Former NAS Moffett Field

Hangar 1 Removal Action Update
         Bryce Bartelma, PG
      Salient Federal Solutions
             supporting
       Navy BRAC PMO West

        November 29, 2012
           RAB Meeting




                 1
Project Objective




• Control release of PCBs from Hangar 1 in accordance
  with EE/CA (July 2008) and Action Memorandum
  (December 2008)
    Demolition of interior structures
    Removal of contaminated siding
    Application of weather-resistant coating to steel frame




                             2
Final Material Removed
     July 19, 2012




          3
Final Scaffolding Removed
     October 18, 2012




           4
Remaining Removal Action Tasks



                  • Mezzanine prep and coat
                  • Final coating touch ups
                  • Soil excavations and
                    confirmation sampling
                  • Concrete slab washing and
                    confirmation sampling
                  • Perimeter Storm Drain
                    clean-out
                  • Demobilize


              5
Hangar 1 Interactive CD


http://historicproperties.arc.nasa.gov




                  6
Hangar 1 CERCLA Process




EE/CA
                    Focused
 and     Removal                     Proposed   Record of   Land Use
                   Feasibility
Action    Action                       Plan     Decision    Controls
                     Study
Memo




                                 7
Schedule


• NTCRA Demobilization
  December 2012
• Draft After Action
  Completion Report
  January 2013
• Focused Feasibility Study
  April 2013
• Proposed Plan
  June 2013
• Public Meeting (tentative)
  July 2013

                               8
Questions?




                 Point of Contact:

                   Scott Anderson
                BRAC Environmental
                      Coordinator
                   (619) 532-0938
             scott.d.anderson@navy.mil




    9

More Related Content

Hangar 1 rab update nov 29 2012

  • 1. Former NAS Moffett Field Hangar 1 Removal Action Update Bryce Bartelma, PG Salient Federal Solutions supporting Navy BRAC PMO West November 29, 2012 RAB Meeting 1
  • 2. Project Objective • Control release of PCBs from Hangar 1 in accordance with EE/CA (July 2008) and Action Memorandum (December 2008)  Demolition of interior structures  Removal of contaminated siding  Application of weather-resistant coating to steel frame 2
  • 3. Final Material Removed July 19, 2012 3
  • 4. Final Scaffolding Removed October 18, 2012 4
  • 5. Remaining Removal Action Tasks • Mezzanine prep and coat • Final coating touch ups • Soil excavations and confirmation sampling • Concrete slab washing and confirmation sampling • Perimeter Storm Drain clean-out • Demobilize 5
  • 6. Hangar 1 Interactive CD http://historicproperties.arc.nasa.gov 6
  • 7. Hangar 1 CERCLA Process EE/CA Focused and Removal Proposed Record of Land Use Feasibility Action Action Plan Decision Controls Study Memo 7
  • 8. Schedule • NTCRA Demobilization December 2012 • Draft After Action Completion Report January 2013 • Focused Feasibility Study April 2013 • Proposed Plan June 2013 • Public Meeting (tentative) July 2013 8
  • 9. Questions? Point of Contact: Scott Anderson BRAC Environmental Coordinator (619) 532-0938 scott.d.anderson@navy.mil 9