turf 47% (39) Benefits of Turf over grass: 1. Safety HS Football survey-44% Fewer Concussions, 33% Fewer ACL Injuries, 34% Fewer Ligament Tears. Meyers, M.C. (2010). Incidence, Mechanisms, and Severity of Game-Related College Football Injuries on FieldTurf Versus Natural Grass American Journal Of Sports Medicine, Vol. 38 (4).
  • 22. Turf vs. Grass 2. Increased play-ability. Stadium can be a multi-purpose facility, not a football field. Now we can allow PE classes and other programs to use the field area. 3. Reduced Maintenance. No need to mow, stripe or water turf. Also no need for pesticides, weed killers or fertilizers.
  • 23. Location Four locations for the stadium were offered on the survey. Results: 1. Southeast of NBHS 31% 2. Current location 28% 3. Near current field, reoriented North to South, 23% 4. Northwest of NBHS 16% The committee decided on the southeast location.
  • 24. Stadium Uses The survey asked, what should the stadium be designed for? Results: 1.Football 98% 2.Track & Field 93% 3. Soccer 80% 4. Band Practice 75% 5. PE Classes 72%
  • 25. Restrooms Several questions were asked regarding restrooms. Results: 1. Acceptable to use MS restrooms? 63% No 2. Exterior restrooms provided? 85% yes 3. Portable toilets for spectators? 57% yes
  • 26. Issues With Current Stadium Not Multi-use- Unable to host anything with the exception of football. Track cannot host home meets. Field is not wide enough for soccer field. Seating- Current seats available-250 home side, and 150 on visitor side. BNC average seats range from 1200-2800. Safety issue with bleachers. Lighting- Recommended lighting calls for 30 footcandles on a high school field. We are below 15.