This document provides biographical information about Emad Boutros' professional experience from December 1987 to March 1990 working on Contract No. 25 for the west bank Cairo wastewater system project in Egypt. It describes the major components of the contract which included constructing 7.6 km of twin culverts connecting the Pyramids pumping station to the new treatment plant. It also outlines some of the project challenges around dewatering and excavation works given the high water table and saturated soil conditions. Over 750,000 cubic meters were excavated and 600,000 cubic meters of concrete with 9,000 tons of rebar were used.
1 of 6
More Related Content
Contract No. 25 west bank Cairo – wastewater system.
1. Arab Republic of Egypt - Cairo
Contract No. 25 west bank Cairo – wastewater system.
CURICULUM VITAE : EMAD BOUTROS
December 1987- March 1990
The Project : great Cairo wastewater system projects – Egypt - a US- AID
funded programme. The project was jointly financed by British –
American engineering consultants named AMBRIC. ( Ambric is a joint venture of
four design firms, two British and two U.S.: John Taylor & Sons (London), Binnie &
Partners (London), Camp Dresser & McKee (Boston), and Black & Veatch
International (Kansas City) ).
Contract No. 25 west bank Cairo – wastewater system.
George A. Fuller Company – general contractor.
The major item of this contract was the construction of twin- culvert ( 2.60m wide * 2.00m hight )
connecting the pyramids pumping station with the new treatment plant at Abu - Rawash. The total
length of the culvert was 7.6 Km along Mansoureya canal.
The project challenges / my professional experience :
- The water table on the flood plain is about 2 to 3 m below the ground surface. In
many areas the sand aquifer is confined by clays and silts.
- The structures was 5m to 10m below ground surface in the saturated alluvium and
therefore groundwater plays a significant part during construction.
- Site investigations were carried out to determine the static water levels and quality of
groundwater. Permeability of the aquifer was ascertained by means of pumping tests.
1
2. Arab Republic of Egypt - Cairo
Contract No. 25 west bank Cairo – wastewater system.
CURICULUM VITAE : EMAD BOUTROS
December 1987- March 1990
- The geotechnical designer was Dr. mamdouh hamaza.
- The dewatering system using mostly deep wells and occasionally
and occasionally well points
-The retaining wall system: bur lien wall ( using solder piles and lagging bracing by
wailers and struts), sheet pilling, side slope, secant piles ---etc. Depending on the depth
and soil stratification.
2
3. Arab Republic of Egypt - Cairo
Contract No. 25 west bank Cairo – wastewater system.
CURICULUM VITAE : EMAD BOUTROS
December 1987- March 1990
-excavation works done in two
stages with excavated quantity
more than 750,000 cu.m.
600,000 cu.m of concrete and 9,000 tons of Rebar's
3
4. Arab Republic of Egypt - Cairo
Contract No. 25 west bank Cairo – wastewater system.
CURICULUM VITAE : EMAD BOUTROS
December 1987- March 1990 1988- 1989
-culvert steel formwork fabricated at CFY- SA
-culvert walls lined by acid resistant
bricks ( blue bricks ) sealed by acid
resistant pointing mortar.
- in addition to contract 25, we get
contract of operation and maintained
works at seven pumping stations (
Zenain stations ) and construction of
approximately 2.5 kilometers of
forced main lines.
4
5. Arab Republic of Egypt – Cairo
Contract No. 25 west bank Cairo –
wastewater system.
institute of wastewater great Cairo.
CURICULUM VITAE : EMAD BOUTROS
December 1987- March 1990
5
6. ARCHIRODON Group.
ARCHIRODON was established in 1959 in the form of a J.V. of the
Greek firms ARCHIMIDIS, Greece's foremost marine contractor at the
time, and ODON & ODOSTROMATON, a road and bridge construction
specialist group.
Guided by Constantinos Karpidas, one of Greece's most prominent
construction pioneers, the J.V. started its professional life by building the
ports of Benghazi in Libya (1961) and subsequently the port of Beirut,
Lebanon (1962).
Its success soon led it to develop into a major contractor in its own merit,
establishing itself in 1971 as ARCHIRODON CONSTRUCTION
(OVERSEAS) CO. S.A. Under sound management, a dedicated
professional staff and the quality and reliability of its work, the company
further developed, expanding its operations initially in Saudi Arabia and
subsequently in other Gulf countries, North Africa and the Mediterranean
area.
Additionally, after American International Contractors Inc. - AICI (a US company initially
operating under the name of George A. Fuller Co.) became part of ARCHIRODON Group
in the late 1980's, there has been further expansion in USAID and US Corps of Engineers
projects in Somalia, Jordan, Kuwait, Sudan and Egypt.
At present ARCHIRODON GROUP N.V., registered in the Netherlands, is the legal parent of
all ARCHIRODON Group companies which have established offices and branches and/or
project sites in, Saudi, Arabia, the UAE, Kuwait, Bahrain, Egypt, Jordan, Libya, Oman,
Qatar, Singapore, Kazakhstan, Cyprus and Greece.
6