Local government control over permits for cell sites and other wireless facilities was drastically curtailed in California. Steve Blum, president of Tellus Venture Associates, offer options for cities and counties at a seminar sponsored by Joint Venture Silicon Valley in San Jose on 8 March, 2016
1 of 8
Download to read offline
More Related Content
Maintain control of wireless permits and adapting to AB 57 requirements
2. Shot clocks designed
for fast decisions: yes
or no
Same rules but new process
Requires change of culture
150 day clock = less than 90 days
working time
Assume colocations fall under 60-day
clock
No more back and forth with
applicants
TellusVenture Associates
3. Front load application
process
Justi鍖cation for less than 150-day window
All state & federal permits, licenses done
Photo simulations, including future modi鍖cations
CEQA studies, including seasonal bio surveys
All information for all local permits, e.g.
encroachment
Valid permit for existing structures
Neighborhood meeting
TellusVenture Associates
4. Encourage
pre-application
consultation
Allow waivers for favored designs,
locations such as facade mounts, light
poles
Fast track city property, ROW
If OK waive neighborhood meeting,
allow negative declaration
Denial of waiver is denial of application
TellusVenture Associates
5. Set up review for
quick initial decision
Publish detailed checklist
Request additional info within 30 days
Administrative approval/denial without
hearing
Incomplete application, design
changes grounds for denial
No additions, changes, amendments
without mutual agreement to pause
(toll)
TellusVenture Associates
6. Automatic appeal of denials
to city council
5 days to appeal approvals,
assume clock keeps running
TellusVenture Associates