My presentation at 2022 MEA conference 2 years ago
1 of 27
Download to read offline
More Related Content
Innovative modelling methodology at MEA conference.pdf
1. INNOVATIVE MODELLING
METHODOLOGY
OF FINCH WEST LRT CORRIDOR SWM MODEL
MEA Conference 2022
Julian Li PEng August, 2022
Transit Review, Toronto Water , City of Toronto
2. CONTENT
Finch West LRT project and its three challenges for water engineering
Surface flooding issue caused by LRT structure
Traditional sewer modelling methodology and its shortcomings
Develop the innovative modelling methodology
FWLRT Application and its impacts on road design and flooding control.
Impacts on new sewer system design at Highway 27.
Possible application on normal roadway to test traffic lane flooding.
3. FINCH WEST LRT PROJECT OVERVIEW
The design review period covered 2018 to 2021 for Toronto Water Transit Review
4. THREE WATER ENGINEERING CHALLENGES
IN FINCH WEST LRT PROJECT
1. The corridor surface flooding analysis
2. Water crossing safety
3. Stray current corrosion control
1
2 3
5. FINCH WEST LRT BUILDS ITS CENTRAL TRACK ISLAND
IN THE MIDDLE OF ROADWAY
The LRT central island will separate the surface runoff flow between two
sides of roadway, increase the complexity of surface flooding analyses of
the corridor.
6. THE LRT INFRASTRUCTURES WILL MAKE NORTH SIDE OF
FINCH WEST ROAD TO BE FLOODED MORE EASILY
Toronto has a general north to south terrain
slope.
The overland storm runoff at Finch West Road
mostly come from the contribution area at
north of the corridor.
The north side of roadway will keep most of
storm runoff because the LRT island restrain
the flow from north side to south side.
The storm water hydraulic model should
reflect the actual hydraulic situation, which
is a technical challenge.
7. NORMAL DUAL DRAINAGE
MODELLING METHODOLOGY
Integrate major system ( overland flow ) and
minor system ( sewer) in one model.
The storm node connecting major and minor
systems normally are manholes, related
catch-basins are assigned to the manhole.
Subcatchment runoff is collected at storm
node (MH), the inflow to the sewer at the MH
will be determined by head-discharge
relationship of related catch basins, the
remaining flow will flow at overland flow path.
The Gully type MHs are the interconnection
points of major and minor systems, the
backup flow from the sewer can overflow to
the major system.
The city of Toronto developed dual drainage
models for basement flooding studies by
InfoWorks.
8. OVERLAND FLOW PATH
IN NORMAL DUAL DRAINAGE MODEL
In urban areas, the overland
system will primarily be made
up of the road network.
For local and collector roads,
a user defined cross-section
based on a typical crowned
road with curb and slope
within ROW normally would
be a equivalent symmetrical
cross-section, so only one
flow channel is needed in
model.
10. APPLICATION OF NORMAL DUAL DRAINAGE MODEL
IN FWLRT 30 % DESIGN STAGE
Still using one equivalent symmetrical
cross-section for whole Finch West LRT
corridor at proposed condition.
No flooding difference between north
side road lanes and south side road
lanes,
Because the corridor is widened by
adding the central LRT island, the flooding
depth at proposed condition would be
less than the flooding depth at existing
condition
The modelling methodology and its results dont reflect actual field situations
11. TECHNICAL COMMUNICATION,
DISCUSSION AND COORDINATION
Biweekly meetings by CoT, Metrolinx, Project
company, design consulting company and
technical adviser of the project.
Many modelling workshops.
Toronto Water provided many technical
reviewing comments, requiring the model
should reflect actual field conditions and
working together with all technical partners.
At 2019 summer, I provided related technical
suggestions that were fully discussed and
adopted.
12. FULL MODEL: THREE OVERLAND PATHS
MODELLING CENTRAL LOCATED LRT CORRIDOR
13. FULL MODEL: THREE OVERLAND PATHS
MODELLING CENTRAL LOCATED LRT CORRIDOR
Three separated overland flow channels to simulate two side roadways
and central LRT lane.
Two side roadway cross-sections use asymmetric section to reflect actual
situation.
The major storm nodes of overland flow paths will be catch basins, not
manholes. Catch basin will directly collect subcatchment runoff.
The catch basin leads will be included in the model.
Connection weirs will be added at adjacent paths to hydraulically
integrate three paths as a whole corridor.
The full model has clear conceptions to simulate three
actual overland flow paths, and there are enough hydraulic
connections among these three paths and sewer system
15. SIMPLIFIED MODEL: TWO OVERLAND PATHS
MODELLING CENTRAL ISLAND LRT CORRIDOR
The LRT track and station drainage system will be designed by separated hydraulic
analysis, but the pipes, catch basins and overland path could not be included in the
corridor system model.
The subcatchment area of LRT central island itself will be relative small, the track
drainage system could be designed without the inflowing restrain of track catch
basins and pipes to collect the runoff.
The subcatchment runoff can be directly assigned to municipal sewer pipe or
manhole.
The track catch basin is located higher than roadway catch basin, the backup
sewer flow will firstly overflow to road way
The simplified two paths model can simulate general
hydraulic performs of central island LRT corridor like FWLRT
18. ROAD CROSS-SECTION DESIGN CHANGE
-ACCORDING TO SWM MODEL FLOODING CONTROL
Toronto Wet Weather Flow Management guide line requires the maximum ponding
depth at new Arterial Road is to the crown of the road under 100 year storm, mostly
means no curb overtopping.
FWLRT roadway is a existing roadway realignment for the LRT, the major system design
criteria include:
---If the exiting condition has no curb overtopping, the proposed condition should
have no curb overtopping.
---If the exiting condition has curb overtopping, the proposed condition should be no
worse than existing condition.
The existing curb height is about 150 mm.
New SWM model already shows the overland flow could concentrate on one side of
the roadway because of central LRT island, then the possibility of curb overtopping
and flooding to nearby properties will be increased at the side.
The solution could be increasing the overland flow path hydraulic capacity to reduce
the flooding possibility.
19. ROAD CROSS-SECTION DESIGN CHANGE
-ACCORDING TO SWM MODEL FLOODING CONTROL
The road design has been changed by
adding a new low curb beside the
bike line.
Two curbs have a total curb height
about 275 mm ( including the bike
lane slope), increasing the major
system capacity a lot.
20. IMPACTS ON HIGHWAY 27 NEW SEWER DESIGN
FWLRT Part A route design around Finch & Highway 27
Finch West LRT west end station is
Humber College Station at High
way 27.
The station is underground , and
the below grade guideway will
extend to Finch West Road , it
goes as a tunnel under the
intersection, then the guideway
ascend to surface before Finch &
Westmore intersection.
21. IMPACTS ON HIGHWAY 27 NEW SEWER DESIGN
Existing sewer system at Highway 27
There is no local sewer system along
high way 27 at the south of Finch West.
A 1200 mm storm sewer crossing
Highway 27 at the north of Humber
College Boulevard.
Another 900 mm storm sewer crossing
Highway 27 at Humber College
Boulevard intersection.
The high way surface flow will run along
the road way and road side swales to
Humber River.
The capacity of these crossing sewer
pipes are limited, and their down
stream areas are prone to possible
basement flooding.
22. IMPACTS ON HIGHWAY 27 NEW SEWER DESIGN
Proposed Highway 27 sewer at 60 % design stage
Finch West LRT project has to build a new storm sewer along the Highway 27 for the LRT track
drainage, but the runoff collection coverage could be only for LRT track drainage plus Highway 27
road surface at the maximum within the project scope.
At 60 % design stage, the new sewer has relative small pipe sizes from 375 mm to 825 mm, and a
new outfall to Humber River.
The proposed new storm sewer is not big enough to work as a local trunk sewer for the community
and possible new development.
23. IMPACTS ON HIGHWAY 27 NEW SEWER DESIGN
New SWM model identified possible flooding risk to the below grade guideway
Finch & Westmore intersection is
the sag point of a big area
The intersection is also the
connection point of the below
grade guideway and surface
tracks.
The new SWM model simulated
high flooding depth at north
west corner with the risk of
flooding the guideway.
The existing down stream sewer
and major system have no
capacity to mitigate the risk.
24. IMPACTS ON HIGHWAY 27 NEW SEWER DESIGN
A large size relief sewer along High way 27 is designed to mitigate LRT flooding risk
A new 1650 mm storm sewer will collect upstream
sewer flow and some surface flow at the low spot ,
going along Highway 27 and discharging to Humber
River.
The new Highway 27 sewer will be sized as 1650 mm
to a 1900mm X1200 mm outfall.
25. ADDITIONAL BENEFITS OF THE RELIEF SEWER
The existing upstream flow at Finch West is diverted to new sewer,
which helps to mitigate the basement flooding problem of downstream
area, and produce new capacity for future development.
The relief sewer has big pipe size and long distance to Humber River,
which can work as a local trunk sewer at the same time to save city
cost.
These two existing sewers crossing highway 27 could connect with the
new sewer and discharge the upstream flow to Humber River.
---help to mitigate the basement flooding problem for both upstream
and downstream areas.
---add new sewer capacity for future development in the whole area.
26. POSSIBLE FUTURE APPLICATION ON NORMAL ROADWAY
TO TEST TRAFFIC LANES FLOODING
Toronto Wet Weather Management Guideline
MTO has flow spread standard on travel lanes
Toronto City has the standard to keep at least
one lane free of water under 2 year storm
There is no existing technical method to test
water flow spread on travel lanes and judge
the standard compliance .
If the flooding depth can be calibrated, the
new TWO overland paths model could be
used to test water flow spread, including the
roadway with horizontal slope.
27. My special thanks to : Paul Haywood
Farzad Fahimi
Stanley Shui of ARUP
Ahmad Norouzi of Metrolinx
Saeid Behnia of CoT, ECS
Mike Jacobs
Lawrence Shintani of CoT, TW
Thank you !
Any questions?