The El-Shabab power plant project in Egypt will add 1000 megawatts of electricity generating capacity to meet growing demand. Kharafi National is constructing the project on an EPC basis, including installing 8 gas turbine generators each with 125 megawatts of output. The project is well on schedule to be completed in June 2021, with turbines installed and civil and mechanical works advancing. At over $1 billion, it is one of Kharafi National's largest projects and winning the contract demonstrates their capabilities in large power plant construction.
1 of 1
Download to read offline
More Related Content
El-Shabab power plant-1
1. 5
ISSUE NO. 28
Projects EPCM
El-Shabab power plant
Rapid economic development and a
fast-expanding population mean that
the output of Egypts energy sector
requires substantial expansion. The
El-Shabab power plant project will
add an additional 1000 mega-watts to
the countrys electricity-generating
capacity.
The client is the East Delta Electricity
Production Company, a state-owned
entity which operates under the Ministry
of Electricity in Egypt. El-Shabab is
located in El-Salhiya, which is about
85km north-east of Cairo.
Khara鍖 National is undertaking
the engineering, procurement and
construction of eight gas turbine
generators, each with an output of
125 MW. As the EPC contractor, KN is
responsible for the design, delivery,
installation, testing and commissioning
of the units. The company will also be
synchronising the new generators with
Egypts national power grid.
The generators GE Frame 9 from the
USA were chosen and sourced by
KN, whose scope of work also includes
auxiliary equipment such as electronic
and electrical control cabinets, 鍖n fan
coolers, exhaust stacks, compressor
and turbine washing skids, and so on,
as well as two solar tanks, a water
services tank, a reverse osmosis (RO)
tank and a demineralization tank.
The scope of work covers all related civil
works, such as the foundations for the
turbines and skids, electrical buildings,
control buildings, the gas-insulated
switch-gear building, medium and low
voltage buildings, the RO treatment
plant, an industrial waste plant, a
fabrication shop and the associated
warehousing.
KN is also constructing the infrastruc-
tural utilities and underground net-
works that will serve the power units, including water and sewage treatment plants,
along with all associated piping, the electrical high, medium and low cable networks,
and the instrumentation networks. In addition, the company is building the road
network for the entire plant.
The project is well on schedule to be 鍖nished in June this year. All eight turbines and
their ancillaries have been installed on their foundations, while the mechanical skids
for the 鍖rst six units are currently being put in. The civil and mechanical works are
at an advanced stage and the construction of the underground utilities and tanks are
in progress.
El-Shabab power plant project is massive and the generators KN is installing are
immense, as can be seen from the photograph. Financially, it is one of the largest
projects KN has ever undertaken and winning the tender was, in itself, a massive
endorsement of Khara鍖 Nationals capabilities in the EPC of power plants. Its
successful completion will consolidate the companys reputation in the Egyptian
market and propel it to the forefront of international bidders for mega-sized power
plant projects in the Middle East.
Strenuous efforts to develop the Egyptian market are now paying off in a big way and Khara鍖
National was recently awarded several mega-projects in Egypt. One of these is El-Shabab
power plant project one of the largest projects KN has ever undertaken on its own.
Project Brief
El-Shabab Power Plant Project
Client : East Delta Electricity Production Company
Main Contractor : Khara鍖 National
Project Number : 3044
Scope of Work : EPC design, delivery, installation, testing,
commissioning and synchronising 8 power units
with total output 1000MW
Start : October 2010
Finish : June 2011
Duration : 8.5 months
Employees (at peak) : 4,500