際際滷

際際滷Share a Scribd company logo
Implementing a fully-coupled thermo-hydro-mechanical model:
lessons learned from the application to radioactive waste storage
Adrien Haxaire 1), Philip J. Vardon 2), Vahid Galavi 3), Ronald B.J. Brinkgreve 1,2)
1) Plaxis, Delft, The Netherlands
2) Department of Geoscience and Engineering, Delft University of Technology, Delft, The Netherlands
3) Deltares, Delft, The Netherlands
Summary
The fully-coupled thermo-hydro-mechanical
(THM) model presented in Haxaire et al. (2013)
has been implemented in the finite element code
PLAXIS 2D. An application to radioactive waste
storage is conducted and analysed. It is inspired
by the OPERA research programme, in the
Netherlands (Verhoef and Schr旦der, 2011). The
formulation and the implementation is stable and
provides qualitative results in accordance with
expectation.
Case study
The case study is inspired by Arnold et al.
(2015). Figure 1 presents the geometry, mesh
and the boundary conditions and Table 1 the
parameters used. The analysis is plane strain. It
consists of a set of two 1.6 m radius galleries
excavated at a 500 m depth in a Boom clay
layer, with a spacing of 50 m (centre to centre).
The mesh contains 2298 fifteen-noded
elements, with 18729 nodes. The boundary
conditions are applied to both galleries. A heat
flux of 11 W/m2 is applied to both tunnel outer
circumferences to model the heat emitted by the
radioactive waste canisters once in place.
First phase: excavation
The largest total displacement on Figure 2.a. is
12.91 cm, or 8% of the radius of the gallery. This
value was confirmed by a three dimensional
calculation performed using PLAXIS 3D. Non
zero values of the displacement field extend to
21 m below the galleries. The total deviatoric
strain on Figure 2.b. exhibits the behaviour
observed for the total displacement field: high
displacements at the edge of the gallery,
combined with an extended shear zone below
the gallery. The maximum value obtained, 8.6 %,
is close to the total displacement ratio,
confirming thus that the displacements are
mainly caused by shearing.
Second phase: heating
Figure 3 presents the temperature and the heat
flux in the model at steady state, reached after
approximatively 1.4.1010 seconds, i.e. 444 years.
The maximum temperature, obtained at the
boundary of the gallery, at point A, reaches 360
K. Figure 3 (a) exhibits the interaction between
the two canisters. The temperature at the middle
of the model, at point E (25.08 m, 51.30 m),
reaches 328.4 K. Figure 3 (b) shows that the
heat flux, as expected, is null at the centre of the
model, confirming the interaction between the
two canisters at steady state.
Figure 4 presents the evolution of the pore
pressure close to the Boom clay-canister
interface, after the start of the heating. We can
see on Figure 4 (a) that, as expected, the
heating increases the pore pressure: as the
permeability is low, the water expands but
cannot flow. The pore pressure initially increases
rapidly due to the rapid temperature increase
and then is subsequently controlled by the
recharge effects of closing and backfilling the
tunnel, returning to hydrostatic conditions.
Figure 4 (b) confirms this result over the three
points A, C and E.
Conclusion
The current implementation of PLAXIS 2D's
fully-coupled THM model has been shown to be
able to simulate the THM effects of a radioactive
waste repository. It can simulate a number of
expected phenomena, leading to confidence in
its ability to be used in further studies. From this
positive experience, more refined studies can be
conducted, such as considering the excavation
damaged zone, or the impact of vapour fluxes
on the THM processes, as well as full validations
based on in situ experiments.
References
Arnold, P., Vardon, P.J., Hicks, M.A., Fokkens, J.
and Fokker, P.A. 2015. A numerical and
reliability-based investigation into the technical
feasibility of a Dutch radioactive waste
repository in Boom Clay. OPERA-PU-TUD311,
COVRA, The Netherlands.
Haxaire, A., Galavi, V. and Brinkgreve, R.B.J.
2013. Definition and implementation of a fully
coupled THM model, Rock Mechanics for
Resources, Energy and Environment -
Kwaniewski & yd甜ba (eds), Taylor & Francis
Group, London, ISBN 978-1-138-00080-3.
Verhoef, E. and Schroder, T. 2011. Research
Plan. OPERA-PG-COV004, COVRA, The
Netherlands.
Figure 1. Mesh and boundary conditions of the case study.
Figure 2. Excavation: total displacements (a) and total
deviatoric strain (b).
Table 1. THM parameters used for the case study.
Mechanical Unit Value Hydraulic Unit Value
E50
ref [kN/m2] 145300 Sres [-] 0.01629
Eoed
ref [kN/m2] 145300 Ssat [-] 1
Eur
ref [kN/m2] 435800 gn [-] 1.103
Power (m) [-] 0.7 ga [1/m] 2.650
einit [-] 0.166 gl [-] 2.5
cref [kN/m2] 300 kx [m/s] 10-12
 [属] 12.5 ky [m/s] 10-12
率 [属] 0 Thermal Unit Value
僚ur [-] 0.3 cs [J/kg.K] 1400
pref [kN/m2] 100 了s [W/m.K] 1.4
K0
nc [-] 0.7836 s [kg/m3] 2000
Model Hardening Soil 留s [-] 5. 10-5
Figure 3. Temperature distribution (a) and heat flux (b) at steady
state.
Figure 4. Pore pressure after 282 days of heating (a) and from
the left canister to the centre of the model until 95 years (b).

More Related Content

Eurock2015-poster

  • 1. Implementing a fully-coupled thermo-hydro-mechanical model: lessons learned from the application to radioactive waste storage Adrien Haxaire 1), Philip J. Vardon 2), Vahid Galavi 3), Ronald B.J. Brinkgreve 1,2) 1) Plaxis, Delft, The Netherlands 2) Department of Geoscience and Engineering, Delft University of Technology, Delft, The Netherlands 3) Deltares, Delft, The Netherlands Summary The fully-coupled thermo-hydro-mechanical (THM) model presented in Haxaire et al. (2013) has been implemented in the finite element code PLAXIS 2D. An application to radioactive waste storage is conducted and analysed. It is inspired by the OPERA research programme, in the Netherlands (Verhoef and Schr旦der, 2011). The formulation and the implementation is stable and provides qualitative results in accordance with expectation. Case study The case study is inspired by Arnold et al. (2015). Figure 1 presents the geometry, mesh and the boundary conditions and Table 1 the parameters used. The analysis is plane strain. It consists of a set of two 1.6 m radius galleries excavated at a 500 m depth in a Boom clay layer, with a spacing of 50 m (centre to centre). The mesh contains 2298 fifteen-noded elements, with 18729 nodes. The boundary conditions are applied to both galleries. A heat flux of 11 W/m2 is applied to both tunnel outer circumferences to model the heat emitted by the radioactive waste canisters once in place. First phase: excavation The largest total displacement on Figure 2.a. is 12.91 cm, or 8% of the radius of the gallery. This value was confirmed by a three dimensional calculation performed using PLAXIS 3D. Non zero values of the displacement field extend to 21 m below the galleries. The total deviatoric strain on Figure 2.b. exhibits the behaviour observed for the total displacement field: high displacements at the edge of the gallery, combined with an extended shear zone below the gallery. The maximum value obtained, 8.6 %, is close to the total displacement ratio, confirming thus that the displacements are mainly caused by shearing. Second phase: heating Figure 3 presents the temperature and the heat flux in the model at steady state, reached after approximatively 1.4.1010 seconds, i.e. 444 years. The maximum temperature, obtained at the boundary of the gallery, at point A, reaches 360 K. Figure 3 (a) exhibits the interaction between the two canisters. The temperature at the middle of the model, at point E (25.08 m, 51.30 m), reaches 328.4 K. Figure 3 (b) shows that the heat flux, as expected, is null at the centre of the model, confirming the interaction between the two canisters at steady state. Figure 4 presents the evolution of the pore pressure close to the Boom clay-canister interface, after the start of the heating. We can see on Figure 4 (a) that, as expected, the heating increases the pore pressure: as the permeability is low, the water expands but cannot flow. The pore pressure initially increases rapidly due to the rapid temperature increase and then is subsequently controlled by the recharge effects of closing and backfilling the tunnel, returning to hydrostatic conditions. Figure 4 (b) confirms this result over the three points A, C and E. Conclusion The current implementation of PLAXIS 2D's fully-coupled THM model has been shown to be able to simulate the THM effects of a radioactive waste repository. It can simulate a number of expected phenomena, leading to confidence in its ability to be used in further studies. From this positive experience, more refined studies can be conducted, such as considering the excavation damaged zone, or the impact of vapour fluxes on the THM processes, as well as full validations based on in situ experiments. References Arnold, P., Vardon, P.J., Hicks, M.A., Fokkens, J. and Fokker, P.A. 2015. A numerical and reliability-based investigation into the technical feasibility of a Dutch radioactive waste repository in Boom Clay. OPERA-PU-TUD311, COVRA, The Netherlands. Haxaire, A., Galavi, V. and Brinkgreve, R.B.J. 2013. Definition and implementation of a fully coupled THM model, Rock Mechanics for Resources, Energy and Environment - Kwaniewski & yd甜ba (eds), Taylor & Francis Group, London, ISBN 978-1-138-00080-3. Verhoef, E. and Schroder, T. 2011. Research Plan. OPERA-PG-COV004, COVRA, The Netherlands. Figure 1. Mesh and boundary conditions of the case study. Figure 2. Excavation: total displacements (a) and total deviatoric strain (b). Table 1. THM parameters used for the case study. Mechanical Unit Value Hydraulic Unit Value E50 ref [kN/m2] 145300 Sres [-] 0.01629 Eoed ref [kN/m2] 145300 Ssat [-] 1 Eur ref [kN/m2] 435800 gn [-] 1.103 Power (m) [-] 0.7 ga [1/m] 2.650 einit [-] 0.166 gl [-] 2.5 cref [kN/m2] 300 kx [m/s] 10-12 [属] 12.5 ky [m/s] 10-12 率 [属] 0 Thermal Unit Value 僚ur [-] 0.3 cs [J/kg.K] 1400 pref [kN/m2] 100 了s [W/m.K] 1.4 K0 nc [-] 0.7836 s [kg/m3] 2000 Model Hardening Soil 留s [-] 5. 10-5 Figure 3. Temperature distribution (a) and heat flux (b) at steady state. Figure 4. Pore pressure after 282 days of heating (a) and from the left canister to the centre of the model until 95 years (b).