The document discusses the process of constructing new railway lines, including preliminary investigations such as traffic and reconnaissance surveys, final location surveys, and modern surveying techniques. It also describes the construction steps such as land acquisition, earthworks, bridge building, track laying using different plate laying methods, and ballasting of tracks. The construction of each mile of new railway line requires 15 to 20 million rupees depending on the topography, construction standard, and other features of the area.
1 of 16
Downloaded 311 times
More Related Content
Engineering surveys and construction of new lines
1. PRESENTERS
RAHMAT ALI SU/10-001-074081
NASIRUDDIN SU/10-001-074075
NUMAN NAZIR SU/10-001-074122
SARHAD UNIVERSITY OF SCIENCE & INFORMATION TECHNOLOGY
PESHAWAR
DATE: 22 Dec,2012
2. INTRODUCTION
The construction of a new
railway is a huge project
and each mile required
Rs.15 to 20 million
depending upon:
The topography of area
Standard of construction
And some other features
3. Why we construct a new
railway lines?
The need of constructing new railway line arises
because of one or more consideration such as:
Political reason.
Development of backward areas.
To connect new trade centers.
To shorten the existing rail link etc.
4. Preliminary investigations for a new
railway line
Traffic survey:
It includes detail
study of traffic
condition:
Possible traffic
the railway line
carry.
Standard of
railway line.
Promising traffic
the railway line
will carry.
5. Preliminary investigations for a new
railway line
Reconnaissance
survey:
This survey consists of a rapid
and rough investigation of the
area by using equipments of
survey:
Such as
Prismatic compass
Binocular
pedometer
Geodimeter
for measurement upto 80 km
distance during day and night
Use of laser etc
Distance upto 70 km can be
measured using laser.
6. Preliminary investigations
for a new railway line
Preliminary survey:
This survey consists of a detailed
instrumental examination of the
route to be selected in order to
estimate the cost of the proposed
railway line
By using:
Total station
Tachometer
Dumpy level etc.
7. Final location survey
Once a decision has been taken for a particular railway line to
be constructed a final location survey is done
Instruments used are the same as in the case of preliminary
survey
Alignment is fully staked.
More detailed project report is prepared.
All working drawings are prepared.
9. CONSTRUCTION OF NEW RAILWAY LINES
Once the survey completed then construction
works begin
It includes
Land acquisition
Earthwork and bridges
Station building, staff quarters
Ballasting of tracks
10. CONSTRUCTION OF NEW RAILWAY LINES
Land acquisition:
It includes:
Width of formation.
Side slopes.
Width of berms.
Borrow pits.
11. CONSTRUCTION OF NEW RAILWAY LINES
Earth work for formation:
The height of earth work depends on the high flood level.
Mechanically compaction is done generally by sheep foot
roller.
12. CONSTRUCTION OF NEW RAILWAY LINES
Bridges construction:
Bridges increased the cost of the railway project.
Bridges may be:
Reinforced cement slab bridges.
Steel bridges etc.
13. CONSTRUCTION OF NEW RAILWAY LINES
Track laying:
Once the formation is ready then
just track laying are required.
It consists:
Laying of ballast
Laying of sleepers and rails
Fastenings
14. PLATE LAYING METHODS
1) Tram line method:
A temporary line laid
by the side of proposed
track.
Modification of this
method is the side
method.
Side method are
applicable when the
service road is parallel to
the track
15. PLATE LAYING METHODS
2) American method:
Rails and sleepers are
first assembled and then
taken to the site.
At site track panels are
then unloaded either
manually or with the help
of cranes
For concrete sleepers
generally cranes are used.