This document provides a status report on construction projects from the House Construction Department 2 as of January 15, 2017. It summarizes that 16 units of the CHP 22 project are overdue and 6 units are delayed. For the SMCV 56 project, 10 units are overdue, 3 units are delayed, 4 units are on hold, and 39 units are on schedule. For the VSL 9 project, 7 units are overdue and 2 units are delayed due to a hold by the electric company. It also includes updates on special jobs, programs of work, material testing, and community association fees.
1 of 6
Download to read offline
More Related Content
Hcd2 pending works-jan 2017
1. Date: January 16, 2017
To: ENGR. WILLIAM A. CHUA
From: HOUSE CONSTRUCTION DEPARTMENT 2
Subject: HCD - 2 PENDING WORKS AS OF January 15, 2017
1. HOUSE CONSTRUCTION
PROJECT PARTICULAR
PE IN
CHARGE
REMARKS/STATUS
CHP 22 UNITS ON GOING RAE 16 UNITS OVERDUE; 6 UNITS DELAYED
SMCV 56 UNITS ON GOING MNB
10 UNITS OVERDUE, 3 UNITS DELAYED; 4 UNITS ON *HOLD, 39 UNITS
ON SCHEDULE
VSL 9 UNITS ON GOING AOC 7 UNITS OVERDUE; 2 UNITS DELAYED
*HOLD DUE TO MERALCO GUY WIRE
2. SPECIAL INSTRUCTION & SPECIAL JOB ORDER (SJO)
PROJECT PARTICULAR
PE IN
CHARGE
REMARKS/STATUS
TERRACOTTA ROOF SHEET SHORT ON SPAN LENGTH
SUBMITTED SJO FOR CORRECT SPAN; SUPPLIER HAS INSPECTED THE
ROOF REPORTED, AWAITING RECOMMENDATION REPORT.
DISMANTLING AND REINSTALLING HOMEOWNER GRILL WITH APPROVED SJO FOR IMPLEMENTATION.
SMCV BATCH 16 TAPPING TO RCDP FOR SUBMISSION
REPLENISHMENT OF 3" PVC PIPE USED FOR BATCH 9 REPAIR FOR SUBMISSION
SMCV BATCH 11 CONSTRUCTION OF PRIVATE POLE FOR BILLING
SMCV BATCH 16 CONSTRUCTION OF PRIVATE POLE FOR BILLING
VSL SUPPLEMENTAL CONSTRUCTION MATERIAL TO COMPLETE BATCH 27 AOC FOR SUBMISSION
3. PROGAM OF WORKS (POW)
PROJECT PARTICULAR
PE IN
CHARGE
REMARKS/STATUS
POW FOR PRICING CHV B9 L10 FOR SUBMISSION
POW FOR TURNOVER CHV B5 L13 FOR IMPLEMENTATION
POW FOR TURNOVER CHV B2 L2 FOR IMPLEMENTATION
POW FOR PRICING CHP B2 L2 FOR IMPLEMENTATION
POW FOR TURNOVER CHP B29 L10 FOR IMPLEMENTATION
POW FOR TURNOVER SMCV B9 L25 FOR BILLING
POW FOR TURNOVER SMCV B10 L49 FOR BILLING
POW FOR TURNOVER SMCV B2 L21 FOR IMPLEMENTATION
POW FOR TURNOVER SMCV B8 L22 FOR IMPLEMENTATION
POW FOR TURNOVER SMCV B9 L38 FOR IMPLEMENTATION
POW FOR TURNOVER SMCV B9 L46 FOR IMPLEMENTATION
POW FOR TURNOVER SMCV B9 L48 FOR IMPLEMENTATION
POW FOR TURNOVER SMCV B11 L17 FOR IMPLEMENTATION
DMCV POW FOR TURNOVER DMCV B3 L4C FOR IMPLEMENTATION
POW FOR PRICING NO4P B2A L10 FOR IMPLEMENTATION
POW FOR PRICING NO4P B2B L18 FOR IMPLEMENTATION
POW FOR TURNOVER NO4P B1A L 22CC ON GOING REPAIR C/O HELPER
POW FOR TURNOVER VSL B5 L4 FOR IMPLEMENTATION
POW FOR TURNOVER VSL B5 L7 FOR IMPLEMENTATION
POW FOR TURNOVER VSL B6 L10 FOR SUBMISSION
WNDRSE POW FOR TURNOVER B1 L10 FOR IMPLEMENTATION
4. OTHERS
PROJECT PARTICULAR
PE IN
CHARGE
REMARKS/STATUS
RCO: EXCAVATION OF ADOBE SOIL BATCH 76 FOR APPROVAL
RCO: EXCAVATION OF ADOBE SOIL BATCH 77 FOR APPROVAL
MATERIAL TESTING(DRSB, CHB & CYLINDER) RESULT BATCH 73 FOR TRANSMITTAL
MATERIAL TESTING(DRSB, CHB & CYLINDER) RESULT BATCH 74 FOR TRANSMITTAL
MATERIAL TESTING(DRSB, CHB & CYLINDER) RESULT BATCH 75 FOR TRANSMITTAL
MATERIAL TESTING(DRSB, CHB & CYLINDER) RESULT BATCH 76 FOR TRANSMITTAL
MATERIAL TESTING(DRSB, CHB & CYLINDER) BATCH 77 FOR TESTING
MATERIAL TESTING(DRSB, CHB & CYLINDER) BATCH 78 FOR TESTING
MATERIAL TESTING(DRSB, CHB & CYLINDER) BATCH 79 FOR TESTING
CRP CAF @ CRP B11B L6 ON GOING
DMCV CAF @ DMCV B22 L21 ON GOING
LOT ONLY NO4P 6B/9B FOR GRASSCUTTING
ACCOUNTABILITIES FOR PULLOUT FROM PROJECT
VSL CAF @ VSL B3 L7 WAITING FOR HOMEOWNER SCHEDULE
Note: See attached individual reports from HCD2 PEs.