CEA Project Logistics Myanmar was hired to transport, clear customs, and install a bottle blowing machine and auxiliary equipment at a soft drink factory in Yangon, Myanmar over the course of 5 days. The project involved transporting over 21 tonnes of machinery in several shipments worth $25,000 USD total. CEA used cranes, forklifts, and skates to carefully move the large equipment pieces into place despite the complex factory layout. Wall modifications were also required. The full installation was completed on time and under budget.
1 of 2
Download to read offline
More Related Content
Bottle Blower Installation
1. BOTTLE BLOWER INSTALLATION
BOTTLEBLOWERINSTALLATION
Location
Yangon, My.
Duration
5 Days
Project value
25,000 USD
Weights
Bottle blower 12 Tonnes
Oven 4.9 Tonnes
Compressor 4 Tonnes
Conveyor feed unit 2 Tonnes
Chiller unit 2 Tonnes
Air handling unit x2 1.5 Tonnes
Equipment Used
10t City crane
3.7t Telehandler
5t Forklift
30t Toejacks x6
12t Skates x6
8 Inch steel form work
4 Axle low bed trailer
6 Man installation team
SCOPE
CEA Project Logistics Myanmar were employed for
the transportation, customs process and installation
of a pre-formed bottle blowing machine and it¡¯s
auxiliary parts at the Loi Hein soft drinks factory in
Yangon, Myanmar. This was the completion of a
three-part project that CEA had been conducting.
CASE STUDY CS020
Bottle Blower Installation 1/2
MAIN BLOWER MACHINE LOWERED ON TO 12T SKATES READY TO MOVE INTO THE FACTORY
2. BOTTLEBLOWERINSTALLATION
CEA PROJECT LOGISTICS
G-18 PEARL CONDO
KABAR AYE PAGODA ROAD
BAHAN TOWNSHIP
YANGON
MYANMAR
+959 421 031 286
www.ceaprojects.com
CEA service teams took charge of the cargo as it arrived at the port
and used escort vehicles throughout the transportation of the
oversized cargo to the factory site. The equipment with a value
of over 500,000 USD was carefully unloaded and unpacked and
lifted on to 15 tonne multi-wheel skates to ease the manoeuvring
through and across the factory to the installation site.
Due to the complexity of the factory layout, a 10-Tonne city
crane was used inside to facilitate the movement of some of the
machinery, modifications to several of the factory¡¯s walls were
also made. When all the bottle blower machinery parts were in
place, each one was jacked down from its skates and final levelling
commenced. The whole project was completed within the five-day
time frame and under budget.
CASE STUDY CS020
Bottle Blower Installation 2/2
STANDARDIZED CARGO AWAITS UNOADING
TELEHANDLER UNLOADING CONTAINERS
OVERSIZED CARGO ARRIVAL AT FACTORY
CEA TEAMS UNPACK THE CARGO
MAIN PARTS ASSEMBLED IN OPERATIONAL LOCATION AND AWAITING FINAL INSTALLATION
BLOWER BEING SKATED ACROSS FACTORY5T FORKLIFT ASSISTS IN SKATING
BLOWER AND OTHER MACHINERY IN PLACEAUXILIARY MACHINERY IN PLACE