I was asked to prepare a brief presentation on th Flagstaff project I helped to build at Empire Pass; Park City, UT. I presented this to the entire company during one of our regular monthly meetings.
10. Paintbrush 11 Paintbrush 10 Paintbrush 8 & 9 Larkspur 21-32 Flagstaff EWP History at Empire Pass
11. Flagstaff Project Specs: Org Contracted Amount: 47 Mil ; Revised Contracted Amount Due to COs: 52 Mil 120,000 SF, 6 Story, 1 遜 Parking levels 37 Condo Units Roughly 2200 SF each, 3 Loft Units, 5000 SF Common Area Structural Steel / S.O.D. / Metal Framing Projected Completion Fall 2009 Superior Subs: Wasatch Electric!! Watch Out For: Tech Steel, Encon United
30. Project Challenges Site Restrictions: No room for storage Only one site access Deliveries & driving on Empire Club Drive Dirt cant leave the mountain [Talisker Develop.] Working through ski season (safety / complaining)
40. Project Challenges Owner Issues: Highest Level of Finish for EWP and Okland ($1700/sf) Owner Changes and Plan Corrections
41. Project Challenges Owner Changes and Plan Corrections: 350 PCOs 150 CORs (worth 5 Million!) 80 ASIs 350 RFIs
42. Project Challenges Owner Issues: Highest Level of Finish for EWP and Okland ($1700/sf) Buyer Changes and Sales Driven Building Architect, Structural Engineer, Int Designer Owner Changes and Plan Corrections