Nivelacion
- 1. |
NIVELACION CAMPUS “UAP”_-_SAN JUAQUIN
CRUCE DE PISTA
UAP FILIAL ICA
BM1= 100
30m
30m
30m
30m
30m
30m
30m
30m30m
Vista atrás
Vista atrás
Vista
adelante ..
Vista atrás
PISTA
- 2. |
OPERACIÓN DE LA LIBRETA D E CAMPO
pto d (+)vista
atrás
(-)vista
adelante
cota
BM2 _ 1.950 101.95 _ 100.00
a 30 _ 1.901 100.049
b 30 _ 1.643 100.307
c 30 _ 1.483 100.467
d 30 1.380 100.57
e 30 1.117 100.78
f 1.993 103.013 0.93 101.02
g 30 1.80 101.213
PTO d (+)vista
atrás
(-)vista
adelante
cota
BM1 _ 1.16 101.16 1.578 1000
1 punto
de cambio
1.292 100.886 1.566 99.594
2 1.24 100.404 1.722 99.164
3 1.235 100.006 1.633 98.771
4 1.308 99.694 1.62 98.386
5 1.183 99.326 1.551 98.143
6 1.141 99.221 1.25 98.08
- 3. |
h 30 1.492 101.521
i 30 1.399 101.614
j 30 1.450 103.29 1.173 101.84
p 30 1.374 101.916
q 30 1.23 102.06
27.20 0.926 102.364