際際滷

際際滷Share a Scribd company logo
By: Daniel Absalon, Miles Nowak, Andrew
Boyce, Omar Alwehaibi, & Andrew Boston
 Given:
 PV = $23,000
 EV = $20,000
 AC = $25,000
 BAC = $120,000
 Calculated:
 Cost Variance(CV) = $-5,000
 Schedule Variance(SV) = $-3,000
 Cost Performance Index(CPI) = 80%
 Schedule Performance Index(SPI) = 87%
 Because the CPI is 80% that means the project
is:
 currently behind schedule
 currently over-budget
 CPI = 80%
 BAC = $120,000
 Estimate At Completion(EAC) = BAC/CPI
 EAC = 120,000/.80 = 150,000
 The project is over-budget $30,000,
therefore the project is performing worse
then planned.
 Estimated Time to Complete = Original Time
Estimate/SPI
 Estimated Time = 1(year)/.87 = 1.149
 Estimated Time to Complete is 1.149 years.
 .149 years more then expected
Earned Value Chart
0
20
40
60
80
100
120
140
160
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Month
$(InGs)
Estimate at
Completion
(EAC)
Budget
At
Completion
(BAC)
Actual Cost
Earned Value
Planned
Value
1.E

More Related Content

Homework chapter 7

  • 1. By: Daniel Absalon, Miles Nowak, Andrew Boyce, Omar Alwehaibi, & Andrew Boston
  • 2. Given: PV = $23,000 EV = $20,000 AC = $25,000 BAC = $120,000 Calculated: Cost Variance(CV) = $-5,000 Schedule Variance(SV) = $-3,000 Cost Performance Index(CPI) = 80% Schedule Performance Index(SPI) = 87%
  • 3. Because the CPI is 80% that means the project is: currently behind schedule currently over-budget
  • 4. CPI = 80% BAC = $120,000 Estimate At Completion(EAC) = BAC/CPI EAC = 120,000/.80 = 150,000 The project is over-budget $30,000, therefore the project is performing worse then planned.
  • 5. Estimated Time to Complete = Original Time Estimate/SPI Estimated Time = 1(year)/.87 = 1.149 Estimated Time to Complete is 1.149 years. .149 years more then expected
  • 6. Earned Value Chart 0 20 40 60 80 100 120 140 160 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Month $(InGs) Estimate at Completion (EAC) Budget At Completion (BAC) Actual Cost Earned Value Planned Value 1.E