1) Kestrel mine underwent an improvement program from 2007-2010 to optimize longwall operations through changes to organization, maintenance practices, cutting practices, and processes.
2) Key changes included implementing split start times to increase cutting time, overhauling maintenance practices, conducting studies to determine the optimal 60:40 cutting pattern, and educating operators to increase automation.
3) As a result of these improvements, from 2010 onward the mine achieved increased cutting hours, fewer days between longwall moves, and higher expected annual production and sales. However, challenges remained such as increased aquifer pressures and transitioning to a new 375m longwall.
This document discusses improvements made to longwall mining operations at Rio Tinto's Kestrel coal mine in Australia. Key points include: upgrading the longwall shearer and supports, improving reliability of hydraulic systems and conveyors, standardizing maintenance practices, reducing downtime during longwall moves, and improving productivity and safety performance. Recent improvements have increased average weekly operating time to over 90 hours and are forecast to increase annual saleable coal production to nearly 6 million tonnes, over 10% higher than the previous year.
Kumar Shashi Kant is seeking a managerial role in project maintenance for a cement company. He has 8 years of experience in cement plant projects, maintenance, and service activities. Currently he is the Deputy Manager of Maintenance at OCL India overseeing the maintenance of cement grinding mills. He has expertise in project maintenance for pyroprocessing equipment, conveyors, and auxiliary systems. He is skilled in planning, scheduling, budgeting, inventory control, and safety compliance.
Boda Nagappa is applying for a senior level position in projects or mechanical operations at Nirma Cement Ltd. He has over 27 years of experience in cement plant operations and maintenance. Currently he is working as General Manager of Mechanical Engineering at Nirma Cement Ltd, where he oversees the operation and maintenance of the entire plant. He is seeking a more responsible position that allows him to further develop his skills and add value to an organization.
Longwall mining is a major method of underground coal extraction worldwide. In India, coal accounts for over 50% of energy production, though most is still extracted via opencast mines. Longwall mining was introduced to India in the 1970s but has seen limited improvement and adoption since. Key longwall equipment includes powered roof supports, shearers, conveyors, and monitoring is important for strata control and safety. Organizing longwall panels and transferring equipment between panels is a complex operation involving dismantling, transport and reassembly of machinery.
Robert Woods has over 25 years of experience in engineering roles within the paper industry. He holds multiple qualifications including a Diploma of Engineering, Bachelor of Engineering, and Graduate Diploma of Business. Woods has a history of successfully managing projects to improve safety, operations, and product quality. He is also experienced in leadership, technical troubleshooting, and maintaining continuous operations.
An australian power plant harnesses the powe of reliability excellenceChad Ethredge
油
The power plant was struggling with reliability issues and high costs that threatened its ability to provide power to a nearby aluminum smelter. It implemented a reliability excellence program with Life Cycle Engineering to improve processes around work planning, materials management, and reliability engineering. This led to increased availability, reduced maintenance costs, and avoided costs of over $1 million annually. As a result, the plant's relationship with the smelter was secured and it transformed to a more proactive, reliable operation.
Ronald Hawkins has over 29 years of experience in mining and construction safety roles. He has worked as a Safety Manager, Safety Advisor, and Safety Coordinator on various projects in Queensland, New South Wales, Western Australia, and the Northern Territory. His experience includes implementing safety plans, performing audits and inspections, investigating incidents, and coordinating training programs.
my most current resume, approximately 5 years experience as a metallurgical engineer at a copper mine, and 2.5 years as an operations supervisor in copper and gold mines.
DIPANKAR BANDYOPADHYAY has over 25 years of experience in production and operations management for petrochemical plants. He has held several leadership roles including Senior Vice President and SBU Head at Reliance Industries Ltd. He has expertise in areas such as production planning, plant safety, quality control, and process optimization. Some of his key achievements include contributing to the engineering of large greenfield projects, improving plant safety standards, and implementing initiatives that increased production and reduced costs.
Sharon Carvolth is a principal consultant at Audit Services International, which provides safety, environmental, and quality management system auditing services to mining, heavy industry, and petroleum companies. She has over 25 years of experience implementing, auditing, and training clients on management systems. Her clients include major companies like BHP Billiton, Rio Tinto, and Origin Energy. She specializes in developing legally compliant safety management systems and facilitating risk assessments to help clients achieve certification and reduce risks.
CV Chris Davies 18.04.2016 Master copyChris Davies
油
Chris Davies has over 30 years of experience in maintenance management and engineering roles. He is currently the Planning and Maintenance Manager at Holcim Cement in Westport, where he oversees maintenance operations, planning, budgets, and safety. Prior to this role, he held positions in maintenance planning and shutdown management at Holcim as well as roles in engine overhaul technician and charge hand roles at Air New Zealand and Hamilton Jet. He has extensive experience managing teams, projects, budgets, and safety.
Rajni Kant Verma has over 23 years of experience in strategic management, project management, operations management and maintenance management. He has successfully led large projects in aluminum smelting and carbon plants for companies like Hindalco, Aditya Birla Group, and Alba Aluminum Bahrain. Verma holds an M.Tech from IIT Delhi and has extensive skills in areas like production management, quality assurance, maintenance, commissioning, and team management.
PST0146 - Trouble Free Well Integrity Management (Profile Updated)Mia.C Petrosync
油
This document provides information on a 5-day course on well integrity management taught by Rein Maatjes, a retired well services specialist with over 35 years of experience at Shell. The course objectives are to discuss completion design and well integrity principles, identify well integrity issues and accountability, and develop preventive maintenance strategies. It provides an agenda that covers topics like barrier understanding, internal and external corrosion monitoring, sand removal, and consequences of well integrity failures. The goal is to help personnel optimize production costs and maintain well integrity over the lifecycle.
Webinar: CCS major project development lessons from the ZeroGen experienceGlobal CCS Institute
油
The ZeroGen Integrated Gasification Combined Cycle (IGCC) with CCS project, was a first-of-a-kind, commercial-scale CCS project proposal in Australia. Lessons learnt from this project include real-life project management experience integrating the key elements of a large-scale CCS project, from the technical to the commercial to stakeholder management.
This webinar was presented by Professor Andrew Garnett, Director, Centre for Coal Seam Gas, The University of Queensland. The Q&A session also included Martin Oettinger, Deputy Director, Low Emissions Technology for ACALET. Martin's career includes 6 years in a senior technical leadership role with ZeroGen.
Proper Asset Maintenance Improves Safety, Reliability, and ProfitabilityUSC Consulting Group
油
Gain firsthand knowledge of strategies, processes, and methodologies used to develop an asset maintenance program for revenue-producing assets. This information can be applied to any industry with a reliance on heavy equipment and assets.
Paul Hampshire is seeking a new position utilizing his experience in clean water projects, site supervision, and reinstatement. He has over 10 years of experience as a Reinstatement Agent managing teams and budgets over $85 million. He is safety-focused, able to develop good practices, and confident he can be a valued addition to any management team.
The document outlines the qualifications and experience of an engineer seeking a position as a Commissioning/Startup Manager, including over 26 years of experience in power plant management, commissioning, and operations. It details roles held with various companies commissioning and starting up combined cycle and simple cycle power plants, providing leadership and training to clients. Relevant skills and qualifications include relationship building, problem solving, and exemplary work ethics.
GreyStar Corporation is an oil and gas operations and maintenance contractor that was founded in 1995. Since then, it has taken over operations for major projects involving offshore fields, platforms, pipelines, gas plants, and wells across the globe. Some of its most notable projects include operating Tennessee Gas Pipeline in the Gulf of Mexico; providing operational readiness for Shell's deepwater Nakika project; and securing a ten-year contract to operate over 60% of Mexico's oil production infrastructure for Pemex. GreyStar is responsible for the safe and reliable management of large-scale oil and gas infrastructure across land and sea.
Craig Ronald Edwards is an experienced Health, Safety and Environment professional with over 15 years of experience. He has held HSE roles at various mining and energy projects in Western Australia, including his current role as HSE Advisor for the Wheatstone LNG project. Edwards has a strong track record of developing and implementing safety programs and procedures, conducting audits and investigations, and advising project teams on compliance with regulations. He aims to apply his expertise to new challenges in the HSE field.
Glenn Whitfield has over 20 years of experience in engineering, operations management, business improvement, and pastoral roles. He has a passion for people and processes and enjoys helping teams achieve goals. His experience includes roles in asset management, strategic planning, business planning, investigations, and culture change with companies like Rio Tinto, Dampier Salt Limited, and churches. He has a Bachelor's in Electrical Engineering and qualifications in operational leadership and Six Sigma.
This document discusses Hydro-Quebec's efforts to optimize the preventive maintenance program at their Gentilly-2 Nuclear Power Plant. It describes developing an integrated equipment reliability process focused on rationalizing preventive maintenance tasks based on criticality and cost-effectiveness. The document outlines applying a preventive maintenance optimization approach based on reliability centered maintenance principles and tools like the EPRI PM Basis Database. This involves analyzing existing tasks, critical equipment, failure modes and setting optimized task frequencies. It also discusses integrating performance monitoring and continuous improvement to form a comprehensive, living equipment reliability process meeting regulatory requirements.
Luz McGrath has over 25 years of experience in engineering, operations, and compliance roles in the energy industry. She has a BS in Mechanical Engineering from Pratt Institute. Most recently, she worked at United Illuminating Company as a NERC Coordinator, where she collaborated on NERC compliance issues across departments and helped transition processes to new standards. Prior to that, she held various engineering and operations roles at Consolidated Edison, including as a power dispatcher and project manager for reactor cooling pump overhauls. She is fluent in Spanish and has certifications in related technical areas.
Dinesh Chauhan has over 35 years of experience in pre-commissioning, commissioning, maintenance and reliability roles. He is currently a Commissioning Coordinator at Sohar Refinery in Oman working for Petrofac International. Prior to this, he has held roles such as Commissioning and Start-up Coordinator at Equate Petrochemicals in Kuwait and Senior Manager of Maintenance at Reliance Industries in India. He has expertise in areas such as procedure development, equipment testing, team leadership, and client relationship management.
This resume is for Gufron, a male Indonesian born in 1963 with a bachelor's degree in mechanical engineering. It summarizes his work experience from 2011 to 1990 at several oil and gas companies in various engineering and management roles related to steam flood projects, central gathering stations, and capital projects management. His most recent role since 2011 has been as the Team Manager for Operational Excellence on the large North Duri Development project in Indonesia.
Susan Cassidy has over 15 years of experience as a process engineer, primarily working on refinery projects. She received her Bachelor's degree in Chemical Engineering in 2000. Her career includes roles as a process engineer at Engen Refinery and Foster Wheeler, where she led engineering projects in South Africa, Malaysia, Thailand, Kuwait, and Canada. Currently, she is the Principal Process Engineer at Engen Refinery, leading the Utilities group and overseeing various water reduction initiatives and projects.
Having the right equipment available at the right time can optimize productivity and reduce costs. Read about how an Asset Reliability Program can match demand with your revenue-producing assets. This whitepaper is focused on the Mining industry but the concepts apply to all industries that rely on heavy assets to generate revenue.
John Stewart has over 30 years of experience in maintenance planning and asset management. He conducted a review of SSE's hydro operations that identified issues like a lack of clear asset management strategy and underutilized planning resources. As a result, he restructured the planning team, defined clear priorities, and developed processes to improve efficiency. Previously, he held various roles at Edinburgh Airport developing maintenance strategies using IBM Maximo and ensuring regulatory compliance. He has a strong background in electrical engineering and maintenance planning.
This curriculum vitae summarizes Marcel Paul's educational background and work experience. He has a BTech in project management, an MBA, and various technical qualifications. His work experience includes positions as an apprentice loom tuner, naval fitter, maintenance fitter for ArcelorMittal steel, maintenance planner, and senior maintenance planner for various companies in oil, gas, and engineering industries. He has experience planning shutdowns and projects.
More Related Content
Similar to Longwall Improvement at Kestrel Mine (20)
DIPANKAR BANDYOPADHYAY has over 25 years of experience in production and operations management for petrochemical plants. He has held several leadership roles including Senior Vice President and SBU Head at Reliance Industries Ltd. He has expertise in areas such as production planning, plant safety, quality control, and process optimization. Some of his key achievements include contributing to the engineering of large greenfield projects, improving plant safety standards, and implementing initiatives that increased production and reduced costs.
Sharon Carvolth is a principal consultant at Audit Services International, which provides safety, environmental, and quality management system auditing services to mining, heavy industry, and petroleum companies. She has over 25 years of experience implementing, auditing, and training clients on management systems. Her clients include major companies like BHP Billiton, Rio Tinto, and Origin Energy. She specializes in developing legally compliant safety management systems and facilitating risk assessments to help clients achieve certification and reduce risks.
CV Chris Davies 18.04.2016 Master copyChris Davies
油
Chris Davies has over 30 years of experience in maintenance management and engineering roles. He is currently the Planning and Maintenance Manager at Holcim Cement in Westport, where he oversees maintenance operations, planning, budgets, and safety. Prior to this role, he held positions in maintenance planning and shutdown management at Holcim as well as roles in engine overhaul technician and charge hand roles at Air New Zealand and Hamilton Jet. He has extensive experience managing teams, projects, budgets, and safety.
Rajni Kant Verma has over 23 years of experience in strategic management, project management, operations management and maintenance management. He has successfully led large projects in aluminum smelting and carbon plants for companies like Hindalco, Aditya Birla Group, and Alba Aluminum Bahrain. Verma holds an M.Tech from IIT Delhi and has extensive skills in areas like production management, quality assurance, maintenance, commissioning, and team management.
PST0146 - Trouble Free Well Integrity Management (Profile Updated)Mia.C Petrosync
油
This document provides information on a 5-day course on well integrity management taught by Rein Maatjes, a retired well services specialist with over 35 years of experience at Shell. The course objectives are to discuss completion design and well integrity principles, identify well integrity issues and accountability, and develop preventive maintenance strategies. It provides an agenda that covers topics like barrier understanding, internal and external corrosion monitoring, sand removal, and consequences of well integrity failures. The goal is to help personnel optimize production costs and maintain well integrity over the lifecycle.
Webinar: CCS major project development lessons from the ZeroGen experienceGlobal CCS Institute
油
The ZeroGen Integrated Gasification Combined Cycle (IGCC) with CCS project, was a first-of-a-kind, commercial-scale CCS project proposal in Australia. Lessons learnt from this project include real-life project management experience integrating the key elements of a large-scale CCS project, from the technical to the commercial to stakeholder management.
This webinar was presented by Professor Andrew Garnett, Director, Centre for Coal Seam Gas, The University of Queensland. The Q&A session also included Martin Oettinger, Deputy Director, Low Emissions Technology for ACALET. Martin's career includes 6 years in a senior technical leadership role with ZeroGen.
Proper Asset Maintenance Improves Safety, Reliability, and ProfitabilityUSC Consulting Group
油
Gain firsthand knowledge of strategies, processes, and methodologies used to develop an asset maintenance program for revenue-producing assets. This information can be applied to any industry with a reliance on heavy equipment and assets.
Paul Hampshire is seeking a new position utilizing his experience in clean water projects, site supervision, and reinstatement. He has over 10 years of experience as a Reinstatement Agent managing teams and budgets over $85 million. He is safety-focused, able to develop good practices, and confident he can be a valued addition to any management team.
The document outlines the qualifications and experience of an engineer seeking a position as a Commissioning/Startup Manager, including over 26 years of experience in power plant management, commissioning, and operations. It details roles held with various companies commissioning and starting up combined cycle and simple cycle power plants, providing leadership and training to clients. Relevant skills and qualifications include relationship building, problem solving, and exemplary work ethics.
GreyStar Corporation is an oil and gas operations and maintenance contractor that was founded in 1995. Since then, it has taken over operations for major projects involving offshore fields, platforms, pipelines, gas plants, and wells across the globe. Some of its most notable projects include operating Tennessee Gas Pipeline in the Gulf of Mexico; providing operational readiness for Shell's deepwater Nakika project; and securing a ten-year contract to operate over 60% of Mexico's oil production infrastructure for Pemex. GreyStar is responsible for the safe and reliable management of large-scale oil and gas infrastructure across land and sea.
Craig Ronald Edwards is an experienced Health, Safety and Environment professional with over 15 years of experience. He has held HSE roles at various mining and energy projects in Western Australia, including his current role as HSE Advisor for the Wheatstone LNG project. Edwards has a strong track record of developing and implementing safety programs and procedures, conducting audits and investigations, and advising project teams on compliance with regulations. He aims to apply his expertise to new challenges in the HSE field.
Glenn Whitfield has over 20 years of experience in engineering, operations management, business improvement, and pastoral roles. He has a passion for people and processes and enjoys helping teams achieve goals. His experience includes roles in asset management, strategic planning, business planning, investigations, and culture change with companies like Rio Tinto, Dampier Salt Limited, and churches. He has a Bachelor's in Electrical Engineering and qualifications in operational leadership and Six Sigma.
This document discusses Hydro-Quebec's efforts to optimize the preventive maintenance program at their Gentilly-2 Nuclear Power Plant. It describes developing an integrated equipment reliability process focused on rationalizing preventive maintenance tasks based on criticality and cost-effectiveness. The document outlines applying a preventive maintenance optimization approach based on reliability centered maintenance principles and tools like the EPRI PM Basis Database. This involves analyzing existing tasks, critical equipment, failure modes and setting optimized task frequencies. It also discusses integrating performance monitoring and continuous improvement to form a comprehensive, living equipment reliability process meeting regulatory requirements.
Luz McGrath has over 25 years of experience in engineering, operations, and compliance roles in the energy industry. She has a BS in Mechanical Engineering from Pratt Institute. Most recently, she worked at United Illuminating Company as a NERC Coordinator, where she collaborated on NERC compliance issues across departments and helped transition processes to new standards. Prior to that, she held various engineering and operations roles at Consolidated Edison, including as a power dispatcher and project manager for reactor cooling pump overhauls. She is fluent in Spanish and has certifications in related technical areas.
Dinesh Chauhan has over 35 years of experience in pre-commissioning, commissioning, maintenance and reliability roles. He is currently a Commissioning Coordinator at Sohar Refinery in Oman working for Petrofac International. Prior to this, he has held roles such as Commissioning and Start-up Coordinator at Equate Petrochemicals in Kuwait and Senior Manager of Maintenance at Reliance Industries in India. He has expertise in areas such as procedure development, equipment testing, team leadership, and client relationship management.
This resume is for Gufron, a male Indonesian born in 1963 with a bachelor's degree in mechanical engineering. It summarizes his work experience from 2011 to 1990 at several oil and gas companies in various engineering and management roles related to steam flood projects, central gathering stations, and capital projects management. His most recent role since 2011 has been as the Team Manager for Operational Excellence on the large North Duri Development project in Indonesia.
Susan Cassidy has over 15 years of experience as a process engineer, primarily working on refinery projects. She received her Bachelor's degree in Chemical Engineering in 2000. Her career includes roles as a process engineer at Engen Refinery and Foster Wheeler, where she led engineering projects in South Africa, Malaysia, Thailand, Kuwait, and Canada. Currently, she is the Principal Process Engineer at Engen Refinery, leading the Utilities group and overseeing various water reduction initiatives and projects.
Having the right equipment available at the right time can optimize productivity and reduce costs. Read about how an Asset Reliability Program can match demand with your revenue-producing assets. This whitepaper is focused on the Mining industry but the concepts apply to all industries that rely on heavy assets to generate revenue.
John Stewart has over 30 years of experience in maintenance planning and asset management. He conducted a review of SSE's hydro operations that identified issues like a lack of clear asset management strategy and underutilized planning resources. As a result, he restructured the planning team, defined clear priorities, and developed processes to improve efficiency. Previously, he held various roles at Edinburgh Airport developing maintenance strategies using IBM Maximo and ensuring regulatory compliance. He has a strong background in electrical engineering and maintenance planning.
This curriculum vitae summarizes Marcel Paul's educational background and work experience. He has a BTech in project management, an MBA, and various technical qualifications. His work experience includes positions as an apprentice loom tuner, naval fitter, maintenance fitter for ArcelorMittal steel, maintenance planner, and senior maintenance planner for various companies in oil, gas, and engineering industries. He has experience planning shutdowns and projects.
1. Longwall Improvement at Kestrel Mine
2010 Longwall Conference, Hunter Valley
2010 Longwall
conference slides.pdf
Brief personal profile
For those of you I have not met my name is John Coughlan and I am the acting General
manager of operations at Kestrel mine. I am privileged to be here today to address this
conference.
Introduction
Kestrel mine is located 50km north of Emerald in central Queenslands Bowen basin. The
mine was purchased by Rio Tinto in 1999 and is one of 6 mines operated by Rio Tinto Coal
Australia (RTCA). The German Creek seam is mined and mix of predominantly coking and
thermal coal is produced. We are currently in the construction phase of an extension to the
mine, to be known as Kestrel south
Kestrel is the only underground coal mine in the RTCA suite of mines. Presently there are
3 development sections, a long wall section, coal clearance to a 3 stage wash plant and a
rail load out. We ship approximately 4 million tonnes per year. The facility is self contained
and can be illustrated in a typical longwall mine value chain.
At Kestrel we are fortunate in that we have 2 available longwall systems each comprising a
Bucyrus shearer, 146 x 860t supports, AFC, BSL and monorail and each has a name plate
capacity of 2,500 tonnes per hour. These components are of various ages however the
supports are original, approaching 20 years in age.
2. In 2007 an improvement programme for the Kestrel mine was initiated. The programme
concentrated on three broad areas of development, longwall and CHPP. Given this is the
longwall conference we will take this opportunity to discuss the longwall improvement.
Context
In 2007 there were several factors that provided the impetus, or burning platform, to
improvement.
The mine recently had a new general manager appointed who had some firm views on
longwall operations; the longwall should provide the drumbeat for the operation, the
longwall should be treated as fixed plant not mobile and finally lean thinking and tools could
be applied to better manage process associated with longwall activities.
At this time Rio Tinto was undergoing a global change to the way assets are managed and
introduced a number of asset management protocols. In the first instance these protocols
were to drive a change to planned maintenance and increased reliability as a platform to
then initiate further refinement and optimisation of maintenance practices. Increased
reliability will then feed into higher operational hours.
Rio Tinto was completing the feasibility and seeking approval for funds for the Kestrel Mine
Extension. This is an ambitious project utilising a state of the art 375m longwall to underpin
a high production low cost mine at Kestrel into the future. Achieving operating parameters
such as cut hours and availability assigned to the new system while operating the existing
system would underpin confidence in the investment decision.
An assessment was carried out with the help of consultants, Deloittes. This assessment
identified the broad areas of opportunity available to deliver improvement and provided a
framework for the improvement initiatives.
Safety
First and foremost, to be judged successful any change introduced for improvement has to
deliver safety improvement.
3. Kestrel continues to set challenging objectives with regard to the health and safety of its
employees. We do this as a part of the industry in Queensland and as part of the broader
Rio Tinto group.
We strive to implement a strategy to develop a culture of trust and transparency driving
improved behavioural safety in an environment compliant to regulation and RT HSE
standards. Through the period 2007 to now we have directed effort into creating
safe people articulating behaviours and setting expectations
safe work continued risk assessment and standardisation of work
safe equipment improving equipment features to eliminate hazards
safe environment using standards, training and contractor management
to enable the above
Whilst we have improved from 2007 to today, we are yet to make a step change to the next
level. We have plateaued. We are performing well within the Queensland underground
coal, and opencut, sector. However our challenge is to be regarded as performing well
within the Rio Tinto group. We have some distance make up the field where internally
some of our RT peers experience incident rates less than 50% those of Kestrel.
Structure and organisation
Early changes made at an organisational level centred on creating 24 hours per day of
opportunity to cut coal. This was not available to the longwall operations.
Split start times were created to create access to sufficient skilled labour operator,
maintenance and statutory to supplement operations through a shift change. The roster
makes use of 12.5 hour shifts so nominal shift starts at 6:00 and 7:30 on day and night shift
were implemented to maintain people at the face for a period at either end of day and night
shift, while other crew members travelled either in or out of the panel. A hot handover at
the face provides face activity continuity and is self-sustaining as an incumbent crew
cannot leave until the replacement crew arrives.
4. Support crew composition was adjusted to provide the skills and people through this
window period. This meant that when required the support personnel could be at the face
cutting and when not they could be performing other support tasks.
Longwall planned stoppages were organised around a single time in the week to conduct
maintenance and support activities for the longwall and clearance system. This day is
developed around pulling up early at a predetermined time, executing the tasks in the day
to a locked in plan and then cutting at least one shear at 5:00pm to set up for the following
shift. Planning and execution of the maintenance component for this day follows the
discipline established by the work management process.
The rebuild process for the alternative longwall system had a full and comprehensive
review. The emphasis of the rebuild changed from fix to overhaul and project management
discipline is applied through the scoping, implementation and finalisation of each rebuild
step. Much of the scoping has been conducted through RAMBO and defect elimination
methods, highlighting tasks previously not undertaken eg replacement of valve gear and
the removal of all the redundant system to be worked on at the surface.
Reliability
The asset management protocols mandated by Rio Tinto have been in place since 2007
with their intent to increase reliability. These protocols provide discipline to the:
management of maintenance work identify, plan, schedule, implement, complete,
analyse
reduction of contamination for example improving support pressures
o improving the quality of water to 7 micron to protect valve gear
o emulsion plant to prepare emulsion and deliver to pump at a pre-determined
quality
elimination of defects for example reduced DA ram failure by increasing rod
diameter from 100 to 120mm
operation for reliability for example analysing the best cut sequence to 60:40
5. maintenance tactics determining task frequency and opportunity to carry out work
in the cutting cycle
The approach to reliability in our longwall operations was further promoted through the
attendance of operations and maintenance leaders at a Ron Moore reliability workshop
where the message was clear reliability is not a maintenance accountability. This
initiated a site longwall reliability workshop involving operations, electrical and mechanical
personnel facilitated by an asset management professional from RTCA. A process where
barriers were identified, prioritised and turned into objectives derived a series of
subsequent actions to be implemented. These actions comprised process, administrative,
logistics, repair and standardising tasks.
A particular effort has been put into management of maintenance work through the work
management process. This is the RT asset management protocol that required a discipline
to be installed. The Kestrel outcomes in this process are measured and benchmarked with
all RT operations in what are called the global metrics. This has created a significant step
for maintenance work to move away from a reactive domain to a planned domain.
Cutting practice
A study was carried out on the cutting modes to determine the extent of discretion being
applied over the parameters on a crew basis and through observation of load ratings how
this variation placed stress on the operating system. This study determined a 60:40 push
to maingate parameter and change management was used to install this practice across
the 4 operating crews.
The key to the change management was the use of a trial across the crews of the various
parameter sets; 80:20, 70:30 and 60:40. Each parameter was used by all crews for a week
and data was obtained during this time. This meant each crew had first hand experience in
each parameter set, could observe what was taking place and understand the assessment
of each technique. The study concluded the 60:40, while not giving the best instantaneous
productivity as the best cutting pattern with regards to safety of the operators, reliability of
equipment, distribution of load and productivity of the mine.
6. Kestrel took a more energetic approach to automated cutting during this time. There was
some automation facility available in the form of an inclinometer system and Bucyrus
software. However there was little confidence in the facility and take up of it had been
unenthusiastic.
Moves to change the perception of automation and capitalise on the benefits consisted of 2
strategies; (i) upgrade the technology to a reliable and accurate system and (ii) educate
and train the operators to sufficiently grow their confidence in the use and benefits of
automation.
Technological changes included an upgrade from the inclinometer to an IMAR system with
associated software adjustments. At this time the mine also implemented a broad ranging
SCADA change through CITECT capability. Now real time information was more readily
accessible and the capacity to monitor automation, and other, activities was improved from
the previous macro-view capability. Further assistance in monitoring is now available
through the provision of push reports detailing activities and time.
Several tactics were used to educate and train operators. A champion for the technology
was identified and introduced a move prompted from a previous paper presented at this
conference. The champion has been rotating though the crews on 2 month blocks. The
role of the champion has been to teach the technology, provide feedback and confidence
that the technology works, educate the operators in the broader quality aspects of cutting
using the roof as the target, speed for operations, arms for quality in a manner that was
more what to do not how to do it. This involvement with the crews was made easier when
the operation scaled back from 4 operating crew to 2 in response to the GFC in 2009. The
concentrated effort on these 2 crews, and that they always returned to their workplace,
meant they were proficient when the operation went back to 4 crews. The effort then went
into the other 2 crews.
The Bucyrus model was brought to site. Operators were able to experience automation
usage in a simulated environment.
7. Now 18 months on there is widespread acceptance of the automation. We are now in the
process of rotating a skilled trainer across all the crews to standardise the how to do it
aspect. Our push reporting now shows that we have 80% of the cutting being conducted in
the automation mode.
Process improvement
A number of longwall processes were addressed through improvement projects.
Lean was introduced to Kestrel at this time and after visits to RTA to look at how it can
work, application of 5s, visual workplace and standardised work became widespread in the
operation. Information boards were designed for the longwall group and these became the
focus area for crew briefings and progress tracking, both performance against plan and
issues resolution. Waste elimination projects such as the overhaul trolley were undertaken
a trolley that houses tools, parts and enables isolation of a single chock.
We introduced a CITECT system improving the access to realtime data and feedback
across operational crews. Reports and system status are immediately available at the
maingate and transformer computers. These reports are available across the network. In
addition we are developing the capability of LVA beyond simply a geotech aid.
The retraction process was reviewed with a view to QCO reduce the time from last shear
to first shear. While the sequencing of tasks was analysed to determine the best allocation
and use of labour, capital was invested in the form of a second transformer and pump
station. This has enabled a leap frog approach to be applied and time savings of up to 8
hours have been achieved.
The commissioning of each installed longwall system post install has been defined as a
process. This starts with a dry phase where there is a run through from power off to power
on with no picks in coal. A disciplined process is then applied to the wet commissioning as
increased numbers of shears are achieved as prescribed checks are completed. The key
to this stage is that the checks take precedence over the shears, containing the urge to
just get going and underpin reliability later in the block.
8. Along the way
In January 2008 we had the floods in Emerald. While this did not directly endanger the
mine, the mine was indirectly affected by cut roads preventing workforce access and water
quality.
Access was maintained to the mine using chartered aircraft and a rotation of mine critical
staff and officials. This kept the mine open, ensured that any critical issues could be
managed and set a platform for remobilisation once the flood situation eased. However our
real test came when the longwall was initiated.
At this time we were commissioning the longwall system in the 305 block. The existing
filtration of raw water could not handle the changed water quality, with higher levels of
sedimentation, leading to continued valve failure in the chocks. In the short term the mine
resolved this using an IMT approach - coupled with some constraint theory (throw
everything at the bottleneck eg charter a plane to bring a full changeout of valves from and
OEM) - by changing out most of the valves in the system, installing a potable water supply
and then proceeding with the purchase and installation of a bulk emulsion plant (we may
have been a bit behind the field on this one)
In 2009 the coking coal market depressed rapidly with the global financial crisis. The
Kestrel response to this was to throttle the mine output in direct proportion to confirmation
of sales. In the longwall a cutting programme was developed using 2 crews out of 4, the
operating principle being that the longwall would run hard for a period then stop rather than
advance continually at a slower rate. The improved reliability and chock performance
enabled this strategy.
Labour not required in the longwall through the non-cut periods was reallocated, essentially
replacing contract labour. Personnel were deployed to development sections, CHPP and
the chock overhaul project. Full manning resumed later in the year most people returned.
9. Where are we now
H1 2010 has seen the manifestation of improvement in the operation and changeover of
the longwalls. The improvement can be seen in the ytd achievements;
cutting hours achieved per week
days per 1st
100 meters cut in a block
annual expected metres retreat
annual expected ROM tonnes
annual expected saleable tonnes
There have been no significant roof events since the support system improvements were
made.
The future
While we have made these changes to date through the efforts of a very dedicated team,
there remain a number of challenges to contend with.
The remaining blocks in the 300 series show an increase in cross grade as these blocks
progress up dip. This is increasing wear and stress on the drives, chains, racks and
trapping shoes.
As we progress up dip we mine in closer proximity to an overlying aquifer. There is a
likelihood of water ingress into the workings so drainage and pumping mitigation factors are
being implemented.
We continue on our automation journey.
We are going to install, commission and bring up to steady state operations a new 375m
unit at Kestrel South.