This document provides status updates for a LEGO Mindstorms robotics project over two sprints. The first sprint shows progress of 45% overall after two weeks, with work deadlines of 100% for week one and 90% for week two. The second sprint shows increased progress, with overall progress of 100% by the end of week four and work deadlines of 85% for week three and 100% for week four.
1 of 4
Download to read offline
More Related Content
Lego Line Follower
1. W O L F w w w . w e b s i t e . c o m 1
L E G O
Minestorms
E C U 1 7 8 P R O J E C T L E G O R O B O T C H A L L E N G E ( L R C ) M I L I N D A P R A S A N D E S I L V A
2. W O L F w w w . w e b s i t e . c o m 2
LEGO
MINDSTORM
3. W O L F w w w . w e b s i t e . c o m 3
First Sprint
(First And Second Week)
WEEK ONE WORK DEADLINE
100%
WEEK TWO WORK DEADLINE
90%
PROGRESS OVERALL OF PROJECT
45%
HAVE WE MET
4. W O L F w w w . w e b s i t e . c o m 4
Second Sprint
(Third And Fourth Week)
WEEK THREE WORK DEADLINE
85%
WEEK FOUR WORK DEADLINE
100%
PROGRESS OVERALL OF PROJECT
100%
HAVE WE MET