The document provides details of an elemental cost analysis for a residential construction project consisting of two blocks, A and B, with a total gross floor area of 2023 square meters. It includes information on the project scope, building plans, area breakdowns by usage, and a brief cost summary. The total contract sum is RM1,588,044.50 with contingencies of 5.6% of the contract sum.
1 of 40
More Related Content
Elemental cost analysis Presentation 際際滷s
1. Elemental Cost Analysis
GROUP E
Group Members :
Calvin Wong Kim Ming 0323642
Chan Wei Lun 0326117
Ee Hui Teng 0322548
Fong Kah Yan 0322815
Gillian Chong Yeong Lin 0323941
Koh Ee Sing 0323855
Kok Ka Shing 0323553
Loh Mun Tong 0323680
Loh Wen Jun 0323551
Muhammad Fareez 0322961
Sew Yue Ling 0327032
Tan Jia San 0322406
Vivian Chin Kha Yee 0331228
Yeong Poh Ling 0323590
2. PROJECT DETAILS
Address: Above Lot 597, Jalan Gempita 1, Taman Salak Selatan Mukim Petaling, Kuala
Lumpur
Building Purposes: Residential
Type of Project: Private
Contract Information: PAM, Private Edition 1998 (without quantities)
Contract Period Stipulated by Client: 52 weeks
Gross Floor Area: 2023 m族
18. Gross Floor Area: 336 m族
Per floor
Block B
(First Floor and Second Floor)
19. Total Gross Floor Area
Location Block A Block B
Total Gross Floor Area
(m族)
Ground Floor 338 336 674
Upper Floors 676 672 1348
Gross Floor Area 2023
20. Total area of all enclosed spaces fulfilling the main
functional requirements of the building (e.g. office
space, shop space, public house drinking area, etc.).
USABLE
26. Total area of all enclosed spaces for lavatories,
cloakrooms, kitchens, cleaners rooms, lift, plant and
tank rooms and the like, supplementary to main
function of the building.
ANCILLARY
28. The area occupied by partitions, columns, internal
structure or party walls.
Note : The sum of the areas falling in the categories
defined above wil equal the Gross Floor Area.
INTERNAL DIVISION
29. Block A
(Ground Floor, First
Floor & Second
Floor)
Internal Division: 45
m族
Internal Partition Wall
Internal Wall
30. Block B
(Ground Floor, First
Floor & Second
Floor)
Internal Division: 48
m族
Internal Partition Wall
Internal Wall
31. Total Gross Floor Area
Location Block A Block B Total Area (m族)
Usable Area 878 866 1744
Circulation Area 91 94 185
Ancillary Area N/A N/A N/A
Internal Division 44 48 93
Gross Floor Area 2023
33. 艶ю ヰ
ヰ
=
.
.
m族
= 1.023
Functional Unit: 1744.218 m族
External Wall Area
Block A - 1103.536
Block B - 966.606
34. Storey Heights
Average Below Ground
Floor: N/A m
At Ground Floor: 3.05m
Above Ground Floor:
6.10m
Ground Floor
First and Second Floor
35. Design / Shape:
Percentage of gross floor area:
A) Below Ground Floor: N/A%
B) Single - Storey Construction: N/A %
C) Two - Storey Construction: N/A %
D) Three - Storey Construction: 100%
36. Brief Cost Information
Contract Sum: (RM) 1,588,044.50
Provisional Sums: (RM) 150,000.00
Prime Cost Sums: (RM) 0.00
Preliminaries: (RM) 79,415.22 being 5.26 %) of remainder
Contingencies: (RM) 80,000.00 being 5.60 %) Contract Sum
Contract Sum
less Contingencies: (RM) 1,508,044.50
Functional Unit Costs excluding
external works: RM 643.80/ m族
37. Discount and Rationalisation
Total Contract Sum RM 1,598,044.50
Contingency RM (80,000.00)
Provisional Sum RM (150,000.00)
RM 1,368,044.50.
Total discount = RM 10,000.00
Discount =
10,000.00
1,368044.50
100%
= 0.730970374%
After discount = RM 1,588,044.50