ºÝºÝߣ

ºÝºÝߣShare a Scribd company logo
@Rob_Garvey
#G4CData
Rob Garvey
University of Westminster
25th February 2015
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 2
Data in
Construction
Current
data use?
Influence
of BIM
Data
capability
Effective
use of
data
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 3
@Rob_Garvey
#G4CData
ACI Blog post June 2014
http://aci.info/2014/07/
12/the-data-explosion-in-
2014-minute-by-minute-
infographic/
G4C Data in ConstructionFebruary 2015 4
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 5
@Rob_Garvey
#G4CData
G4C Data in Construction
February 2015
6
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 7
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 8
@Rob_Garvey
#G4CData
G4C Data in Construction
February 2015
9
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 10
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 11
Source Causes of Time Waste
Design
Interaction between various specialists
Rework due to design changes and revisions
Lack of information about types and sizes of
materials on design documents
Error in information about types and sizes of
materials on design documents
Contradictions in design documents
Delay in approval drawings
Procurement
Delay in material supply
Receiving materials that do not fulfil project
requirements defined on design documents,
and waiting for replacement
Delay in transportation and/or installation of
equipment
Operation
Scarcity of crews
Unrealistic master schedule
Rework due to workers¡¯ mistakes
Scarcity of equipment
Waiting for design documents and drawings
Lack of coordination among crews
Choice of wrong construction method
Accidents due to lack of safety
Examples of time waste (Polat and Ballard 2004)
Many due to poor information management
@Rob_Garvey
#G4CData
? Improving decision
making process and
working collaboratively
? The government is
going to get good at
buying data
G4C Data in Construction
February 2015
12
May¡¯11
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 13
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 14
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 15
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 16
Ref: Terry Stocks, Keynote speech at RICS BIM Conference Feb¡¯15
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 17
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 18
Influence of
BIM
Improving
process
Data
Drops
Decision
Density
Examples
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 19
Ref: John Eynon, B1M University
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 20
http://www.theb1m.com/
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 21
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 22
@Rob_Garvey
#G4CData
Decision density
starts to increase in
a BIM environment
Ref: Dave Monswhite
aka @noscalerule
G4C Data in ConstructionFebruary 2015 23
@Rob_Garvey
#G4CData
Decision density
v
Intelligence density
Information utility
Ref: Dave Monswhite aka @noscalerule
G4C Data in ConstructionFebruary 2015 24
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 25
@Rob_Garvey
#G4CData
Design office On-site
RFID data
G4C Data in Construction
February 2015
26
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 27
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 28
Data
capability
Data
basics
Client
requirements
Performance
management
Skills
required
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 29
Data
capability
Data
basics
Client
requirements
@Rob_Garvey
#G4CData
? Challenge
? Constant plea to improve
? Check
? Progress; planned against
actual
? Comply
? Non-negotiable obligations
G4C Data in ConstructionFebruary 2015 30
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 31
Ref: https://www.linkedin.com/pulse/how-marissa-mayer-got-yahoo-
moving-again-nicholas-carlson
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 32
@Rob_Garvey
#G4CData
G4C Data in ConstructionFebruary 2015 33
@Rob_Garvey
#G4CData
? Think differently about data
? Understand data requirements
? Align to purpose
? Comply / Check / Challenge
? Improve data efficiency
? Hidden waste / duplication / GIGO
? Acquire data at appropriate point
? Develop data capabilities
G4C Data in ConstructionFebruary 2015 34

More Related Content

Data in Construction for G4C

Editor's Notes

  1. Understand the information and data you require and identify whether this is being produced by others and could be bought as part of the transaction ¡­ it¡¯s one of the key reasons why the government strategy focuses on data.
  2. It recognises that much of the problems faced during operations is due to poor information transfer at the end of a project and this data could easily have been asked for at the start of the project ¡­ we just haven¡¯t done so. But acquiring the data is all part of improving the decision making process. If we just have quick look at the overarching objective of the GCS ¡­
  3. We¡¯ll see it is about reducing costs ¡­ come and listen to my talk at the London Constructing Excellence Club event on 12th May and I¡¯ll give you an update on whether these reductions have been achieved by the end of the parliament. However a fundamental part of the strategy is the implementation process and articulating how these savings could be achieved ¡­ Move SLIDE
  4. The Government Construction Strategy highlights the poor management of data by the public sector and the first issue here is ¡­ how to better leverage the data the public sector requires principally to inform better decision making The strategy focuses on how to improve the public sector approach to buying effectively and minimising the inefficiencies within the process by Increasing standardisation Aggregating demand Ensuring early contractor involvement, including with those at lower levels within the supply chain And encouraging the creation of integrated project teams. It¡¯s not my intention to debate these points, just to highlight this is where the Government perceive the opportunities to exist Move SLIDE
  5. Why do we need to get better a data management ¡­ well here is slide from BAM FM This shows the points at which data is transferred ¡­ ie at tender stage, handover and then with each change of FM provider ¡­ the grey blocks shows the gap in the transfer of data between the different parties ¡­ ie during construct the contractor is generating more information and this is not shared with the client until handover ¡­ Another example of this was shown last week at the RICS BIM Conference
  6. Referring to the Concrete pour example and BAM¡¯s slide, this shows the pattern of poor data management in the traditional process and highlgihts te Governments view that we can improve the situation ¡­ As this shows BIM can make this better ¡­ can¡¯t it?
  7. Yes , but ¡­ We talk about BIM in more detail, however there are
  8. There is still a catch mind. Any ideas what it is? Its called decision density. BIM does not reduce the number of decisions that need to be made, even if the quality of information has increased. In fact the opposite could be true ¨C richer information usually leads to a greater number of decisions needing to be made. We never used to consider all the variables we do now ¨C mostly due to unconscious unawareness. I now know exactly how much sun comes through the window ¨C decisions become more binary, but there are more of them¡­ Stakeholder management and gateway process becomes more important ¨C we still depend on high numbers of decision making people. Information is richer, but their ability to make decisions ¨C the judgement aspect, imagination, extrapolation of concepts to form the envelope of a decision does not change. BIM cannot replace this ¨C it still needs managing by someone. All those decisions to be recorded, chased, reported, enacted. No Jeremy Kyle for me then ¨C because its not likely the Architect will do all that. The time aspect is still critical, as are all the constraints. I can make better decisions ¨C but I still have to make lots of them, in the right sequence, timeously. The project management role is effectively the same, but now the inputs and decisions arrive harder and faster. BIM changes the way the team works ¨C and crucially, when elevated from a pure 3d drafting tool, presents our clients with far more to think about.
  9. Dhar and Stein (1997) define Intelligence Density (ID) as the amount of useful ¡°decision support information¡± that a decision maker gets from using a system for a certain amount of time. Alternately ID can be defined as the amount of time taken to get the essence of the underlying data from the output. This is done using the ¡°utility¡± concept, initially developed in decision theory and game theory (Lapin & Whisler, 2002). Numerical utility values, referred to as utilities (sometimes called utiles) express the true worth of information. These values are obtained by constructing a special utility function. Thus intelligence density can be defined more formally as follows: Utilities of decision making power gleaned (quality) Intelligence Density = ----------------------------------------------------------------- Units of analytic time spent by the decision maker Increasing the intelligence density of its data enables an organization to be more effective, productive, and flexible.
  10. If you believe the matrix, the world is made up of data ¡­ are we in a game?
  11. We¡¯re reliant on computers and information technology ¡­
  12. It¡¯s important and valuable