ºÝºÝߣ

ºÝºÝߣShare a Scribd company logo
BOTTLE BLOWER INSTALLATION
BOTTLEBLOWERINSTALLATION
Location
Yangon, My.
Duration
5 Days
Project value
25,000 USD
Weights
Bottle blower 12 Tonnes
Oven 4.9 Tonnes
Compressor 4 Tonnes
Conveyor  feed unit 2 Tonnes
Chiller unit 2 Tonnes
Air handling unit x2 1.5 Tonnes
Equipment Used
10t City crane
3.7t Telehandler
5t Forklift
30t Toejacks x6
12t Skates x6
8 Inch steel form work
4 Axle low bed trailer
6 Man installation team
SCOPE
CEA Project Logistics Myanmar were employed for
the transportation, customs process and installation
of a pre-formed bottle blowing machine and it¡¯s
auxiliary parts at the Loi Hein soft drinks factory in
Yangon, Myanmar. This was the completion of a
three-part project that CEA had been conducting.
	
CASE STUDY		 CS020
Bottle Blower Installation 1/2
MAIN BLOWER MACHINE LOWERED ON TO 12T SKATES READY TO MOVE INTO THE FACTORY
BOTTLEBLOWERINSTALLATION
CEA PROJECT LOGISTICS
G-18 PEARL CONDO
KABAR AYE PAGODA ROAD
BAHAN TOWNSHIP
YANGON
MYANMAR
+959 421 031 286
www.ceaprojects.com
CEA service teams took charge of the cargo as it arrived at the port
and used escort vehicles throughout the transportation of the
oversized cargo to the factory site. The equipment with a value
of over 500,000 USD was carefully unloaded and unpacked and
lifted on to 15 tonne multi-wheel skates to ease the manoeuvring
through and across the factory to the installation site.
Due to the complexity of the factory layout, a 10-Tonne city
crane was used inside to facilitate the movement of some of the
machinery, modifications to several of the factory¡¯s walls were
also made. When all the bottle blower machinery parts were in
place, each one was jacked down from its skates and final levelling
commenced. The whole project was completed within the five-day
time frame and under budget.
CASE STUDY		 CS020
Bottle Blower Installation 2/2
STANDARDIZED CARGO AWAITS UNOADING
TELEHANDLER UNLOADING CONTAINERS
OVERSIZED CARGO ARRIVAL AT FACTORY
CEA TEAMS UNPACK THE CARGO
MAIN PARTS ASSEMBLED IN OPERATIONAL LOCATION AND AWAITING FINAL INSTALLATION
BLOWER BEING SKATED ACROSS FACTORY5T FORKLIFT ASSISTS IN SKATING
BLOWER AND OTHER MACHINERY IN PLACEAUXILIARY MACHINERY IN PLACE

More Related Content

Bottle Blower Installation

  • 1. BOTTLE BLOWER INSTALLATION BOTTLEBLOWERINSTALLATION Location Yangon, My. Duration 5 Days Project value 25,000 USD Weights Bottle blower 12 Tonnes Oven 4.9 Tonnes Compressor 4 Tonnes Conveyor feed unit 2 Tonnes Chiller unit 2 Tonnes Air handling unit x2 1.5 Tonnes Equipment Used 10t City crane 3.7t Telehandler 5t Forklift 30t Toejacks x6 12t Skates x6 8 Inch steel form work 4 Axle low bed trailer 6 Man installation team SCOPE CEA Project Logistics Myanmar were employed for the transportation, customs process and installation of a pre-formed bottle blowing machine and it¡¯s auxiliary parts at the Loi Hein soft drinks factory in Yangon, Myanmar. This was the completion of a three-part project that CEA had been conducting. CASE STUDY CS020 Bottle Blower Installation 1/2 MAIN BLOWER MACHINE LOWERED ON TO 12T SKATES READY TO MOVE INTO THE FACTORY
  • 2. BOTTLEBLOWERINSTALLATION CEA PROJECT LOGISTICS G-18 PEARL CONDO KABAR AYE PAGODA ROAD BAHAN TOWNSHIP YANGON MYANMAR +959 421 031 286 www.ceaprojects.com CEA service teams took charge of the cargo as it arrived at the port and used escort vehicles throughout the transportation of the oversized cargo to the factory site. The equipment with a value of over 500,000 USD was carefully unloaded and unpacked and lifted on to 15 tonne multi-wheel skates to ease the manoeuvring through and across the factory to the installation site. Due to the complexity of the factory layout, a 10-Tonne city crane was used inside to facilitate the movement of some of the machinery, modifications to several of the factory¡¯s walls were also made. When all the bottle blower machinery parts were in place, each one was jacked down from its skates and final levelling commenced. The whole project was completed within the five-day time frame and under budget. CASE STUDY CS020 Bottle Blower Installation 2/2 STANDARDIZED CARGO AWAITS UNOADING TELEHANDLER UNLOADING CONTAINERS OVERSIZED CARGO ARRIVAL AT FACTORY CEA TEAMS UNPACK THE CARGO MAIN PARTS ASSEMBLED IN OPERATIONAL LOCATION AND AWAITING FINAL INSTALLATION BLOWER BEING SKATED ACROSS FACTORY5T FORKLIFT ASSISTS IN SKATING BLOWER AND OTHER MACHINERY IN PLACEAUXILIARY MACHINERY IN PLACE