The Hyderabad Metro Rail Project team erected a station building in just 50 days, setting a new benchmark by installing 16 precast elements per day, much faster than the average of 4.56. The feat was accomplished under the guidance of the Project Director and other managers, with a team meticulously planning the execution with support from other departments.
1 of 1
Download to read offline
More Related Content
Hyderabad Metro Rail Project team sets benchmark-6657
1. Project News
Hyderabad Metro Rail Project
team sets benchmark.
Erects station building in 50
days!
The HMRL project witnessed an achievement
of complete erection of spines, PL beams and
wings in a record time of 50 days by erecting
16 precast elements per day as against the
average of 4.56.
The feat was accomplished under the guidance
of Mr. S Arunakumar, Project Director, Mr.
Rajesh Bhagwan Kondle, Cluster Project
Manager, Mr. H.S.P Shukla, Project Manager,
and Mr Koti Reddy, Erection In-charge. Mr. C
Sankaralingam, Task Force Leader, appreciated
the entire team on this marvellous
achievement.
The team comprising Mr. Santosh Patil,
Erection In-charge, Mr.Mohan Pradeep,
Planning In-charge, Mr. Siva Prasad and Mr.
Surya Narayana, Erection Engineers
meticulously planned the execution with
proactive support from the P&M and the
precast yard team.