際際滷

際際滷Share a Scribd company logo
Estimating & Costing - I
ESTIMATION
Estimation or estimating is the process of
calculating the quantities of various items of
works involved in the project.
ESTIMATE
Estimate is a document which furnishes the quantities
of different works involved, their rates and the
expenditure anticipate in a project
NECESSITY OF ESTIMATES
 To know about the approximate cost of the
building construction.
To calculate the tax of the building
To fix the rent of building
The know about the various items of works
involved in the building construction and arrange
the available materials of the construction.
To arrange the labours of the construction works.
Take the approval for the government projects.
To having the loan from the bank.
QUANTITY SURVEYOR
 Takking Off Quantities
 Squaring Dimension And Calculating Of Quantity
 Data (Calculation Of Rate Per Unit)
 Abstract Estimate
 Measurement Billing.
DUTIES OF QUANTITY SURVEYOR
The quantity surveyor must be well versed with the
drawing of work.
He should be able to read the drawing correctly and
bill the quantities accurately.
He should have the knowledge of the construction
procedure
He should be able to write the description of different
works.
He should able to prepare the schedule of the project
He should be able to value all variations under the
contract.
TYPES OF ESTIMATE
The estimates may be divided in to the following categories:-
(1) Preliminary or Approximate estimate.
(2) Rough cost estimate based on plinth area.
(3) Rough cost estimate based on cubic contents.
(4) Detailed estimate.
(5) Annual repair estimate.
(6) Special repair estimate.
(7) Revised estimate
(8) Supplementary estimate.
(9)Complete estimate.
1. Preliminary or Approximate
Estimate
This estimate is prepared to decide financial aspect,
policy and to give idea of the cost of the proposal to the
competent sanctioning authority. It should clearly show the
necessity of the proposal and how the cost has been arrived
at .
The estimate which is prepared using any rough
method to get approximate cost of the construction
anticipate in a project is called approximate estimate.
The following documents should be attached with it.
(a) Detailed report
(b) Site plan of the proposal
(c) It should also clearly mention about the acquisition of
land, Provision of electric and water supply etc.
2. Plinth area Estimate (Based on
Rough Cost)
Plinth area of a building means Length x Breadth ( roofed
portion only ) excluding plinth offsets. The estimates are prepared on
the basis of plinth areas of the various buildings proposed to be
constructed. The rates are being arrived at the dividing the total cost of
construction with its plinth area.
The following documents are attached with the estimate.
(a) Line plan with brief specifications.
(b) Cost of various services added i.e. electric and water supply etc.
(c) North line should be shown clearly on line plan.
3. Detailed Estimate
 After getting Administrative approval on rough cost
estimate, detailed estimates are prepared.
 The estimate which provide the itemwise quantities of
works, itemwise unit rate and itemwise expenditure in
the project is called detailed estimate.
 In this, the estimate is divided in to sub-heads and
quantities of various items are calculated individually.
 The detailed estimate shall also provide for the cost of
approach road, water supply, electric installations and
acquisition of land etc., so as to call it a comprehensive
estimate.
4. Cubic Contents Estimate
 The cubic contents of a building means plinth area x
height of the building. The height is taken from top
of floor level to top of roof.
 The cubic contents of the proposed building are
multiplied with cubic rates arrived at for the similar
construction i.e. total cost of construction divided by
cubic contents = cost per cubic metre.
5. Annual maintenance estimate
Annual maintenance estimates are being prepared
by the concerned department for getting allocation
of funds made in the annual budgets.
In order to keep building and roads in perfect condition,
annual repairs should be carried out as follow:-
 (i) In case of a building-white washing, oiling and
painting of doors and windows, cement plaster repairs
(inside & outside), repairs of floors etc. In no case this
annual repair amount should increase more that 11/2%
to 2% of the capital cost of the building.
 (ii) In case of a road-filling patches, maintenance of
berms etc.
6. Special repair estimate
If the work cannot be carried out of the annual repair
funds due to certain reasons resulting in the genuine
increase in cost, then special repairs estimate is to be
prepared.
The reason of increase may be:-
 (i) In case of a building-opening of new doors, change of
floors, plastering walls etc.
 (ii) In case of roads-if the whole surface is full of
corrugation & patches, then the total surface is to be
scarified. The old metal is taken out, consolidation by
adding more metal is done and top surface is repainted.
7. Revised estimate
When the sanctioned estimate exceeds by 5% either due
to the rate being found insufficient or due to some other
reasons, a fresh estimate is prepared which is called a
Revised Estimate. A comparative statement on the last
page of the estimate is attached giving there in the
reasons of the increase of cost in case of each item.
8. Supplementary Estimate
This is fresh detailed estimate in addition to the original
sanctioned estimate prepared when additional works are
deemed necessary during the progress of a work to
supplement the original works. The abstract of cost
should show the amount of the original sanctioned
estimate as well as the supplementary amount of the
original sanctioned estimate as well as the
supplementary amount for which sanction is required.
9.Complete estimate
 The estimate which includes, in addition to the cost of
construction, the cost of land, the expenses towards
surveying, preparation of plans and estimates, legal
assistance, registration of documents, payment of
taxes and service charges , etc. Is called complete
estimate.
Sub estimate
Sub estimate are being prepared for
each and every such items in detail
to ensure and see that the expense
towards these items do not exceed
the corresponding provisions already
made in the original estimate.
THANKING YOU

More Related Content

Estimating & Costing - I

  • 2. ESTIMATION Estimation or estimating is the process of calculating the quantities of various items of works involved in the project.
  • 3. ESTIMATE Estimate is a document which furnishes the quantities of different works involved, their rates and the expenditure anticipate in a project
  • 4. NECESSITY OF ESTIMATES To know about the approximate cost of the building construction. To calculate the tax of the building To fix the rent of building The know about the various items of works involved in the building construction and arrange the available materials of the construction. To arrange the labours of the construction works. Take the approval for the government projects. To having the loan from the bank.
  • 5. QUANTITY SURVEYOR Takking Off Quantities Squaring Dimension And Calculating Of Quantity Data (Calculation Of Rate Per Unit) Abstract Estimate Measurement Billing.
  • 6. DUTIES OF QUANTITY SURVEYOR The quantity surveyor must be well versed with the drawing of work. He should be able to read the drawing correctly and bill the quantities accurately. He should have the knowledge of the construction procedure He should be able to write the description of different works. He should able to prepare the schedule of the project He should be able to value all variations under the contract.
  • 7. TYPES OF ESTIMATE The estimates may be divided in to the following categories:- (1) Preliminary or Approximate estimate. (2) Rough cost estimate based on plinth area. (3) Rough cost estimate based on cubic contents. (4) Detailed estimate. (5) Annual repair estimate. (6) Special repair estimate. (7) Revised estimate (8) Supplementary estimate. (9)Complete estimate.
  • 8. 1. Preliminary or Approximate Estimate This estimate is prepared to decide financial aspect, policy and to give idea of the cost of the proposal to the competent sanctioning authority. It should clearly show the necessity of the proposal and how the cost has been arrived at . The estimate which is prepared using any rough method to get approximate cost of the construction anticipate in a project is called approximate estimate. The following documents should be attached with it. (a) Detailed report (b) Site plan of the proposal (c) It should also clearly mention about the acquisition of land, Provision of electric and water supply etc.
  • 9. 2. Plinth area Estimate (Based on Rough Cost) Plinth area of a building means Length x Breadth ( roofed portion only ) excluding plinth offsets. The estimates are prepared on the basis of plinth areas of the various buildings proposed to be constructed. The rates are being arrived at the dividing the total cost of construction with its plinth area. The following documents are attached with the estimate. (a) Line plan with brief specifications. (b) Cost of various services added i.e. electric and water supply etc. (c) North line should be shown clearly on line plan.
  • 10. 3. Detailed Estimate After getting Administrative approval on rough cost estimate, detailed estimates are prepared. The estimate which provide the itemwise quantities of works, itemwise unit rate and itemwise expenditure in the project is called detailed estimate. In this, the estimate is divided in to sub-heads and quantities of various items are calculated individually. The detailed estimate shall also provide for the cost of approach road, water supply, electric installations and acquisition of land etc., so as to call it a comprehensive estimate.
  • 11. 4. Cubic Contents Estimate The cubic contents of a building means plinth area x height of the building. The height is taken from top of floor level to top of roof. The cubic contents of the proposed building are multiplied with cubic rates arrived at for the similar construction i.e. total cost of construction divided by cubic contents = cost per cubic metre.
  • 12. 5. Annual maintenance estimate Annual maintenance estimates are being prepared by the concerned department for getting allocation of funds made in the annual budgets. In order to keep building and roads in perfect condition, annual repairs should be carried out as follow:- (i) In case of a building-white washing, oiling and painting of doors and windows, cement plaster repairs (inside & outside), repairs of floors etc. In no case this annual repair amount should increase more that 11/2% to 2% of the capital cost of the building. (ii) In case of a road-filling patches, maintenance of berms etc.
  • 13. 6. Special repair estimate If the work cannot be carried out of the annual repair funds due to certain reasons resulting in the genuine increase in cost, then special repairs estimate is to be prepared. The reason of increase may be:- (i) In case of a building-opening of new doors, change of floors, plastering walls etc. (ii) In case of roads-if the whole surface is full of corrugation & patches, then the total surface is to be scarified. The old metal is taken out, consolidation by adding more metal is done and top surface is repainted.
  • 14. 7. Revised estimate When the sanctioned estimate exceeds by 5% either due to the rate being found insufficient or due to some other reasons, a fresh estimate is prepared which is called a Revised Estimate. A comparative statement on the last page of the estimate is attached giving there in the reasons of the increase of cost in case of each item.
  • 15. 8. Supplementary Estimate This is fresh detailed estimate in addition to the original sanctioned estimate prepared when additional works are deemed necessary during the progress of a work to supplement the original works. The abstract of cost should show the amount of the original sanctioned estimate as well as the supplementary amount of the original sanctioned estimate as well as the supplementary amount for which sanction is required.
  • 16. 9.Complete estimate The estimate which includes, in addition to the cost of construction, the cost of land, the expenses towards surveying, preparation of plans and estimates, legal assistance, registration of documents, payment of taxes and service charges , etc. Is called complete estimate.
  • 17. Sub estimate Sub estimate are being prepared for each and every such items in detail to ensure and see that the expense towards these items do not exceed the corresponding provisions already made in the original estimate.