KHUSELEKA
North-West, Rustenburg
PROJECT TYPE: OPENCAST MINING
CLIENT:
Anglo Platinum Limited
VALUE:
R109 Million
CONSULTANTS:
None
PROJECT DURATION:
24 Months
DATE OF PROJECT:
1 November 2011
PROJECT DESCRIPTION:
Opencast Mining of Merensky Reef to a depth of
20m.
Approximate volumes mined for the project :-
 Topsoil 384,428m続
 Overburden 1,342,440m続
 Ore 169,878m続
 Topsoil Rehab 337,189m続
 Filling Void 1,039,109m続

More Related Content

Kuseleka Opencast

  • 1. www.construction.murrob.com KHUSELEKA North-West, Rustenburg PROJECT TYPE: OPENCAST MINING CLIENT: Anglo Platinum Limited VALUE: R109 Million CONSULTANTS: None PROJECT DURATION: 24 Months DATE OF PROJECT: 1 November 2011 PROJECT DESCRIPTION: Opencast Mining of Merensky Reef to a depth of 20m. Approximate volumes mined for the project :- Topsoil 384,428m続 Overburden 1,342,440m続 Ore 169,878m続 Topsoil Rehab 337,189m続 Filling Void 1,039,109m続