DDiioossyynntthh -- MMeerrcckk 
EEvvaappoorraattoorr 
August 2009 to October 2010
EEvvaappoorraattoorr 
Project Scope 
 An Evaporator System was required to remove the organic solids from the waste 
stream generated by Porcine Heparin batch production process. The objective is to 
vaporize the water and separating from the concentrated solids (~ 45% solids) stream 
that will be sent for landfill. The evaporated water must be condensed and will be sent 
for further downstream on-site waste treatment prior to discharge to the Sabesb sewer. 
 Each digestion sub batch consists of 36,000 kgs of Mucosa. The site currently 
produces six batches per week with batches completing digestion from Monday night 
through to Thursday. The maximum number of batches per week is currently six, but 
may be increased to 8 batches per week when about 20 % of ribbons are added to the 
mucosa. Processing of ribbons in Mucosa will increase the peptone volume by 25%. 
 If required, then vendor to include a CIP skid with holding tank. 
 The Evaporator and associated equipment shall be in continuous operation 365 days 
per year except when cleaning and maintenance is required. 
 The Supplier should therefore consider the following supply as a minimum: 
 Complete engineering design; lay out of the system, specifications and process 
responsibility for the complete evaporator system package. Civil and structural design 
with will be done by a third part. Vendor should include design review man hours. 
 Supply of the major equipment and critical items. 
 Control system and software. 
 Any proprietary or custom equipment as part of the evaporator package.
EEvvaappoorraattoorr 
Project Functional Chart 
GES 
Manager 
corporate 
Procurement 
Safety 
Supervisor 
Document 
Control 
Mechanical 
Technician 
Cost Control 
Cash Flow 
Civil 
Engineer 
Planning 
Engineer 
JJ 
Engineering 
Consulting 
SHE 
Director 
corporate 
SHE 
Manager 
E&I 
Technician 
Safety 
Technician 
Construction- 
Assembly 
Team 
GES Project 
Support 
corporate 
Utilities 
Operator
EEvvaappoorraattoorr 
Conceptual Design, 1rst draft
EEvvaappoorraattoorr 
Civil Works
EEvvaappoorraattoorr 
Follow-Up at Supplier
EEvvaappoorraattoorr 
Follow-Up at Supplier
EEvvaappoorraattoorr 
Unloading and Positioning Equipment
EEvvaappoorraattoorr 
Unloading and Positioning Equipment
EEvvaappoorraattoorr 
Unloading and Positioning Equipment
EEvvaappoorraattoorr 
Equipment Assembly
EEvvaappoorraattoorr 
Equipment Assembly
EEvvaappoorraattoorr 
Equipment Assembly
EEvvaappoorraattoorr 
Equipment Assembly
EEvvaappoorraattoorr 
Equipment Assembly
EEvvaappoorraattoorr 
Control System
EEvvaappoorraattoorr 
Site Master Plan 
IInniittiiaall LLaayyoouutt 
FFiinnaall LLaayyoouutt 
CChheemmiiccaall SSttoorraaggee TTaannkkss 
LLPPGG TTaannkkss 
CCoonnttrraaccttoorr SShhoopp 
CCoovveerreedd PPaarrkkiinngg 
CCoonnttrrooll RRoooomm 
TTeemmpp SSoollvveenntt TTaannkkss 
PPrroodduuccttiioonn BBuuiillddiinngg 
WWaarreehhoouussee 
NNeeww 
SSuubbssttaattiioonn 
EEvvaappoorraattoorr 
BBiioollooggiiccaall 
UUnniitt 
CCoovveerreedd PPaarrkkiinngg 
GGuuaarrddhhoouussee 
FFiirree PPuummpp 
TTrruucckk 
PPaarrkkiinngg 
BBooiilleerr HHoouussee
EEvvaappoorraattoorr 
Project Overall Schedule 
Order 
Kick-Off 
Start Quotation up 
Negotiation 
Construction - Assembly 
Commissioning 
Total Investment: US$ 1,5 Millions

More Related Content

Diosynth Evaporator

  • 1. DDiioossyynntthh -- MMeerrcckk EEvvaappoorraattoorr August 2009 to October 2010
  • 2. EEvvaappoorraattoorr Project Scope An Evaporator System was required to remove the organic solids from the waste stream generated by Porcine Heparin batch production process. The objective is to vaporize the water and separating from the concentrated solids (~ 45% solids) stream that will be sent for landfill. The evaporated water must be condensed and will be sent for further downstream on-site waste treatment prior to discharge to the Sabesb sewer. Each digestion sub batch consists of 36,000 kgs of Mucosa. The site currently produces six batches per week with batches completing digestion from Monday night through to Thursday. The maximum number of batches per week is currently six, but may be increased to 8 batches per week when about 20 % of ribbons are added to the mucosa. Processing of ribbons in Mucosa will increase the peptone volume by 25%. If required, then vendor to include a CIP skid with holding tank. The Evaporator and associated equipment shall be in continuous operation 365 days per year except when cleaning and maintenance is required. The Supplier should therefore consider the following supply as a minimum: Complete engineering design; lay out of the system, specifications and process responsibility for the complete evaporator system package. Civil and structural design with will be done by a third part. Vendor should include design review man hours. Supply of the major equipment and critical items. Control system and software. Any proprietary or custom equipment as part of the evaporator package.
  • 3. EEvvaappoorraattoorr Project Functional Chart GES Manager corporate Procurement Safety Supervisor Document Control Mechanical Technician Cost Control Cash Flow Civil Engineer Planning Engineer JJ Engineering Consulting SHE Director corporate SHE Manager E&I Technician Safety Technician Construction- Assembly Team GES Project Support corporate Utilities Operator
  • 8. EEvvaappoorraattoorr Unloading and Positioning Equipment
  • 9. EEvvaappoorraattoorr Unloading and Positioning Equipment
  • 10. EEvvaappoorraattoorr Unloading and Positioning Equipment
  • 17. EEvvaappoorraattoorr Site Master Plan IInniittiiaall LLaayyoouutt FFiinnaall LLaayyoouutt CChheemmiiccaall SSttoorraaggee TTaannkkss LLPPGG TTaannkkss CCoonnttrraaccttoorr SShhoopp CCoovveerreedd PPaarrkkiinngg CCoonnttrrooll RRoooomm TTeemmpp SSoollvveenntt TTaannkkss PPrroodduuccttiioonn BBuuiillddiinngg WWaarreehhoouussee NNeeww SSuubbssttaattiioonn EEvvaappoorraattoorr BBiioollooggiiccaall UUnniitt CCoovveerreedd PPaarrkkiinngg GGuuaarrddhhoouussee FFiirree PPuummpp TTrruucckk PPaarrkkiinngg BBooiilleerr HHoouussee
  • 18. EEvvaappoorraattoorr Project Overall Schedule Order Kick-Off Start Quotation up Negotiation Construction - Assembly Commissioning Total Investment: US$ 1,5 Millions