際際滷

際際滷Share a Scribd company logo
@Rob_Garvey
#lcecGTP
Rob Garvey
University of Westminster
12th May 2015
@Rob_Garvey
#lcecGTP
Work 1st 20yrs
Academic work
. Interests
Government Construction Strategy 2May 2015
Education
BSC (Hons)
Quantity
surveying
MSc
Construction
Economics &
Management
Professional
Doctorate
@Rob_Garvey
#lcecGTP
Work 1st 20yrs
Academic work
. Interests
Government Construction Strategy 3May 2015
Education
BSC (Hons)
Quantity
surveying
MSc
Construction
Economics &
Management
Professional
Doctorate
@Rob_Garvey
#lcecGTP
Objectives
Context
Progress
So What 
 next?
Government Construction StrategyMay 2015 4
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 5
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 6
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 7
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 8
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 9
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 10
@Rob_Garvey
#lcecGTP
Objectives
Context
Progress
So What 
 next?
Government Construction StrategyMay 2015 11
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 12
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 13
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 14
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 15
72
447
840
476
2400
3500
0
500
1000
1500
2000
2500
3000
3500
4000
2011/12 2012/13 2013/14 2014/15
Savings / Expenditure
Saving Expenditure
15.6%
13.1%
19.6%
?
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 16
Department Actual Cost reduction
13/14
BIS 贈58m 10%
DCLG 贈42m 13.3%
DEFRA 贈20m 14.2%
DfE 贈127m 31.4%
DfT / HA-MP 贈379m 27.7%
DfT / NDD 贈119m 15%
DoH 贈60m 12.9%
MoD 贈8m 9.3%
MoJ 贈25m 18.4%
@Rob_Garvey
#lcecGTP
1720
100
40
0
200
400
600
800
1000
1200
1400
1600
1800
2000
Total Government spend Total Construction Output Public Sector Construction
output
Expenditure
Expenditure
Government Construction StrategyMay 2015 17
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 18http://www.clipartpanda.com/categories/pipeline-20clipart
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 19
@Rob_Garvey
#lcecGTP
Objectives
Context
Progress
So What 
 next?
Government Construction StrategyMay 2015 20
@Rob_Garvey
#lcecGTP
21
'Never Waste A Good Crisis- A Challenge To The UK Construction Industry,
Constructing Excellence (2009)
(available at www.constructingexcellence.org.uk)
May 2015 Government Construction Strategy
@Rob_Garvey
#lcecGTP
22May 2015 Government Construction Strategy
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 23
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 24
May11
Oct10 Dec10
March13
July13
@Rob_Garvey
#lcecGTP
Objectives
Context
Progress
So What 
 next?
Government Construction StrategyMay 2015 25
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 26
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 27
https://www.gov.uk/government/organisations/cabinet-
office/series/government-construction
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 28
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 29
@Rob_Garvey
#lcecGTP
Intelligent client
Procurement
routes
Effectiveness
of
Frameworks
Cross
Government
collaboration
in
procurement
Government Construction StrategyMay 2015 30
Intelligent client
Procurement
models
Effectiveness
of
Frameworks
Cross
Government
collaboration
in
procurement
@Rob_Garvey
#lcecGTP
Cost-led
Two-stage open
book
Integrated project
insurance
Government Construction StrategyMay 2015 31
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 32
@Rob_Garvey
#lcecGTP
Cost targets and savings
Reduced supply
chain costs
Improved
client brief
Simpler
pricing
Greater
visibility of
workload
Procurement
Lower bid
costs
Due to
simpler
procurement
process
Commercial
Government Construction StrategyMay 2015 33
14%
16.5%
@Rob_Garvey
#lcecGTP
 Early engagement of
supply chain
 Standardised
specifications
 Improved briefing process
 Supply chain innovation
 Improved quality control
 Extended warranties
 Improved repairs and
maintenance
Government Construction StrategyMay 2015 34
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 35
"planned and confirmed
turnover, cash flow certainty,
direct communication
between all parties from client
to resident"
(Sovereign)
"The use of local resources
and labour from the areas we
are working in helps break the
barriers sometimes felt
between local residents and
the client or constructor"
(Dendale).
Increased confidence in
relationship between client
and supply chain enabling
higher levels of productivity
and performance
"Everyone is more than
happy to help each other
out to get the works
complete at the same
time, keeping the tenants
informed and happy"
(Masher Bros)
"The speed of which a
contract can go from AMP
inspection to starting on
site and completion is far
quicker than normal
procurement practices"
(Gunite)The supply chain said
@Rob_Garvey
#lcecGTP
 Intelligent client
 Hard work
 All focused on delivery
 Engaged supply chain
 Early contractor involvement
 Confidence = reduced risk
 Significant benefits
 Cultural Change
Government Construction StrategyMay 2015 36
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 37
@Rob_Garvey
#lcecGTP
Intelligent client
Procurement
routes
Effectiveness
of
Frameworks
Cross
Government
collaboration
in
procurement
Government Construction StrategyMay 2015 38
@Rob_Garvey
#lcecGTP
Objectives
Context
Progress
So What 
 next?
Government Construction StrategyMay 2015 39
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 40
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 41
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 42
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 43
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 44
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 45
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 46
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 47
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 48
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 49
623Mt
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 50
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 51
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 52
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 53
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 54
@Rob_Garvey
#lcecGTP
Objectives
Context
Progress
So What 
 next?
Government Construction StrategyMay 2015 55
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 56
@Rob_Garvey
#lcecGTP
Government Construction StrategyMay 2015 57
@Rob_Garvey
uk.linkedin.com/in/garveyrob
r.garvey@westminster.ac.uk

More Related Content

Has the Government Construction Strategy Delivered?

Editor's Notes

  1. 13 themes mention Co-ordination and Leadership Client skills New procurement models BIM
  2. There have been a plethora of industry wide reports, numerous government sponsored and others by organisations such as Building Property Federation. Fundamentally the reports have highlighted similar problem areas namely poor performance associated with building projects resulting in time delays, cost overruns, poor quality and poor H&S. For more detail on all these reports up until Rethinking Construction, Sir John Egans report in 1994 look at David Langford and Mike Murrays book
  3. Leadership central focus across all government departments
  4. Key points despite Construction Matters desire to have a focal point for construction it could be argued this has not be
  5. Not a project, but a programme Year March13 to April14 Interim and final case studies
  6. Improved client / resident satisfaction Improved predictability of time & cost Improved quality Improved sustainability Improved leaseholder relations The cost savings have been achieved through two principle cost reductions through firstly procurement and then through process improvement using the SCMG Starting on the right The procurement savings were achieved by lower bid costs. The SCMG has enabled both clients to simplify their procurement process and lower not only their own bid costs, but also those of the tenderers. Secondly, there was a commercial advantage gained through the procurement process. These are attractive contracts worth approximately 贈75m pa. But that bidders already had a good appreciation of the SCMG and were keen to work on it. Secondly the SCMG processes enabled the supply chain costs to al be reduced. With a clearer understanding of what the client requires, better scopes and specifications have been generated and standardised, reducing the time to start works as well as giving confidence to the project teams on what is expected of them. Greater standardisation of specs and scopes have enabled a simpler method of price determination which again reduces the time involved in agreeing both the anticipated costs as well as the final costs. There are minimal variations I touch on this again in a minute. But another key cost reduction has been the transparency of workload, which takes out risk for the supply chain as they can have greater confidence in deploying dedicated resources to the projects So what have we reported well we have audited savings of approximately 31%; with savings in procurement at 16.5% and process improvement savings at 14%
  7. So Ive touch on some of these already but if I focus on a couple Firstly, supply chain innovation the tier 2 suppliers have a voice and have greater confidence in the process that they are prepared to engage and consider alternative solutions. Whatever the innovations, introducing new materials such as upgrading windows at no extra cost it is the process that encourages suppliers to contribute Another example of this is the extended warranties. Actually whilst they may have extended the warranties, the real benefit has been in effective management of the warranties. Both clients now have a much improved process that if damage occurs to a property, before a repairs and maintenance gang attend the warranties are checked. So if a window is damaged, the original supplier, who is more than happy to fulfil the warranty obligation is given the opportunity to attend the repair. This means the authority has saved money in not occurring the cost in the repairs and maintenance division, but also benefitted from activating the warranty. Moreover the supplier can understand and record what the problem is and potentially improve their own products Another example is the roofs this fits in quality control as well. But dialogue with the roofing companies led to the introduction of an inspection after one year because if a roof is going to fail, statistics say it will be within the first year of two. Any issues can be immediately attended to. We can see that there is now a benefit of not incurring additional costs of repairs to properties down the line, but these cant be accounted for!
  8. Ill leave you to read the quotes from the supply chain, but Im really just reinforcing what Ive already said Integrated working has resulted in increased confidence in the relationship between the clients and the supply chain which has led to improved productivity and performance It really is a feel good story and one that I feel should be shouted from the rooftops. Collaboration and integrated working achieves so much more than just cost savings
  9. Why will other clients adopt these new methods what are the challenges going forward? Relate to Industrial Strategy?
  10. s National Change Agent Davis Langdon will oversee the 贈35m Efficency Challenge Fund, which will be used to establish procurement consortia. It will be assisted by solicitor Trowers and Hamlins. Housing minister Keith Hill said: Collective procurement can deliver big benefits for social landlords and their tenants. As well as reducing costs, it can improve quality by developing long term relationships with suppliers. This appointment comes as part of the ODPMs response to the Gershon review that said money saved on procurement could be used to build more social housing. The 2003 Spending Review said that collective purchasing arrangements that focused on the whole supply chain and managed demand had significant potential to reduce costs and improve quality.
  11. Just to quickly summarise, weve looked at the GCS and its evident that the objective of cost reduction is being achieved, however its not clear whether this is just short term cost reduction that also supports whole life value? Its been recognised that a key driver has to be not only focus on cost, but also carbon reduction we cant wait! I suppose my final point is that the GCS is a good example of the leadership the strategy itself has called for. The challenge is whether the future leaders will continue and achieve the potential legacy the GCS was aspiring to achieve. IN that vain it will be interesting to see who will be the next Chief Construction Advisor. The other aspect of the strategy was to influence us to do things different. the implications of my poll indicate you are all prepared to do something, but the challenge is to influence that early majority. To that end, what is apparent to me, the emphasis on being better informed clients on the demand side will help, but on the supply side of the industry we have the capability to solve our problems and to do things differently, its up to us to align our capabilities to deliver the appropriate solutions.