This presentation was shared at the Euclid Planning Commission meeting on February 13, 2024.
For more information, please visit https://www.countyplanning.us/projects/euclid-pedestrian-bicycle-safety-action-plan/
1 of 34
Download to read offline
More Related Content
Euclid Pedestrian & Bicycle Safety Action Plan Presentation to the Euclid Planning Commission
2. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
OUR TEAM
• Mary Cierebiej, AICP, Executive Director
• James Sonnhalter, Planning Manager, Design & Implementation
• Dan Meaney, GISP, Manager, Information & Research
• Rachel Novak, AICP, Senior Planner (Project Lead)
• Kevin Leeson, Planner
• Paul Triolo, Planner
• Maureen Riley, Planner
• Liam Leveto, GIS Technician
• Luke Ols, Planning Intern
3. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
PROJECT TEAM
• Kirsten Holzheimer Gail, Mayor
• Patrick Grogan-Myers, EDFP, Planning & Development Director
• Christine McIntosh, Planning & Development Coordinator
• Daniel Knecht, Public Service Director
• Mac Stephens, Recreation Director
• Anthony Pellegrino, Fire Prevention Captain
• Kristian Jarosz, Ward 4 Council Member
• Kate McLaughlin, Community Policing Coordinator
• Patrick Higley, Director of Business Operations, ECSD
• Christopher Papouras, Superintendent, ECSD
4. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
AGENDA
PLANNING PROCESS REVIEW
RECOMMENDED ACTIONS
IMPLEMENTATION
QUESTIONS & DISCUSSION
5. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
PLANNING PROCESS REVIEW
6. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
OUR PROCESS | OVERVIEW
Collect and
analyze data,
trends, and
information to
establish current
snapshot
Collect feedback
to establish vision
for how the
community wants
to improve active
transportation
Outline specific
recommendations
to achieve the
desired vision
Outline
responsibilities,
partners, and
priorities for
accomplishing
recommendations
Finalize
document and
present Plan to
Planning
Commission/City
Council
ANALYSIS VISION ACTION STEPS IMPLEMENTATION FINAL PLAN
WE
ARE
HERE
7. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
OUR PROCESS | OVERVIEW
ANALYSIS VISION ACTION STEPS IMPLEMENTATION FINAL PLAN
START:
FEBRUARY
2023
FINISH:
February
2024
~12 MONTHS
WE
ARE
HERE
8. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
COMMUNITY
ENGAGEMENT
# Engagement Type
4 Project Team meetings
2 Public meetings/open houses
2 Online surveys (results reports)
1 Senior Center presentation
1 Chardon Hills HOA Presentation
1 Virtual Focus Group meeting
1 Focus Group walking tour
1 E. 200th Street Stroll table
1 Bike With a Mayor Event
1 League of American Bicyclists Workshop
9. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
RECOMMENDED ACTIONS
10. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
ACTIVE TRANSPORTATION OBJECTIVES
The City of Euclid will have an active
transportation network that:
1) Is inclusive of all ages and abilities
2) Supports creating informed citizens and
education opportunities
3) Is welcoming to all users
4) Is coordinated by prioritizing active
transportation projects
5) Is prepared for creating safe and convenient
connections
11. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
RECOMMENDED ACTIONS OVERVIEW
RECOMMENDED ACTIONS FOR A MORE PEDESTRIAN & BICYCLE FRIENDLY EUCLID
Goal A: Sidewalk Availability Goal H: Shared Transportation & Micromobility
Goal B: Road & Lane Diet Conversions Goal I: Wayfinding, Signage & Mobile Apps
Goal C: Buffered Bike Lakes & Two-Way Cycle Tracks Goal J: Bike/Ped Advisory Committee & Policing
Goal D: All-Purpose Trails & Sidepaths Goal K: Safe Routes to School
Goal E: Neighborhood Greenways & Traffic Calming Goal L: Complete & Green Streets Policy
Goal F: Temporary Installations Goal M: Zoning & Codified Ordinances
Goal G: Streetscaping & Amenities Goal N: Project Coordination & Collaboration
12. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CONNECTIVITY
NETWORK
13. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CONNECTIVITY
NETWORK
NEAR-TERM FACILITY IMPROVEMENTS (1-3 YEARS)
TARGET IMPLEMENTATION:
Sidewalks & Neighborhood Greenways
14. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CONNECTIVITY
NETWORK
MID-TERM FACILITY IMPROVEMENTS (3-7 YEARS)
TARGET IMPLEMENTATION:
Bike lanes & All-Purpose Trails
15. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CONNECTIVITY
NETWORK
LONG-TERM FACILITY IMPROVEMENTS (7+ YEARS)
TARGET IMPLEMENTATION:
Challenging All-Purpose Trail Connections
16. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
IMPLEMENTATION
17. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
IMPLEMENTATION
OVERVIEW
• Early Win Goals
• First Step Actions
• Catalyst Projects
• Funding Opportunities
• Implementation Matrix
• Estimated Timelines
• Estimated Costs
• Priority Levels
• Potential Partners
18. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
EARLY WIN GOALS
EARLY WIN INFRASTRUCTURE GOALS EARLY WIN POLICY GOALS
Goal A: Complete Sidewalk Inventory Goal J: Safety Review Committee & Policing
Goal E: Neighborhood Greenways & Traffic Calming Goal K: Safe Routes to School Program
Goal F: Temporary Installations Goal L: Complete and Green Streets Policy
Goal M: Zoning and Codified Ordinances
Goal N: Project Coordination & Collaboration
HIGH PRIORITY & LOW-COSTS
19. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
Near-term actions that build
momentum toward longer-term
goals
EXAMPLE
Goal C: Buffered Bike Lanes &
Two-Way Cycle Tracks
FIRST STEP: Evaluate identified
roads for preferred on-road
facility type
FIRST STEP ACTIONS
20. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
FIRST STEP ACTIONS | IMPLEMENTATION
21. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CATALYST PROJECTS
Infrastructure enhancements that have a significant impact on pedestrian and bicycle safety—regardless
of cost or timeline
22. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CATALYST PROJECTS
Infrastructure enhancements that have a significant impact on pedestrian and bicycle safety—regardless
of cost or timeline
23. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CATALYST PROJECTS
Infrastructure enhancements that have a significant impact on pedestrian and bicycle safety—regardless
of cost or timeline
24. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CATALYST PROJECTS
Infrastructure enhancements that have a significant impact on pedestrian and bicycle safety—regardless
of cost or timeline
25. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
CATALYST PROJECTS
Infrastructure enhancements that have a significant impact on pedestrian and bicycle safety—regardless
of cost or timeline
26. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
SAMPLE IMPLEMENTATION MATRIX
27. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
SAMPLE IMPLEMENTATION MATRIX
Priority Level
 Highest Priority
 Medium Priority
 Lowest Priority
28. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
SAMPLE IMPLEMENTATION MATRIX
Estimated Timelines
Ongoing
6 months
1 Year
1-2 Years
3-5 Years
29. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
SAMPLE IMPLEMENTATION MATRIX
Estimated Cost
$$$ High Cost (Over $500,000)
$$ Medium Cost ($100,000-$500,000)
$ Low Cost (Up to $100,000)
30. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
SAMPLE IMPLEMENTATION MATRIX
Estimated Cost
$$$ High Cost (Over $500,000)
$$ Medium Cost ($100,000-$500,000)
$ Low Cost (Up to $100,000)
31. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
FUNDING OPPORTUNITIES
RELEVENT SECTIONS IN THE FUNDING &
RESOURCES FOR COMMUNITIES GUIDEBOOK
Natural Environment: Recreation pg. 55
Natural Environment: Trees pg. 55
Transportation: Equity & Mobility pg. 60
Transportation: Safety pg. 64
Transportation: Various Transportation Funding pg. 66
Water Resources: Shorelines & Streams pg. 70
Water Resources: Stormwater Management pg. 72
32. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
POTENTIAL PARTNERS
33. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
QUESTIONS & DISCUSSION
34. CITY OF EUCLID | PEDESTRIAN & BICYCLE SAFETY ACTION PLAN
THANK YOU