  Hanford Waste Treatment Plant completes fifth concrete
            wall elevation for largest facility
MEDIA CONTACTS:
Suzanne Heaston, Bechtel National, Inc., (509) 371-2329
Carrie Meyer, Department of Energy, (509) 372-0810

   Richland, Wash. -- Last week, crews at the Hanford Waste Treatment Plant, also
known as the Vit Plant, finished installing the Pretreatment Facilitys fifth elevation of
concrete walls. The fifth elevation reaches 96 feet at the top.
   To place the final walls, crews used a specialized concrete pumping truck with an
extendable arm that reaches approximately 200 feet vertically or horizontally.
   The Pretreatment Facility, the largest of the Vit Plants four major nuclear facilities,
comprises six elevated concrete sections and more than 113,000 cubic yards of concrete.
Work on the sixth and final elevation is already in progress, and only four small wall
sections remain before all concrete walls in the Pretreatment Facility are complete.
   When complete, the buildings walls will reach a total height of 109 feet. Steel
columns and roof trusses will extend beyond the walls to an overall height of 120 feet.




(Photo 1 of 3)
                                        (continued)
(Photo 2 of 3)




(Photo 3 of 3)

   Bechtel National, Inc. is designing and building the worlds largest radioactive waste
treatment plant for the U.S. Department of Energy at the Hanford Site in southeastern
Washington state. The $12.2 billion Waste Treatment and Immobilization Plant, also
known as the Vit Plant, will immobilize the radioactive liquid waste currently stored in
177 underground tanks using a process called vitrification.

                                       (continued)
Vitrification involves blending the waste with molten glass and heating it to high
temperatures. The mixture is then poured into stainless steel canisters. In this glass form,
the waste is stable and impervious to the environment, and its radioactivity will dissipate
over hundreds to thousands of years.
   The Vit Plant will cover 65 acres with four nuclear facilities -- Pretreatment,
Low-Activity Waste Vitrification, High-Level Waste Vitrification and Analytical
Laboratory -- as well as operations and maintenance buildings, utilities and office space.
   Construction of the Vit Plant began in 2001 and is more than 60 percent complete.
The project is scheduled to complete construction in 2016; will reach commissioning in
2019 and achieve full operations in 2022.

NR11-20                                       ###

More Related Content

Viewers also liked (7)

PDF
ORP 2011 Cleanup Caucus Presentation
DOE Office of River Protection
PPTX
Memory management for i os dev
Anton Krokhmalyuk
PPT
Best presentation
Chan Choi
PDF
IHS McCloskey Nuclear business
DOE Office of River Protection
PDF
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
DOE Office of River Protection
PPT
Vamos contar
Marilene Terra
PDF
Navicat
Orlando Gavilanez
ORP 2011 Cleanup Caucus Presentation
DOE Office of River Protection
Memory management for i os dev
Anton Krokhmalyuk
Best presentation
Chan Choi
IHS McCloskey Nuclear business
DOE Office of River Protection
Hanford Waste Treatment Plant receives and sets key air-filtration equipment ...
DOE Office of River Protection
Vamos contar
Marilene Terra

Similar to Hanford Waste Treatment Plant completes fifth concrete wall elevation for largest facility (10)

PDF
Hanford Waste Treatment Plant completes concrete design for largest facility
DOE Office of River Protection
PDF
Waste Treatment & Immobilization Plant Project
haysqaammudlwp
PDF
Hanford Waste Treatment Plant receives national safety award for excellent he...
DOE Office of River Protection
PPTX
Radioactive waste management
Enoch Iraianbu
PDF
Hanford Waste Treatment Plant Construction Site Receives Department of Energy...
DOE Office of River Protection
PPTX
Vitrification and it's use in treating hazardous waste
Tianna Drew
PPTX
Week 11_CH 418 Nuclear Waste 2025.pptx.new
MuhammadUsmanAsghar4
PPTX
Week 11_CH 418 Nuclear Waste 2025.pptx.new
MuhammadUsmanAsghar4
PDF
InsideICP_121411_calcine
Beau Johnston, P.E.
PPTX
Radioactive wastes and management
Gopika Beena Chandran
Hanford Waste Treatment Plant completes concrete design for largest facility
DOE Office of River Protection
Waste Treatment & Immobilization Plant Project
haysqaammudlwp
Hanford Waste Treatment Plant receives national safety award for excellent he...
DOE Office of River Protection
Radioactive waste management
Enoch Iraianbu
Hanford Waste Treatment Plant Construction Site Receives Department of Energy...
DOE Office of River Protection
Vitrification and it's use in treating hazardous waste
Tianna Drew
Week 11_CH 418 Nuclear Waste 2025.pptx.new
MuhammadUsmanAsghar4
Week 11_CH 418 Nuclear Waste 2025.pptx.new
MuhammadUsmanAsghar4
InsideICP_121411_calcine
Beau Johnston, P.E.
Radioactive wastes and management
Gopika Beena Chandran
Ad

Recently uploaded (20)

PDF
2025_06_18 - OpenMetadata Community Meeting.pdf
OpenMetadata
PPTX
叶Wondershare Filmora Crack 14.0.7 + Key Download 2025
sebastian aliya
PDF
Darley - FIRST Copenhagen Lightning Talk (2025-06-26) Epochalypse 2038 - Time...
treyka
PDF
Automating the Geo-Referencing of Historic Aerial Photography in Flanders
Safe Software
PDF
Why aren't you using FME Flow's CPU Time?
Safe Software
PPTX
Simplifica la seguridad en la nube y la detecci坦n de amenazas con FortiCNAPP
Cristian Garcia G.
PPTX
Paycifi - Programmable Trust_Breakfast_PPTXT
FinTech Belgium
DOCX
Daily Lesson Log MATATAG ICT TEchnology 8
LOIDAALMAZAN3
PDF
EIS-Webinar-Engineering-Retail-Infrastructure-06-16-2025.pdf
Earley Information Science
PDF
Unlocking FME Flows Potential: Architecture Design for Modern Enterprises
Safe Software
PPTX
Practical Applications of AI in Local Government
OnBoard
PDF
Cracking the Code - Unveiling Synergies Between Open Source Security and AI.pdf
Priyanka Aash
PPTX
MARTSIA: A Tool for Confidential Data Exchange via Public Blockchain - Poster...
Michele Kryston
PDF
5 Things to Consider When Deploying AI in Your Enterprise
Safe Software
PDF
Optimizing the trajectory of a wheel loader working in short loading cycles
Reno Filla
PDF
Open Source Milvus Vector Database v 2.6
Zilliz
PDF
Quantum AI Discoveries: Fractal Patterns Consciousness and Cyclical Universes
Saikat Basu
PPSX
Usergroup - OutSystems Architecture.ppsx
Kurt Vandevelde
PDF
UiPath Agentic AI ile Ak脹ll脹 Otomasyonun Yeni a脹
UiPathCommunity
PDF
Salesforce Summer '25 Release Frenchgathering.pptx.pdf
yosra Saidani
2025_06_18 - OpenMetadata Community Meeting.pdf
OpenMetadata
叶Wondershare Filmora Crack 14.0.7 + Key Download 2025
sebastian aliya
Darley - FIRST Copenhagen Lightning Talk (2025-06-26) Epochalypse 2038 - Time...
treyka
Automating the Geo-Referencing of Historic Aerial Photography in Flanders
Safe Software
Why aren't you using FME Flow's CPU Time?
Safe Software
Simplifica la seguridad en la nube y la detecci坦n de amenazas con FortiCNAPP
Cristian Garcia G.
Paycifi - Programmable Trust_Breakfast_PPTXT
FinTech Belgium
Daily Lesson Log MATATAG ICT TEchnology 8
LOIDAALMAZAN3
EIS-Webinar-Engineering-Retail-Infrastructure-06-16-2025.pdf
Earley Information Science
Unlocking FME Flows Potential: Architecture Design for Modern Enterprises
Safe Software
Practical Applications of AI in Local Government
OnBoard
Cracking the Code - Unveiling Synergies Between Open Source Security and AI.pdf
Priyanka Aash
MARTSIA: A Tool for Confidential Data Exchange via Public Blockchain - Poster...
Michele Kryston
5 Things to Consider When Deploying AI in Your Enterprise
Safe Software
Optimizing the trajectory of a wheel loader working in short loading cycles
Reno Filla
Open Source Milvus Vector Database v 2.6
Zilliz
Quantum AI Discoveries: Fractal Patterns Consciousness and Cyclical Universes
Saikat Basu
Usergroup - OutSystems Architecture.ppsx
Kurt Vandevelde
UiPath Agentic AI ile Ak脹ll脹 Otomasyonun Yeni a脹
UiPathCommunity
Salesforce Summer '25 Release Frenchgathering.pptx.pdf
yosra Saidani
Ad

Hanford Waste Treatment Plant completes fifth concrete wall elevation for largest facility

  • 1. November 16, 2011 Hanford Waste Treatment Plant completes fifth concrete wall elevation for largest facility MEDIA CONTACTS: Suzanne Heaston, Bechtel National, Inc., (509) 371-2329 Carrie Meyer, Department of Energy, (509) 372-0810 Richland, Wash. -- Last week, crews at the Hanford Waste Treatment Plant, also known as the Vit Plant, finished installing the Pretreatment Facilitys fifth elevation of concrete walls. The fifth elevation reaches 96 feet at the top. To place the final walls, crews used a specialized concrete pumping truck with an extendable arm that reaches approximately 200 feet vertically or horizontally. The Pretreatment Facility, the largest of the Vit Plants four major nuclear facilities, comprises six elevated concrete sections and more than 113,000 cubic yards of concrete. Work on the sixth and final elevation is already in progress, and only four small wall sections remain before all concrete walls in the Pretreatment Facility are complete. When complete, the buildings walls will reach a total height of 109 feet. Steel columns and roof trusses will extend beyond the walls to an overall height of 120 feet. (Photo 1 of 3) (continued)
  • 2. (Photo 2 of 3) (Photo 3 of 3) Bechtel National, Inc. is designing and building the worlds largest radioactive waste treatment plant for the U.S. Department of Energy at the Hanford Site in southeastern Washington state. The $12.2 billion Waste Treatment and Immobilization Plant, also known as the Vit Plant, will immobilize the radioactive liquid waste currently stored in 177 underground tanks using a process called vitrification. (continued)
  • 3. Vitrification involves blending the waste with molten glass and heating it to high temperatures. The mixture is then poured into stainless steel canisters. In this glass form, the waste is stable and impervious to the environment, and its radioactivity will dissipate over hundreds to thousands of years. The Vit Plant will cover 65 acres with four nuclear facilities -- Pretreatment, Low-Activity Waste Vitrification, High-Level Waste Vitrification and Analytical Laboratory -- as well as operations and maintenance buildings, utilities and office space. Construction of the Vit Plant began in 2001 and is more than 60 percent complete. The project is scheduled to complete construction in 2016; will reach commissioning in 2019 and achieve full operations in 2022. NR11-20 ###