際際滷

際際滷Share a Scribd company logo
Rain Garden/Bioretention Cell

                               LOW POINT IN A
                                SMALL WATERSHED
                                AREA - .37 ACRES
                               LITTLE IMPERVIOUS
                                SURFACE IN
                                WATERSHED
                               POORLY DRAINED
                               EXISTING CATCH
                                BASIN




            BEFORE


      Green Pilot Project 1
Rain Garden/Bioretention Cell

                               FOREBAY OF RIVER
                                STONE TO PREVENT
                                SEDIMENTATION
                               GRADE REQUIRED
                                BOULDERS TO
                                SHORE UP SLOPE




      DESIGN

      Green Pilot Project 1
Rain Garden/Bioretention Cell

                               DESIGNED TO
                                RETAIN AND SLOWLY
                                FILTER WATER
                               DESIGNED TO
                                ABSORB THE FIRST
                                FLUSH (1.2) OF ALL
                                STORM EVENTS




      DESIGN

      Green Pilot Project 1
Rain Garden/Bioretention Cell
TYPICAL CONSTRUCTION SEQUENCE
1. Install sediment control devices as shown on the plans.
2. Grade site to elevations shown on plan. Construct curb openings, and/or
   remove and replace existing concrete as specified on the plan. Measures
   should be taken to prohibit drainage from entering construction area. At the
   end of each workday, all excavations shall be protected by
   construction safety fencing or temporary backfill as needed.
3. Stabilize grading within Limit of Disturbance except for Bioretention Area
   itself.
4. Excavate bioretention area to proposed invert depth and scarify the existing
   soil surfaces, taking care not to compact existing grade.
5. Install underdrain system and observation wells, if specified
6. Backfill with planting soil as shown in the plans and detailed in the
   specifications, leaving space for the upper layer of mulch. (Overfilling is
   recommended to account for settlement.)
7. Presoak the soil prior to planting, to allow for settlement.
8. Plant vegetation specified in the planting plan for Bioretention Area.
9. Mulch and install erosion protection at entrance points.

                     Green Pilot Project 1
Rain Garden/Bioretention Cell

                                 Step 1
                                 SEDIMENT CONTROL




IN PROGRESS


         Green Pilot Project 1
Rain Garden/Bioretention Cell

                                 Step 2
                                 EXCAVATION/GRADING




IN PROGRESS



         Green Pilot Project 1
Rain Garden/Bioretention Cell
                               Step 3
                               FILTER FABRIC,
                               OBSERVATION WELLS




IN PROGRESS




       Green Pilot Project 1
Rain Garden/Bioretention Cell
                                  Step 4
                                  RIVER STONE FOREBAY
                                  IS IN PLACE, DRAIN
                                  LINES ARE INSTALLED.
                                  FIRST AGGREGATE
                                  LAYER IS BEING
                                  INSTALLED
                                  NOTE: THERE IS NO
                                  STORAGE LAYER IN THIS
                                  DESIGN.




IN PROGRESS



          Green Pilot Project 1
Rain Garden/Bioretention Cell
                               Step 5
                               CHOKER LAYER OF
                               AGGREGATE IS BEING
                               SPREAD. NOTICE THE
                               CARE TO KEEP
                               SEDIMENT OFF OF THE
                               AGGREGATE.




IN PROGRESS



       Green Pilot Project 1
Rain Garden/Bioretention Cell

                               Step 6
                               MIXING THE
                               AMENDMENT INTO
                               RESERVED TOPSOIL




IN PROGRESS




       Green Pilot Project 1
Rain Garden/Bioretention Cell

                              Step 7
                              PLANTED
                              MARCH/APRIL, 2008




      Green Pilot Project 1
Rain Garden/Bioretention Cell

                              MAY, 2008




      Green Pilot Project 1
Rain Garden/Bioretention Cell

                                    SEPT 23, 2009
                                    AFTER THE GREAT FLOOD!




NO STANDING WATER




                Green Pilot Project 1
Rain Garden/Bioretention Cell

                          JUNE 14, 2010




      Green Pilot Project 1

More Related Content

Oakland City Rain Garden

  • 1. Rain Garden/Bioretention Cell LOW POINT IN A SMALL WATERSHED AREA - .37 ACRES LITTLE IMPERVIOUS SURFACE IN WATERSHED POORLY DRAINED EXISTING CATCH BASIN BEFORE Green Pilot Project 1
  • 2. Rain Garden/Bioretention Cell FOREBAY OF RIVER STONE TO PREVENT SEDIMENTATION GRADE REQUIRED BOULDERS TO SHORE UP SLOPE DESIGN Green Pilot Project 1
  • 3. Rain Garden/Bioretention Cell DESIGNED TO RETAIN AND SLOWLY FILTER WATER DESIGNED TO ABSORB THE FIRST FLUSH (1.2) OF ALL STORM EVENTS DESIGN Green Pilot Project 1
  • 4. Rain Garden/Bioretention Cell TYPICAL CONSTRUCTION SEQUENCE 1. Install sediment control devices as shown on the plans. 2. Grade site to elevations shown on plan. Construct curb openings, and/or remove and replace existing concrete as specified on the plan. Measures should be taken to prohibit drainage from entering construction area. At the end of each workday, all excavations shall be protected by construction safety fencing or temporary backfill as needed. 3. Stabilize grading within Limit of Disturbance except for Bioretention Area itself. 4. Excavate bioretention area to proposed invert depth and scarify the existing soil surfaces, taking care not to compact existing grade. 5. Install underdrain system and observation wells, if specified 6. Backfill with planting soil as shown in the plans and detailed in the specifications, leaving space for the upper layer of mulch. (Overfilling is recommended to account for settlement.) 7. Presoak the soil prior to planting, to allow for settlement. 8. Plant vegetation specified in the planting plan for Bioretention Area. 9. Mulch and install erosion protection at entrance points. Green Pilot Project 1
  • 5. Rain Garden/Bioretention Cell Step 1 SEDIMENT CONTROL IN PROGRESS Green Pilot Project 1
  • 6. Rain Garden/Bioretention Cell Step 2 EXCAVATION/GRADING IN PROGRESS Green Pilot Project 1
  • 7. Rain Garden/Bioretention Cell Step 3 FILTER FABRIC, OBSERVATION WELLS IN PROGRESS Green Pilot Project 1
  • 8. Rain Garden/Bioretention Cell Step 4 RIVER STONE FOREBAY IS IN PLACE, DRAIN LINES ARE INSTALLED. FIRST AGGREGATE LAYER IS BEING INSTALLED NOTE: THERE IS NO STORAGE LAYER IN THIS DESIGN. IN PROGRESS Green Pilot Project 1
  • 9. Rain Garden/Bioretention Cell Step 5 CHOKER LAYER OF AGGREGATE IS BEING SPREAD. NOTICE THE CARE TO KEEP SEDIMENT OFF OF THE AGGREGATE. IN PROGRESS Green Pilot Project 1
  • 10. Rain Garden/Bioretention Cell Step 6 MIXING THE AMENDMENT INTO RESERVED TOPSOIL IN PROGRESS Green Pilot Project 1
  • 11. Rain Garden/Bioretention Cell Step 7 PLANTED MARCH/APRIL, 2008 Green Pilot Project 1
  • 12. Rain Garden/Bioretention Cell MAY, 2008 Green Pilot Project 1
  • 13. Rain Garden/Bioretention Cell SEPT 23, 2009 AFTER THE GREAT FLOOD! NO STANDING WATER Green Pilot Project 1
  • 14. Rain Garden/Bioretention Cell JUNE 14, 2010 Green Pilot Project 1