KING ABDULLAH SPORTS CITY
HEALTH SAFETY & ENVIRONMENT (HSE) DEPARTMENT

NEAR MISS REPORT
INCIDENT DETAILS: Lifting LED Wall screen on elevated level
Project: KASC
Date: 20/11/2013
Near Miss Description:

Time: 10:05AM

Location/Plant/Equipment:Level-4th floor

(Explain What Happened _ Use attachments if needed) Workers were lifting the

LED by using the electric winch .The LED screen failed due to the clamp was not properly fasten with
the LED. The height was around four meters.

ESTIMATE OF LOSS POTENTIAL

(What injuries or losses might have occurred) Waiting report

from engineer.

INJURIES: No injury
PROPERTY / EQUIPMENT/DAMAGE: Waiting report from engineer and QC-dept.
ENVIRONMENTAL DAMAGE: No.
Other:
Analysis: (why did it happen, List unsafe conditions, wrong procedure/Equipment or other factors)
Lack of supervision.

CORRECTIVE ACTIONS what must be done to prevent reoccurrence  List recommendation)
The workers should check the hooks are properly tight .
No worker should stay under the load during lifting.

Reported By:

Name/Title/ Badge: Mushfiq Ullah Khan, HSE Supervisor

Reviewed By:

Name/Title/Badge: Mohammd Tarique Hussain/HSE Manager

More Related Content

Near miss report

  • 1. KING ABDULLAH SPORTS CITY HEALTH SAFETY & ENVIRONMENT (HSE) DEPARTMENT NEAR MISS REPORT INCIDENT DETAILS: Lifting LED Wall screen on elevated level Project: KASC Date: 20/11/2013 Near Miss Description: Time: 10:05AM Location/Plant/Equipment:Level-4th floor (Explain What Happened _ Use attachments if needed) Workers were lifting the LED by using the electric winch .The LED screen failed due to the clamp was not properly fasten with the LED. The height was around four meters. ESTIMATE OF LOSS POTENTIAL (What injuries or losses might have occurred) Waiting report from engineer. INJURIES: No injury PROPERTY / EQUIPMENT/DAMAGE: Waiting report from engineer and QC-dept. ENVIRONMENTAL DAMAGE: No. Other: Analysis: (why did it happen, List unsafe conditions, wrong procedure/Equipment or other factors) Lack of supervision. CORRECTIVE ACTIONS what must be done to prevent reoccurrence List recommendation) The workers should check the hooks are properly tight . No worker should stay under the load during lifting. Reported By: Name/Title/ Badge: Mushfiq Ullah Khan, HSE Supervisor Reviewed By: Name/Title/Badge: Mohammd Tarique Hussain/HSE Manager