BIG TEE BRIDGE REPLACEMENT
County Route 14 over Leading Creek
Randolph County, WV
State Project No. S342-14-0.06
Project Sponsor
 West Virginia DOT, Division of Highways
District 8
Purpose of the Project
 To replace the existing structure with a
bridge that meets the requirements set
forth by the West Virginia Bridge Design
Manual and the Design Directives.
  and in a hurry
Project Site
Project Site
flow
flow
CR14 looking upstation (north)
West Elevation (looking downstream)
Dave Scott
Ron Klavuhn
Stanford Mills
Lora Freeman
Dave Morgan
Chad Mann
OBEC Consultants
Salem, Oregon
Project Team
Owner Agency
WVDOH
District 8
Contractor
C.L. Belt
Construction
Substructure &
Foundation
Engineer
WVDOH
District 8
Superstructure
Designer/
Fabricator
U.S. Bridge
Project Timeline
Originally
Programmed
1999
Funding
Approved
Early 2009
Begin 07/09
End 09/10
Adv 09/29/10
Let 10/26/10
Awd 10/28/10
Begin 02/11
End 11/11
Design
Phase
Programming
Phase
Bid
Phase
Construct
Phase
13 months 1 month 9 months10 years
programmed as an ASAP project
ASAP Project
 An ASAP Project is a fast-track project
with limited details that is bid as lump
sum. The contractor is responsible to
apply for permits, to arrange for utility
relocations, to make the material
selections with the suppliers, and
construct the project meeting the
requirements, such as waterway opening,
design loading, and general geometry.
Funding

More Related Content

CR14 over Leading Creek - Big Tee Bridge Replacement, Randolph County, WV (03-21-12)

  • 1. BIG TEE BRIDGE REPLACEMENT County Route 14 over Leading Creek Randolph County, WV State Project No. S342-14-0.06
  • 2. Project Sponsor West Virginia DOT, Division of Highways District 8
  • 3. Purpose of the Project To replace the existing structure with a bridge that meets the requirements set forth by the West Virginia Bridge Design Manual and the Design Directives. and in a hurry
  • 7. Dave Scott Ron Klavuhn Stanford Mills Lora Freeman Dave Morgan Chad Mann OBEC Consultants Salem, Oregon Project Team Owner Agency WVDOH District 8 Contractor C.L. Belt Construction Substructure & Foundation Engineer WVDOH District 8 Superstructure Designer/ Fabricator U.S. Bridge
  • 8. Project Timeline Originally Programmed 1999 Funding Approved Early 2009 Begin 07/09 End 09/10 Adv 09/29/10 Let 10/26/10 Awd 10/28/10 Begin 02/11 End 11/11 Design Phase Programming Phase Bid Phase Construct Phase 13 months 1 month 9 months10 years programmed as an ASAP project
  • 9. ASAP Project An ASAP Project is a fast-track project with limited details that is bid as lump sum. The contractor is responsible to apply for permits, to arrange for utility relocations, to make the material selections with the suppliers, and construct the project meeting the requirements, such as waterway opening, design loading, and general geometry.