Directors Meeting - March 29, 2022
University of South Carolina Division of Student Affairs and Academic Support
presenters:
April Barnes, executive director of University Housing
Dennis Pruitt, vice president for student affairs
4. CAMPUS VILLAGE OPENING FALL 2023
$240,000,000
project, the largest project in SC state history
504,034 sq. feet
housing, dining, collaborative spaces and more
6. CAMPUS VILLAGE STUDENT IMPACT
Living Learning Communities
Entrepreneurship and Innovation
Engineering
Student Success Center
University Health Satellite Center
Community Kitchens, Study Spaces,
and Lounges
Collaborative Spaces
Food Options
Dining Hall
Starbucks
Gamecock General
7. CAMPUS VILLAGE
Building Information
Bldg 1 412 Beds (2 Bedroom Pods)
Bldg 2 436 Beds (4 Bedroom Suites; 9 ADA Accessible)
Bldg 3 460 Beds (4 Bedroom Suites; 10 ADA Accessible)
Bldg 4 500 Beds (4 Bedroom Suites; 20 ADA Accessible)
Good morning! It is my pleasure to get to speak with you today and update you on the progress we have made on the campus village project. We are getting excited to see the buildings start to take form and wanted you to see how the landscape on south campus is changing.
We are excited to be participating in the largest building project in the history of the state of SC. This 240 million dollar project will add over half a million square feet for our students to engage and grow in.
There are four buildings and a transportation hub to the project. I wanted to orient you so you know what I'm referring to as we move through this presentation.
Campus village was intentionally designed to reimagine and revitalize south campus. It not only will house studentswhich we will get to, but it also hold a lot of engagement opportunities. We have two living learning communities that will be housed in buildings 3 and 4. We have a satellite office for the student success center with offices and multipurpose space. It will house a health center outpost. Each building has community lounges, kitchens, study spaces...places for staff and students to really build community and enhance the student experience. We have three collaboration spaces that look a lot like classrooms and multiple food options including a brand new all you can eat dining hall, a starbucks, and a convenience store.
Prescient System
All four buildings expected to be substantially complete mid-April 2023
Mechanical and Electrical System Rough-In
Contractors in progress on bottom floors and beginning work in floors that are structurally complete
Building Envelope
Weatherproofing of exterior in progress on several buildings; window installation started on Bldg 4.
Parking Garage
To be started mid-April
Prescient System
All four buildings expected to be substantially complete mid-April 2023
Mechanical and Electrical System Rough-In
Contractors in progress on bottom floors and beginning work in floors that are structurally complete
Building Envelope
Weatherproofing of exterior in progress on several buildings; window installation started on Bldg 4.
Parking Garage
To be started mid-April
Prescient System
All four buildings expected to be substantially complete mid-April 2023
Mechanical and Electrical System Rough-In
Contractors in progress on bottom floors and beginning work in floors that are structurally complete
Building Envelope
Weatherproofing of exterior in progress on several buildings; window installation started on Bldg 4.
Parking Garage
To be started mid-April
Prescient System
All four buildings expected to be substantially complete mid-April 2023
Mechanical and Electrical System Rough-In
Contractors in progress on bottom floors and beginning work in floors that are structurally complete
Building Envelope
Weatherproofing of exterior in progress on several buildings; window installation started on Bldg 4.
Parking Garage
To be started mid-April
Prescient System
All four buildings expected to be substantially complete mid-April 2023
Mechanical and Electrical System Rough-In
Contractors in progress on bottom floors and beginning work in floors that are structurally complete
Building Envelope
Weatherproofing of exterior in progress on several buildings; window installation started on Bldg 4.
Parking Garage
To be started mid-April
Prescient System
All four buildings expected to be substantially complete mid-April 2023
Mechanical and Electrical System Rough-In
Contractors in progress on bottom floors and beginning work in floors that are structurally complete
Building Envelope
Weatherproofing of exterior in progress on several buildings; window installation started on Bldg 4.
Parking Garage
To be started mid-April
Prescient System
All four buildings expected to be substantially complete mid-April 2023
Mechanical and Electrical System Rough-In
Contractors in progress on bottom floors and beginning work in floors that are structurally complete
Building Envelope
Weatherproofing of exterior in progress on several buildings; window installation started on Bldg 4.
Parking Garage
To be started mid-April