The document outlines a project to install two new pumps at the Mirfa Pumping Station Extension in the United Arab Emirates. The pumps will have a total capacity of 34 million imperial gallons per day and a head of 241 meters. They will supply a new DN1200 cast iron pipeline to Madinat Zayed. The project scope includes interfacing the new pumps with existing storage tanks at the Independent Water and Power Plant, constructing a new 33kV substation to power the pumps, and integrating the new control system with the existing supervisory control and data acquisition system. The project is scheduled to start on November 11, 2018 and be completed by July 31, 2023.
2. N-14673.2 MIRFA-C ADDITIONAL PUMPS GROUP TO SUPPLY DN1200 CS PIPELINE TO MADINAT ZAYED
2
2
Mirfa Pumping Station Extension – Installation of 2 New
Pumps, total capacity of 34 MIGD / head of 241m with 33 kV
Switchgear Building, Electrical Control Building and associated
works including the following: .
• Interface with IWPP – New Twin DN1400 CS pipeline to
interface with new storage tanks within IWPP.
• Power Requirements – New 33kV Substation and associated
equipment to supply power for the 2 New Pump Sets
• SCADA Integration – Integration of New Control System with
existing SCADA system.
Scope of work
Project Start Date: 11-11-2018
Expected Completion Date 31-07-2023
3. N-14673.2 MIRFA-C ADDITIONAL PUMPS GROUP TO SUPPLY DN1200 CS PIPELINE TO MADINAT ZAYED
3
3
EPH
ECB
IVC 01
WO 02
IVC 02