際際滷

際際滷Share a Scribd company logo
Ministry of Water Resources & Electricity
Dams ImplementatIon UnIt
GENERAL DIRECTORATE OF PROJECTS
DAM COMPLEX OF UPPER
ATBARA PROJECT
Brief Introduction to Contracts& Planning Works
ENG.Awad Hamdan
Contracts & Planning Department
1.Contract
1.1 Definition:
A voluntary, deliberate, and legally binding agreement
between two or more competent parties
Contracts & Planning Department
1.Cotracts
1.2 Contracts Essentials
 Offer
 Acceptance
 Objective
 Obligations
 Consideration
 Competent Parties
Contracts & Planning Department
2. Project
2.1 Definition
Set of one or more activities that should be
performed within a period of time , budget
and quality.
Contracts & Planning Department
Contracts & Planning Department
Project planning is the process that defines the project
activities and end products that will be performed and
describes how the activities will be accomplished. The
purpose of project planning is to define each major
task, estimate the time and resources required, and
provide a framework for management review and
control.
2. Project
2.3 Project Planning
Contracts & Planning Department
project planning activities Scope:
 To define the specific work to be performed and
goals that define and bind the project.
 to define the Estimates to be documented for
planning, tracking, and controlling the project.
 to define Commitments that are planned,
documented, and agreed to by affected groups.
 Project alternatives, assumptions, and constraints.
2. Project
2. Project
The planning process includes steps to estimate the
size of the project, estimate the technical scope of
the effort, estimate the resources required to
complete the project, produce a schedule, identify
and assess risks, and negotiate commitments.
Contracts & Planning Department
2. Project
Repetition of the previous steps is necessary to
establish the project plan. Typically, several
iterations of the planning process are performed
before a plan is actually completed.
Contracts & Planning Department
3. Construction Projects
3.1 Construction Project Parties
 Client (Employer)
 Consultant (Engineer)
 Contractor
3.2 Contractual Relationship Between Parties
 Employer-Consultant Contract
 Employer-Contractor Contract
Contracts & Planning Department
4. Projects Constraints
Contracts & Planning Department
 Measurement Contract
 Lump-sum Contract
 Direct Labour Contract
 Cost Plus Contract




Based on Price Determination
5. Types of Contracts
Contracts & Planning Department
100%
 Lump-sum Contract
 Measurement Contract
 Cost Plus Contract
 Direct Labour Contract
0% 100%
5. Types of Contracts
0%
Contractors RiskType of ContractEmployers Risk
Contracts & Planning Department
Contracts & Planning Department
Measurement for payment of drilling holes in any
material will be made per linear metre actually drilled
and when specified per hole drilled for setting up the
drilling machine, shifting it from one borehole to
another, within the site limits, including erection,
dismantling and linking with energy and water sources.
No measurement is made for re-drilling when grouting is
carried-out by progress procedure.
6. MEASUREMENT AND PAYMENT Of Drilling Works
Contracts & Planning Department
All boreholes stopped due to fault of the Contractor
before reaching the depth required by the Engineer will
not be considered for payment.
6. MEASUREMENT AND PAYMENT Of Drilling Works
Contracts & Planning Department
Measurement for payment of water tests will be the
number of water tests satisfactorily carried-out in 5 m
sections or smaller than 5 m at the Engineer's request.
Measurement for drainage hole will be made on the
same basis as drilling.
Measurement of grouting work will be made per hole
drilled; when specified for handling and setting up the
grouting equipment and the removal of the same per
section grouted, and per kilo of dry material actually
injected.
6. MEASUREMENT AND PAYMENT Of Drilling Works
1. Drawings
2. Specification
3. Bills of Quantities
4. Conditions of Contract
5. Instructions to Tenderers
6. Soil Investigation Report
1.
2.
3.
4.
5.
6.
7. Contracts Document
4.1
Contracts & Planning Department
4.2
7.
8.
9.
10.
7. Agreement
8. Letter of Acceptance
9. Memorandum of Understanding
10.Contractors Schedules
Contracts & Planning Department
7. Contracts Document
悸悸悸悸悸 悸悸悸悸悸悸悸 悸悸悸悸 悸悸悸 悸悸悸悸悸
悸悸悸悸悸悸悸悸
悸悸悸悸悸
Contracts & Planning Department
Wishing you A Fruitful Training
Period at DCUAP
悸悸悸悸悸悸 悸悸悸悸 悸

More Related Content

Contract adminstration and planning

  • 1. Ministry of Water Resources & Electricity Dams ImplementatIon UnIt GENERAL DIRECTORATE OF PROJECTS DAM COMPLEX OF UPPER ATBARA PROJECT Brief Introduction to Contracts& Planning Works ENG.Awad Hamdan Contracts & Planning Department
  • 2. 1.Contract 1.1 Definition: A voluntary, deliberate, and legally binding agreement between two or more competent parties Contracts & Planning Department
  • 3. 1.Cotracts 1.2 Contracts Essentials Offer Acceptance Objective Obligations Consideration Competent Parties Contracts & Planning Department
  • 4. 2. Project 2.1 Definition Set of one or more activities that should be performed within a period of time , budget and quality. Contracts & Planning Department
  • 5. Contracts & Planning Department Project planning is the process that defines the project activities and end products that will be performed and describes how the activities will be accomplished. The purpose of project planning is to define each major task, estimate the time and resources required, and provide a framework for management review and control. 2. Project 2.3 Project Planning
  • 6. Contracts & Planning Department project planning activities Scope: To define the specific work to be performed and goals that define and bind the project. to define the Estimates to be documented for planning, tracking, and controlling the project. to define Commitments that are planned, documented, and agreed to by affected groups. Project alternatives, assumptions, and constraints. 2. Project
  • 7. 2. Project The planning process includes steps to estimate the size of the project, estimate the technical scope of the effort, estimate the resources required to complete the project, produce a schedule, identify and assess risks, and negotiate commitments. Contracts & Planning Department
  • 8. 2. Project Repetition of the previous steps is necessary to establish the project plan. Typically, several iterations of the planning process are performed before a plan is actually completed. Contracts & Planning Department
  • 9. 3. Construction Projects 3.1 Construction Project Parties Client (Employer) Consultant (Engineer) Contractor 3.2 Contractual Relationship Between Parties Employer-Consultant Contract Employer-Contractor Contract Contracts & Planning Department
  • 10. 4. Projects Constraints Contracts & Planning Department
  • 11. Measurement Contract Lump-sum Contract Direct Labour Contract Cost Plus Contract Based on Price Determination 5. Types of Contracts Contracts & Planning Department
  • 12. 100% Lump-sum Contract Measurement Contract Cost Plus Contract Direct Labour Contract 0% 100% 5. Types of Contracts 0% Contractors RiskType of ContractEmployers Risk Contracts & Planning Department
  • 13. Contracts & Planning Department Measurement for payment of drilling holes in any material will be made per linear metre actually drilled and when specified per hole drilled for setting up the drilling machine, shifting it from one borehole to another, within the site limits, including erection, dismantling and linking with energy and water sources. No measurement is made for re-drilling when grouting is carried-out by progress procedure. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 14. Contracts & Planning Department All boreholes stopped due to fault of the Contractor before reaching the depth required by the Engineer will not be considered for payment. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 15. Contracts & Planning Department Measurement for payment of water tests will be the number of water tests satisfactorily carried-out in 5 m sections or smaller than 5 m at the Engineer's request. Measurement for drainage hole will be made on the same basis as drilling. Measurement of grouting work will be made per hole drilled; when specified for handling and setting up the grouting equipment and the removal of the same per section grouted, and per kilo of dry material actually injected. 6. MEASUREMENT AND PAYMENT Of Drilling Works
  • 16. 1. Drawings 2. Specification 3. Bills of Quantities 4. Conditions of Contract 5. Instructions to Tenderers 6. Soil Investigation Report 1. 2. 3. 4. 5. 6. 7. Contracts Document 4.1 Contracts & Planning Department
  • 17. 4.2 7. 8. 9. 10. 7. Agreement 8. Letter of Acceptance 9. Memorandum of Understanding 10.Contractors Schedules Contracts & Planning Department 7. Contracts Document
  • 18. 悸悸悸悸悸 悸悸悸悸悸悸悸 悸悸悸悸 悸悸悸 悸悸悸悸悸 悸悸悸悸悸悸悸悸 悸悸悸悸悸 Contracts & Planning Department Wishing you A Fruitful Training Period at DCUAP 悸悸悸悸悸悸 悸悸悸悸 悸