ºÝºÝߣ

ºÝºÝߣShare a Scribd company logo
OPERATION RESEARCH

***PRESENTED BY***
Jacob John Panicker
PRESENTATION OUTLINE
•
•
•
•
•
•

Project time cost trade off
Project crashing
Time cost trade off procedure
Resource allocation
Resource leveling
Resource smoothing
PROJECT TIME COST TRADE OFF

 Project time can be reduced by crashing
 Normal time reduced, budget increase
 Use additional resource to complete on time
PROJECT CRASHING
Crashing number of activities to reduce
duration of project
Cost increases more quickly when time is
reduced
Relationship between normal time and cost
and crash time and time is linear
Operation research
TIME COST TRADE OFF PROCEDURE
1. Determine normal project completion time
and associated critical path
2. Identify critical activities and compute cost
slope
cost slope= crash cost - normal cost
crash time - normal time
3. Identify and crash an activity time on critical
path
4. If the critical path is still critical, return to
step 3
5. Terminate the procedure after each critical
activity crashed to its lower possible time
RESOURCE ALLOCATION
Resources are:men, money, material, machinery etc..,
Network analysis PERT/CPM is carried out
using unlimited resources
Resources may not be uniform throughout the
project
RESOURCE LEVELLING
 Stabilize rate of resource utilization without
changing project duration
 Total float of non-critical activity
 Shift non-critical activity between earliest start
time and latest allowable time can lower
maximum resource requirement
i. Total float=free float can be scheduled between
earliest start and latest times
ii. Total float>free float starting time can be
delayed
RESOURCE SMOOTHING
Reduce peak demand for resources and
reallocate them and shortest duration
I. Calculate earliest start and latest finish
times, draw time scaled network
II. Draw resource histogram
III. Shift the start time of those non-critical
activities
CONCLUSION
I conclude by saying that to reduce the
time duration the cost of the project will be
increased. The crash point is the point beyond
which the time cannot be reduced nor the
cost can be increased.
THANK YOU

More Related Content

Operation research

  • 2. PRESENTATION OUTLINE • • • • • • Project time cost trade off Project crashing Time cost trade off procedure Resource allocation Resource leveling Resource smoothing
  • 3. PROJECT TIME COST TRADE OFF  Project time can be reduced by crashing  Normal time reduced, budget increase  Use additional resource to complete on time
  • 4. PROJECT CRASHING Crashing number of activities to reduce duration of project Cost increases more quickly when time is reduced Relationship between normal time and cost and crash time and time is linear
  • 6. TIME COST TRADE OFF PROCEDURE 1. Determine normal project completion time and associated critical path 2. Identify critical activities and compute cost slope cost slope= crash cost - normal cost crash time - normal time
  • 7. 3. Identify and crash an activity time on critical path 4. If the critical path is still critical, return to step 3 5. Terminate the procedure after each critical activity crashed to its lower possible time
  • 8. RESOURCE ALLOCATION Resources are:men, money, material, machinery etc.., Network analysis PERT/CPM is carried out using unlimited resources Resources may not be uniform throughout the project
  • 9. RESOURCE LEVELLING  Stabilize rate of resource utilization without changing project duration  Total float of non-critical activity  Shift non-critical activity between earliest start time and latest allowable time can lower maximum resource requirement i. Total float=free float can be scheduled between earliest start and latest times ii. Total float>free float starting time can be delayed
  • 10. RESOURCE SMOOTHING Reduce peak demand for resources and reallocate them and shortest duration I. Calculate earliest start and latest finish times, draw time scaled network II. Draw resource histogram III. Shift the start time of those non-critical activities
  • 11. CONCLUSION I conclude by saying that to reduce the time duration the cost of the project will be increased. The crash point is the point beyond which the time cannot be reduced nor the cost can be increased.